Contact your Parish Council


Policy and Resources Committee

24 October 2018

 

100% Business Rates Retention Pilot - Update

 

Final Decision-Maker

Policy and Resources Committee

Lead Head of Service/Lead Director

Mark Green, Director of Finance and Business Improvement

Lead Officer and Report Author

Mark Green, Director of Finance and Business Improvement

Classification

Public

 

Wards affected

All

 

 

Executive Summary

The Council is due to receive additional business rates income, initially estimated as £640,000, for one year only in 2018/19 as a result of its participation in the Kent and Medway 100% Business Rates Retention pilot.  Policy and Resources Committee agreed 13 projects for funding from this additional income at its meeting on 28 March 2018.  This report describes progress with these projects to the end of quarter 2 of 2018/19.   

 

This report makes the following recommendations to this Committee:

That progress with the Business Rates Retention pilot projects be noted.

 

 

Timetable

Meeting

Date

Policy and Resources Committee

24 October 2018

Further progress reports will be submitted to the Committee each quarter.

 



100% Business Rates Retention Pilot - Update

 

 

INTRODUCTION AND BACKGROUND

 

1.1           Kent County Council, Medway Council, and all twelve districts within the Kent county area successfully applied last year to become a 100% Business Rates Retention pilot.  This means that the Government will allow 100% of business rates growth to be retained within the local area.  The consequent financial gain across the whole area was estimated to be £24.7 million in 2018/19, to be split 70:30 between a Financial Sustainability Fund and a Housing and Commercial Growth Fund.

 

Financial Sustainability Fund

 

1.2     Maidstone’s share of the Financial Sustainability Fund (FSF) was estimated as being £640,000.  Officers developed proposals for a number of discrete projects which would meet the criteria for the FSF and Policy and Resources Committee agreed thirteen projects at its meeting on 28 March, as follows:

 

 

£000

Tranche 1

 

Housing First and Rough Sleepers

80

Regeneration Opportunity Areas

80

Property Asset Review

55

Members' Community Grant

60

 

 

Tranche 2

 

Predictive analytics and preventing homelessness

80

Housing Delivery Partnership

40

Go Green, Go Wild

90

Maidstone Business capital of Kent – marketing strategy

35

Staplehurst Village Centre Masterplan

15

 

 

Tranche 3

 

Maidstone Housing Design Guide

40

Electric vehicle charging points

20

Bus Station improvement - feasibility study

10

Data analytics for Inclusive Growth

35

 

 

TOTAL

640

 

1.3     Funding for each tranche is released as soon as it is considered prudent to do so.  Current projections indicate that at least £640,000 will be generated from the Pilot so all three tranches of funding have been released.

1.4     Progress to date is set out in Appendix 1.  Work has commenced on six of the thirteen projects.  In total, £246,000 has been spent or committed.

Housing and Commercial Growth Fund

1.5     The Business Rates Retention Pilot bid specified that the Housing and Commercial Growth Fund would be allocated between three clusters of authorities, representing East, North and West Kent.  Decisions about use of the fund are made using the established leaders’ board arrangements in the respective areas.  North Kent leaders (Dartford, Gravesham, Medway, Swale and Maidstone) have met and considered a prospectus setting out proposals for use of the Fund.  This is currently awaiting formal sign-off.

 

2.        AVAILABLE OPTIONS

 

2.1     This report is to note only.

 

 

3.       RISKS

3.1     As with any projects, the Business Rates Retention Pilot projects could fail to be delivered, or could be delivered but exceed their budget allocations.  This risk is mitigated in several ways.  There is a strong project management culture in the Council.  Monitoring arrangements have been put in place for all the projects, to ensure that they deliver within budget and to the agreed timetable.  Finally, post project reviews will be carried out to evaluate the outcomes and to derive any lessons learned from the projects.

           

 

 

 

4.       CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK

 

4.1     Policy and Resources Committee received an initial report on Business Rates Retention pilot projects at its meeting on 24 January 2018.  A draft set of projects was included within the budget proposals considered by the Committee at its meeting on 14 February 2018.  The Committee requested that further consideration be given to the priority and scope of the projects.  An informal briefing was held on 8 March, to which all councillors were invited, at which project sponsors described their projects and answered questions on them.  The Committee then formally agreed thirteen projects at its meeting on 28 March.

 

 

 

 

5.       NEXT STEPS: COMMUNICATION AND IMPLEMENTATION OF THE DECISION

 

5.1     Progress with the pilot projects is being reported to Policy and Resources Committee on a quarterly basis during the course of the year.

 

 

 

6.       CROSS-CUTTING ISSUES AND IMPLICATIONS

 

 

Issue

Implications

Sign-off

Impact on Corporate Priorities

The projects described in this report support the Council’s strategic plan objectives.

Section 151 Officer & Finance Team

Risk Management

See section 3 above.

Section 151 Officer & Finance Team

Financial

Set out in report.

Section 151 Officer & Finance Team

Staffing

None.

Section 151 Officer & Finance Team

Legal

The Council has a statutory obligation to set a balanced budget.  Allocation of resources in the way set out in this report supports achievement of a balanced budget.

Legal Team

Privacy and Data Protection

None. 

Section 151 Officer & Finance Team

Equalities

Where appropriate, Equalities Impact Assessments will be carried out for specific projects.

Section 151 Officer & Finance Team

Crime and Disorder

None.

Section 151 Officer & Finance Team

Procurement

Procurement of services in the course of delivering the projects will be in accordance with the procurement provisions within the Council’s constitution.

Section 151 Officer & Finance Team

 

 

 

7.        REPORT APPENDICES

 

The following documents are to be published with this report and form part of the report:

·         Appendix 1: Project updates.

 

 

8.        BACKGROUND PAPERS

 

There are no background papers.