Policy & Resources

25 April 2018

 

Corporate Risk Update

 

Final Decision-Maker

Policy & Resources Committee

Lead Director

Mark Green - Head of Finance & Business Improvement

Lead Officer and Report Authors

Russell Heppleston – Deputy Head of Audit Partnership

Alison Blake – Audit Manager (Maidstone & Ashford)

Classification

Public

Wards affected

All

 

Executive Summary

In this report we provide Members with an update of the Council’s corporate risks, and more generally, an update on the risk management process. We provide this update twice a year, but this will be the first update since adoption of the risk appetite statement in October 2017.

 

This report makes the following recommendations to this Committee:

1.   That the Corporate risks (as set out in Appendix 1) are discussed & noted 

 

 

Timetable

Meeting

Date

Policy & Resources Committee

25 April 2018



Corporate Risk Update

 

1.    INTRODUCTION AND BACKGROUND

 

1.1     Risk management is the process undertaken to identify, evaluate and mange risks. In early 2016 we implemented a new risk management framework designed to improve the risk management process. This included implementing a programme of monitoring and review stages for Officers and Members. As a result, we have been providing updates twice a year to this Committee to present risk information and detail how the corporate level risks are being managed.

 

1.2     Following our last update in October 2017, Members adopted the risk appetite statement. This statement sets out the level of risk that the Council is willing to take in order to achieve objectives, and also establishes a process for risks that sit above the tolerance level. This was the final element of the risk management process to be implemented, and so since that time we have been working with Officers to update and review all the Council’s risks in accordance the appetite and tolerance levels.

 

1.3     This report provides Members the with outcomes of this review work, including:

 

·         Updates to each corporate risk

·         Risks in the context of our Mid Kent partners

·         Operational risk profile

·         Planned work for 2018/19

 

1.4     The update report is attached in appendix 1 and a full copy of the risk register is attached in appendix 1A

 

 

2.        AVAILABLE OPTIONS

 

2.1     In order for any risk management process to be effective it is vital that risk information is reported, that risks are monitored and that action is taken to manage risks to an acceptable level. This has been recognised by the Committee who have requested updates twice a year.

 

2.2     An alternative option would be for the Committee to change the frequency of our reporting of risks, or stop it altogether. This would however be contrary to previous requests.

 

 

3.        PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS

 

3.1     This report is largely for noting and for discussion during the meeting. This has been a valuable exercise in past meetings, and so the preferred option would be for these updates to continue in this format.

 

 

 

4.       RISK

4.1    The focus of this report is risk management. The update is presented for information only and so has no risk management implications.

 

 

5.       CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK

 

5.1     All risks are allocated an owner, that is, someone in the Council who is best placed to co-ordinate a response and to monitor progress. Risk owners range from our Managers, Heads of Service, up to Corporate Leadership Team.

 

5.2     Risk owners provide their own updates and so all of the Officers identified in the report, and all of the Corporate Leadership Team, has been consulted on the content of this update.

 

 

6.       NEXT STEPS: COMMUNICATION AND IMPLEMENTATION OF THE DECISION

 

6.1     Unless requested otherwise, we will continue to report risk updates to Members of this Committee every 6 months.

 

 

7.       CROSS-CUTTING ISSUES AND IMPLICATIONS

 

 

Issue

Implications

Sign-off

Impact on Corporate Priorities

Risk management is a key component in the Council’s governance. Good governance underpins everything that the Council does.

Russell Heppleston

 

Deputy Head of Audit Partnership

Risk Management

Risk management is the focus of this paper.

Russell Heppleston

 

Deputy Head of Audit Partnership

Financial

Risk management support is provided through the Mid Kent Audit partnership within existing budgets.

 

This decision therefore has no direct financial implications.

Russell Heppleston

 

Deputy Head of Audit Partnership

Staffing

There are no staffing implications to this decision.

Russell Heppleston

 

Deputy Head of Audit Partnership

Legal

There are no legal implications to this decision. 

Russell Heppleston

 

Deputy Head of Audit Partnership

Privacy and Data Protection

There are no privacy or data protection implications to this decision.

Russell Heppleston

 

Deputy Head of Audit Partnership

Equalities

The recommendations do not propose a change in service therefore do not require an equalities impact assessment

Russell Heppleston

 

Deputy Head of Audit Partnership

Crime and Disorder

Not applicable

Russell Heppleston

 

Deputy Head of Audit Partnership

Procurement

Not applicable

Russell Heppleston

 

Deputy Head of Audit Partnership

 

8.        REPORT APPENDICES

 

The following documents are to be published with this report and form part of the report:

·         Appendix 1: Corporate Risk Update

 

 

 

 

 

9.        BACKGROUND PAPERS

 

The risk management framework (detailed guidance) was reported to Policy and Resources Committee in February 2016 and is publically available on the Council’s website.

The Council’s risk appetite statement was agreed by Policy and Resources Committee in October 2017 and is publically available on the Council’s website.