Subject: Highway Works Programme 2011/12

To:                              Maidstone Joint Transportation Board

 

By:                              KCC Highways, Transportation & Waste

 

Date:                           10th July 2019

 

Subject:                      Highway Forward Works Programme – 2019/20 onwards

 

Classification:           Information Only

 

 

Summary: This report updates Members on the identified schemes approved for construction

 

 

1. Introduction

 

This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.

 

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year.  For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.

 

This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

 

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

           

Drainage Repairs & Improvements – see Appendix B

 

Street Lighting – see Appendix C

 

Transportation and Safety Schemes see Appendix D

  • Casualty Reduction Measures
  • Externally funded schemes
  • Local Growth Fund

 

Developer Funded Works – see Appendix E

 

Bridge Works – see Appendix F

 

Traffic Systems – see Appendix G

 

Combined Member Fund – see Appendix H

 

Conclusion

 

1.    This report is for Members’ information.

 

Contact Officers:

 

The following contact officers can be contacted on 03000 418181

 

Kirstie Williams                                   Highway Manager Mid Kent

Susan Laporte                                     Maidstone District Manager

Alan Casson                                        Strategic Asset Manager                   

Earl Bourner                                        Drainage & Structures Asset Manager

Sue Kinsella                                        Street Light Asset Manager

Toby Butler                                         Traffic & Network Solutions Asset Manager

Jamie Hare                                         Development Agreements Manager

Jamie Watson                                     Schemes Programme Manager

                                   


Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

 

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

 

 

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name

Parish

Extent of Works

Current Status

A274 Maidstone Road

Langley

From the B2163 Upper Street to Warmlake Road

Programmed 21st November 2019

A20 King Street

 Maidstone

Watt Tyler Way and Wyke Manor Road

 

Programmed 3rd October 2019

Linton Road

Loose

From Lancet Lane to Rosemount Close

 

Programmed 21st October 2019

Forstal Road

Aylesford

From bridge deck over motorway to Beddow Way

 

Programmed 8th November 2019

Sheal’s Crescent

 Maidstone

From Loose Road (through Hayle Road, College Road, Mill Street) to Bishops Way

 

To be programmed late 2019/early 2020

A20/A26 Rocky Hill

Maidstone

Maidstone Gyratory to Terrace Road

 

To be programmed early 2020

 

Footway Improvement - Contact Officer Mr Neil Tree

Road Name

Parish

Extent and Description of Works

Current Status

Mote Road

Maidstone

From the junction with Square Hill Road to Willow Way (Northern side)

(Footway Reconstruction)

 

Completed

 

Winifred Road

Bearsted

Entire length

(Footway Reconstruction).

 

On site

 

Royston Road

Bearsted

Entire length

(Footway Reconstruction).

 

On site

 

Rosemary Road

Bearsted

Entire length

(Footway Reconstruction).

 

On site.

 

Trenton Close

Allington

Entire length

(Footway Reconstruction).

 

To be designed and programmed.

 

Beverley Road

Barming

Entire length

(Footway Protection)

 

Designed and programmed for week commencing

24th June 2019

 

Egremont Road

Bearsted

Entire length

(Footway Protection)

 

Designed and programmed for week commencing

8th July 2019

 

Roseholme

Maidstone

Entire length

(Footway Protection)

 

Designed and programmed for week commencing

24th June 2019

 

Wesley Close

Barming

Entire length

(Footway Protection)

 

Designed and programmed for week commencing

1th July 2019

 

 

Broomshaw Road

 

Barming

Entire length

(Footway Protection)

 

Designed and programmed for week commencing

1th July 2019

 

Surface Treatments – Contact Officer Mr Jonathan Dean

Micro Surfacing

Road Name

Parish

Extent and Description of Works

Current Status

GLEBE LANE

 

 

Maidstone

(Barming)

Tonbridge Road to Farleigh Lane

 

 

Programmed for 9th August 2019 for 2 days

GATLAND LANE

 

Maidstone

(Barming)

Farleigh Lane to Fant Lane

 

 

Programmed for 10th August 2019 for 3 days

FAVERSHAM ROAD

 

Lenham

 

 

Whole Road

 

 

Programmed for 10th July 2019 for 3 days

WEST STREET

 

Lenham

Faversham Road to Flint Lane (West Street Lenham

 

 

Programmed for 10th July 2019 for 1 day

MARDEN ROAD

 

Marden

Battle Lane to "Mountain Farmhouse"

 

 

Programmed for 17th July 2019 for 3 days

MAIDSTONE ROAD

 

Marden

"Hartridge" to 150m north of j/w Milebush Lane (Kiln Farm)

 

 

Programmed for 18th July 2019 for 3 days

HEADCORN ROAD

 

Platts Heath / Lenham

Chain Gate Road to Station Approach, Lenham

 

 

Programmed for 12th July 2019 for 4 days

HEADCORN ROAD

 

Sandway

Headcorn Road to Sandway Road

 

 

Programmed for 12th July 2019 for 2 days

SANDWAY ROAD

 

Sandway

Headcorn Road to "Little Biggen"

 

 

Programmed for 12th July 2019 for 2 days

GALLANTS LANE

 

East Farleigh

Lower Road to Heath Road

 

 

Programmed for 23rd July 2019 for 3 days

HUNTON ROAD

 

Marden

River Beult bridge (Clapper Green) to "Reed Court Cottages"

 

 

Programmed for 22nd July 2019 for 2 days

OLD TREE LANE/CLIFF HILL

 

Boughton Monchelsea

From The Quarries to Combe Bank House -

To Be Programmed

SANDWAY ROAD

 

Platts Heath

Around "Sandway Triangle"

 

Programmed for 12th July 2019 for 2 days

KENWARD ROAD

 

Yalding

Hunt Street to Yalding Hill

 

Programmed for 5th August 2019 for 3 days

BOW ROAD

Wateringbury

Corner after bridge to Hunt Street

Programmed for 7th August 2019 for 2 days

SMITHS HILL

 

Yalding

 

To Be Confirmed

 

 

Programmed for 8th August 2019 for 2 days

Surface Treatments – Contact Officer Mr Jonathan Dean

Surface Dressing

Road Name

Parish

Extent and Description of Works

Current Status

A20 ASHFORD ROAD

Hollingbourne

Near j/w Old Mill Road to j/w Roundwell

 

 

Programmed for August 2019

A20 ASHFORD ROAD

 

Hollingbourne

Old Ashford Road to Northdown Close

 

 

Programmed for August 2019

CHARLTON LANE

 

East Sutton

From Chartway Street to Church Lane

 

Programmed for August 2019

 

 


Appendix B – Drainage Repairs & Improvements

 

Drainage Repairs & Improvements - Contact Officer Earl Bourner 

Road Name

Parish

Description of Works

Current Status

Green Lane

Chart Sutton

Repair the culvert and edge of road/ verge/ ditch.

Awaiting Start Date

Tufa Close

Walderslade

Relocation of soakaway

Completed

Smith’s Hill

West Farleigh

Investigation works

Cleansing works complete further investigation required at Shingle Barn Lane.

The Broadway

Maidstone

Surface water system surcharging

Chasing Southern Water following our Investigations that there is an issue with their main system.

Dray Corner Road

Headcorn

Investigation works required

Due to commence 28/6/19

Dunn Street

Bredhurst

Repair broken pipe

Awaiting start date

Fisher Street

Maidstone

Reports of broken pipes and repairs to be carried out

Awaiting start date

Lower Road

East Farleigh

Repair broken pipes

Awaiting start date

West Street

Hunton

Repair broken pipes

Awaiting start date

 

 


Appendix C – Street Lighting

 

Structural testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.

 

 

Street Lighting Column Replacement – Contact Officer Sue Kinsella

 

Road Name

Column

Parish

Description of Works

Status

Warwick Place

KWAI502

Maidstone

Lit Sign Replacement

Completion by September 2019

Warwick Place

KWAI501

Maidstone

Lit Sign replacement

Completion by September 2019

Brishing Lane

KBFE010

Maidstone

Column replacement

Completion by September 2019

High Street

KHDO053

Staplehurst

Column replacement

Completion by September 2019

Milton Street

KMCW503

Maidstone

Lit Sign replacement

Completion by September 2019

Whitmore Street

KWCR501

Maidstone

Lit Sign replacement

Completion by September 2019

Station Road

KSFA029

Staplehurst

Column replacement

Completion by September 2019

Castle Dene

KCAO002

Maidstone

Column Replacement

Completion by September 2019

Impton Lane

KIAC001

Boxley

Column Replacement

Completion by September 2019

Maynards

KMBY002

Marden

Column Replacement

Completion by September 2019

Egerton Road

KEAQ003

Ringlestone

Column Replacement

Completion by September 2019

King Street

KKAM009

Maidstone

Column Replacement

Completion by September 2019

Woodlands

KXEF107

Boxley

Column Replacement

Completion by September 2019

 

 

 

 

Appendix D – Transportation and Safety Schemes

 

Casualty Reduction Measures

 

The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety).  Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status correct as of 24/06/2019.

 

Location

Parish

Description of Works

Lead officer

Current Status

Great Danes Roundabout

Hollingbourne

Signing and road marking improvements

Jennie Watson

All works due for completion June 2019

Mill Street/Palace Avenue

Maidstone

Lining refreshing

Jennie Watson

Works partially completed in October 2018 – Yellow box markings completed – Contractor to return to refresh white lining

A20 Ashford Road, Lenham

Lenham

Scheme to make changes to junction

Jennie Watson

Additional works to be carried out 10-12 July

Springfield Roundabout - A229 Royal Engineers Road

Maidstone

Signing and road marking improvements

Paul Leary

 

At design stage – scheme to be progressed this financial year

St Faiths Street/ Fairmeadow

Maidstone

Signing and road marking improvements

Jennie Watson

At design stage – scheme to be progressed this financial year

A229 Lower Stone Street/ Knightrider Street

Maidstone

Introduction of red-light camera

Bob Westamacott

At design stage – scheme to be progressed this financial year

Boxley Road/Sandling Lane, roundabout

Maidstone

Signing and road marking improvements

Bob Westamacott

At design stage – scheme to be progressed this financial year

A20 Ashford Road/M20 Slip

Hollingbourne

Signing and road marking improvements

Jennie Watson

At design stage – scheme to be progressed this financial year

 

Externally Funded Schemes

 

The Schemes Planning & Delivery team is implementing schemes within the borough of Gravesham funded by external corporations whilst still meeting KCC’s strategic targets with the road network.

 

Location

Parish

Description of Works

Lead officer

Current Status

East Farleigh Bridge

East Farleigh

Upgrade of signing and lining for bridge width restriction

Paul Leary

Works completed May 2019.  Minor snagging items to be carried out

Mote Park Cycleway (Phase 1)

Maidstone

Upgrade of cycle route

Paul Leary

Works completed May 2019.  Minor snagging items to be carried out.  

Mote Park Cycleway

(Phase 2)

Maidstone

Signing and road marking improvements between Chancery Lane and Maidstone House

Paul Leary

At design stage – Current handover to contactor programmed for end August 2019

 

Local Growth Fund

 

Local Growth Fund programme update for Maidstone Borough  

 

 

The Department for Transport (DfT) added £100m to the Local Growth Fund (LGF) pot in order to fund Local Sustainable Transport Fund Style schemes.  KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion.  The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.

 

The schemes aim to:

 

·         improve access to employment and services

·         reduce the need to travel by the private car

·         enhance pedestrian, cycle and public transport facilities

·         improve sustainable transport connections 

 

The following schemes have been submitted as part of the successful Kent Thameside/West Kent (delete as applicable) LSTF this financial year.

 

 

Scheme

Status

MAIDSTONE EAST STATION IMPROVEMENTS

Following the discovery of Asbestos at the Maidstone East Station site Network Rail concluded that the current contractor should stand down and an Asbestos and demolition specialist appointed due to the timelines given by the previous contractor. This has resulted in the existing scaffolding being removed and replaced by the new contractor Rhodar. The new scaffolding will be in place by end July. The completion date for the overall programme will remain unknown until the scaffolding and demolition is clear and the programmes can be aligned. Any public enquiries are being dealt with by Network Rail. Additional KSIP funding has now been confirmed to progress further highway improvements and walking and cycling connections to the station.  

 


Appendix E – Developer Funded Works

 

Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers for sites Jamie Hare, Aaron Divall, Steven Noad, (Sarah Parris), Andy Padgham, Steve A Stickels

 

Scheme Name

File Ref.

Officer

Parish

Description of Works

Current Status

BP Tudor Service Station, London Road

MA003072

CV

Allington

Alterations to existing access

Pedestrian crossing point and additional signage still to do.

Bell Farm, North Street

MA003098

SN

Barming

New accesses to split sites, shared surface and new crossing point

Agreement signed, highway works commenced, due to complete June.

Cross Keys

MA003100

JH

Bearsted

New access, crossing point and parking area

Agreement signed

Barty Farm, Roundwell,

MA003278

AD

Bearsted

New Bellmouth and Lining works

Agreement Signed

Bicknor Road

MA003256

AP

Bicknor

Formation of hard surfaced passing places

Awaiting technical approval

Heath Road/Church Street

MA003111

CV (SP)

Boughton Monchelsea

New access, footway works, yellow lines and crossing upgrade

High Friction surfacing remedials scheduled June ‘19.

Hubbards Lane

MA003084

CV

Boughton Monchelsea

Two accesses to minor developments

Works completed on both accesses, pedestrian crossing point to add


Lyewood Farm, Green Lane

MA3247

MA3248

AP

Boughton Monchelsea

New housing development and access

Awaiting technical approval

Goya Development, St Michaels Close, Aylesford

MA003123

CV

(SP)

Boxley

New access and footway work to new commercial properties

Works complete except for new gulley.

Maidstone Studios, New Cut Road

MA003110

AD (SP)

Boxley

Zebra crossing and pedestrian crossing points

Defective High Friction surfacing scheduled for replacement June ‘19

St Michaels Close, Aylesford

MA003103

CV (SP)

Boxley

Waitrose car park, new access

Final remedials due.

Forstal Lane

Ma003141

AP (SP)

Coxheath

Widening of road and new footpath with access to new development

Awaiting Technical Approval – In discussion with developer

Heath Road

(North side)

MA003063

CV

Coxheath

New access and Footway work

Works completed and in maintenance

Land north of Heath Road Phase 2

MA3257

AP

Coxheath

Access to new development

Awaiting technical approval

Linden Farm, Stockett Lane

MA003107

 

AP (SP)

Coxheath

Access to new development and footway link to community hall

Access & footway completed further 2 accesses to restore to footway near completion of development.

Gatland House, Gatland Lane

MA003081

 

CV

Fant ward

Parking restrictions, signage, road markings and tactile crossings for new school

Works completed, Remedials to do

Bell Farm, Ashford Road

MA003094

 

 

CV

Harrietsham

Realignment of Church Road to form new access onto A20. New footway along A20

Works completed and in maintenance.

Mayfield Nursery, Ashford Road

MA003135

CV (SP)

Harrietsham

New access and alterations to existing Highway to adjoin upcoming Scheme Works

Works ongoing on site currently in conjunction with Harrietsham improvement scheme

Forge Meadows

MA3253

AP

Headcorn

Access to 2 new properties and vehicle crossovers to existing properties

Awaiting technical approval

Grigg Lane & Wheeler Street

MA3250

SAS

Headcorn

Access to Gibbs Farm development and zebra crossing on Wheeler St

Awaiting technical approval

Grigg Lane, Lenham Road,

 

MA003050

CV

Headcorn

Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane

New accesses Grigg Lane and Lenham Road in place, New footway Grigg Lane completed

Kings Road/Millbank

MA3262

AP

Headcorn

Signalised crossroads (linked to Ulcombe Road MA3150)

Awaiting technical approval

Lenham Road (North side)

MA003062

CV

Headcorn

New Footway to site and extend speed limit boundary

Works completed and in Maintenance

Lenham Road (South side)

MA003057

CV

Headcorn

New footway

Agreement prepared

Oak Lane and Wheeler Street

MA003048

CV

Headcorn

New footway plus junction improvements

Works completed and in maintenance

Ulcombe Road

MA003150

AP (SP)

Headcorn

Access to new development

Accesses both in, awaiting street lighting agreement and TRO. Technical Approval in progress.

Wheeler Street, Headcorn

MA003137

SAS

Headcorn

2 new accesses - off Wheeler Street and Kingsland Grove

Technical Approval given awaiting fees and signed agreement before works commence.

Eyhorne Street

MA3198

AP

Hollingbourne

New access to development

Awaiting technical approval

Ledian Farm

MA003086

JH

Leeds

Proposed new access to development site at Ledian Farm

Works completed

8 Faversham Road

MA003032

CV

Lenham

New access

In maintenance, streetlight to replace

Old Ashford Road

MA003018

CV

Lenham

New footway plus access

Approaching end of maintenance, bus stop location to amend.

The Paddocks, Ashford Road (Grove House, Old Ashford Road)

MA3114

CV

Lenham

New access, speed reduction to 50mph and footway link to Faversham Road

Revised to include traffic island on A20. TRO applied for. Works sched for late summer.

Westwood Park, Ham Lane

MA003305

AP

Lenham

Main and emergency accesses to new housing development

Awaiting technical approval

531 Tonbridge Road

MA003045

CV

Maidstone

Service layby for new retail unit

In maintenance

Bicknor Green, Gore Court Road

MA003053

 

AD

Maidstone

Change of road priorities and widening / upgrading

Works mostly complete

Hartnup Street

MA003138

CV

(SP)

Maidstone

New Access

 Works complete now in                  maintenance.

Heath Road, Coxheath

MA003134

CV (SP)

Maidstone

New access and new footway

Technical Approval given. Currently going through legal.

Hermitage Lane, (opp. Maidstone Hospital)

MA003060

 

JH

Maidstone

New Traffic signal junction

In maintenance period


Hermitage Lane/ Howard Drive

MA003070

 

AD

Maidstone

New access for development (opposite the quarry entrance)

Works complete

Howard Drive

MA003303

 

AD

Maidstone

Junction works to facilitate Bus Gateway entrance to Croudace site

Agreement Signed

Imperial Park

MA003017

 

AD

Maidstone

New right turn lane and bellmouth junction, plus associated footway works

Adopted

Maidstone School of Science, New Cut Road

MA003197

 

AD (SP)

Maidstone

New access to School and New roundabout and alterations to Highway

Temp access granted and works commenced off the Highway.  Looking to carry out works from May 2019. Technical Approval.

McDonalds drive-through, Hart Street

MA003013

CV

Maidstone

New access, improvements to Hart Street.

Approaching the end of maintenance - remedial works completion scheduled June ‘19

Oakapple Lane/ Hermitage Lane

MA003046

AD

Maidstone

New bellmouth junction and associated ancillary works for new development including new bus stop

Main works complete, remedial works awaited

Royal Engineers Road

MA003127

CV (SP)

Maidstone

New footpaths to development

Awaiting Structures Approval

The Poplars, Ashford Road

MA3254

AP

Maidstone

Access to new development

Awaiting technical approval

Wallis Avenue Phase 3, Parkwood

MA003085

CV

Maidstone

Some stopping up of highway and redevelopment of old carpark and shops area opp. Longshaw Road

Works complete

Week St/Gabriel’s Hill

MA003120

SS

Maidstone

Town Centre Public Realm improvements

Completed and inspected for maintenance

Albion Road, Marden

MA003132

CV (SP)

Marden

New Access and development

S278 works part completed.

Goudhurst Road, Church Green (Plain Road development)

MA3118

CV

Marden

Install Zebra crossing near rail station.

Completed – in Maintenance

Goudhurst Road/West End (Plain Road Development)

MA3118

CV

Marden

Refurbish Zebra crossing outside school and Bus Borders to add by Library stops.

Work completed and in Maintenance

Howland Road

 

MA003088

 

SN

Marden

New development access

Agreement signed; highway works part complete

MAP Depot, Goudhurst Road

MA003012

CV

Marden

New bellmouth junction and footway

Works in maintenance. Remedial works near completed and interactive speed sign awaiting installation

Napoleon Drive and Plain Road

MA003079

CV

Marden

New access on each road for new housing development

New accesses in place. Provision made for new bus waiting area outside site on Plain Road.

Spencers Field, Goudhurst Road

MA003151

CV (SP)

Marden

Access to new development (via the Parsonage)

Awaiting Technical Approval

The Parsonage, Goudhurst Road

MA003066

MA003067

CV

Marden

New access and associated upgrade works

Access substantially completed, village gateway to be agreed

Bell Lane

MA003030

CV

Staplehurst

Upgrade of existing access for new development

Due for adoption.

Fishers Farm (East) Headcorn Road (Redrow)

MA3106

CV (SP)

Staplehurst

Realignment and new access at Headcorn Road/Pile Lane junction

Realignment complete and Pile Lane open

Fishers Farm (West), Headcorn Road (Bovis)

MA3037

SAS (SP)

Staplehurst

New access onto Headcorn Road

Access in place.

Hen and Duckhurst Farm, Marden Road

MA003109

CV

Staplehurst

New Roundabout for development access

Works on highway almost completed. HFS delayed by utility works.

Oliver Road Staplehurst

MA003019

CV

Staplehurst

Ped crossing to Marden Road, junction markings and bus boarders

Works completed

Woodford Park

MA003099

CV (SP)

Staplehurst

New access for 9 dwellings

Works completed and on to maintenance.

Appleacres, Maidstone Road

MA003152

CV (SP)

Sutton Valence

Access to new development and footway works

Awaiting Technical Approval

The Oaks, Maidstone Road

MA003078

CV

Sutton Valence

Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing.

Works complete

Valdene Industrial Estate

MA003054

CV

Sutton Valence

Upgrade of existing bellmouth and extension to f/w

Footway works carried out, access still to do.

Cripple Street Maidstone

MA003093

CV

Tovil

New access to development, widening and footway works

Due for adoption – remedials due

Site opposite cottages 129-147 Dean Street/Farleigh Hill

MA003007

CV

Tovil

New access speed limit relocation, new footway and bus stop provision

Works completed and in maintenance

Tovil Green Lane

MA003095

CV

Tovil

New Footway and crossing point to side of site

Remedials completed – in maintenance

Hampstead Lane

MA3101

(SP)

Yalding

Relocate access to new development at old depot adj. station. Minor footway works

Awaiting snagging works to be completed.

Vicarage Road

MA003121

(SP)

Yalding

New access to development and speed restraints on existing Highway

Technical Approval Granted

 

 

 

 

Developer Funded Works (Section 106 Works)

 

File Ref.

Road Name

Parish

Description of Works

Current Status

18/19-S106-MA-486

A20 Ashford Road

Harrietsham

Village improvement works: 2 phase approach as not all of the S106 developer contributions have been collected. A final contribution of £171,500 is due from Bellway Homes in a couple of years pending the rate of their build and occupancy.

Phase 1 which consisted of narrowing the carriageway, widening footways to allow shared footway/cycleway, altering the controlled crossing, provision of central islands and changes to the speed limits and associated signing and lining.

Phase 2 will include relocating street lighting columns to better suit the new road layout and to extend the lighting to include all of the 30mph limit. Resurfacing of the carriageway to hide the old white lining and then new lining to the recently installed layout.

It is likely that there will not be sufficient S106 funds to cover all of Phase 2, however KCC is investigating final costs for phase 1, what the estimated costs for phase 2 will be and will then investigate how any funding gap can be dealt with to allow the second phase to be delivered without delay. Bellway Homes have offered to pay early the S106 contribution as long as they do not have to pay the index link which amounts to about £12,500 if KCC/Maidstone BC accepted the offer now.

Phase 1 Works completed in June 2019. KCC investigating how phase 2 can be brought forward as there is a potential funding gap and whether to collect the remaining S106 contribution from Bellway Homes now less the indexation.

18/19-S106-MA-819

Linton Crossroads

Linton/Loose

Junction/signal upgrade

Finalising designs however the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. It is hoped that a public consultation can be undertaken around October/November with implementation in 2020 pending all land, environmental and funding issues being resolved.

 

 

 

 

 

 

 

Appendix F – Bridge Works

 

Bridge Works – Contact Officer Earl Bourner

Road Name

Parish

Description of Works

Current Status

No planned works


Appendix G – Traffic Systems

 

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

 

 

Traffic Systems - Contact Officer: Toby Butler

 

Location

Description of Works

Current Status

A26 Tonbridge Road near Milton Street, Maidstone

Refurbishment of traffic signal-controlled crossing

Programmed August 2019

B2162 Twyford Bridge, Yalding

Refurbishment of traffic signals

To be Programmed

A229 Fairmeadow/ Medway Street

Refurbishment of traffic signal-controlled junction

Programmed September 2019

A20 London Road near Broadway

Replacement of signal controller

Programmed September 2019

A20 Tonbridge Road near Station Approach

Replacement of signal controller

Programmed September 2019

 


Appendix H - Combined Member Grant programme update

 

Member Highway Fund programme update for the Maidstone District

 

The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are

·         in design

·         at consultation stage

·         about to be programmed

·         Recently completed on site.

 

The list is up to date as of 24/06/2019

      

The details given below are for highway projects only.  This report does not detail

·         Contributions Members have made to other groups such as parish councils

·         highway studies

·         traffic/ non-motorised user surveys funded by Members.  

 

More information on the schemes listed below can be found by contacting the District Manager for the Maidstone District, Susan Laporte.

 

Dan Daley and Rob Bird

 

Details of Scheme

Status

18/19-CMG-MA-722 – Queens Avenue, Maidstone

 

Construction of build out for part one way

 

 

Works Complete – Snagging items to be carried out

 

 

 

Eric Hotson  

 

Details of Scheme

Status

19/20-CMG-MA-923 – Church Hill, Boughton Monchelsea

 

Traffic Regulation Order application for speed limit reduction

 

 

Notice of Intent sent out to formal consultation on 31 May 2019

 

Paulina Stockell

 

Details of Scheme

Status

19/20-CMG-MA-947 – Darman Lane, Laddingford, Yalding

 

Traffic Regulation Order application for speed limit reduction

 

Notice of Intent sent out to formal consultation on 31 May 2019

 

 


1.1               Legal Implications

1.1.1         Not applicable.

1.2               Financial and Value for Money Considerations

1.2.1         Not applicable.

1.3               Risk Assessment

1.3.1         Not applicable.

Contacts: Kirstie Williams/ Susan Laporte 03000 418181