Subject: Highway Works Programme 2011/12

To:                              Maidstone Joint Transportation Board

 

By:                              KCC Highways, Transportation & Waste

 

Date:                           8th July 2020

 

Subject:                      Highway Forward Works Programme – 2020/21 onwards

 

Classification:           Information Only

 

 

Summary: This report updates Members on the identified schemes approved for construction

 

 

1. Introduction

 

This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.

 

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2020/21 and 2021/22) and Year Three to Five (2022/23 to 2024/25) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year.  For some assets this interim programme covers approximately the first six months of 2020/21, whilst for others it includes most of the works planned for the whole year.

 

This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

 

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

           

Drainage Repairs & Improvements – see Appendix B

 

Street Lighting – see Appendix C

 

Transportation and Safety Schemes see Appendix D

  • Casualty Reduction Measures
  • Externally funded schemes
  • Local Growth Fund

 

Developer Funded Works – see Appendix E

 

Bridge Works – see Appendix F

 

Traffic Systems – see Appendix G

 

Combined Member Fund – see Appendix H

 

Conclusion

 

1.    This report is for Members’ information.

 

Contact Officers:

 

The following contact officers can be contacted on 03000 418181

 

Kirstie Williams                                   Highway Manager Mid Kent

Susan Laporte                                     Maidstone District Manager

Alan Casson                                        Strategic Asset Manager                   

Earl Bourner                                        Drainage & Structures Asset Manager

Sue Kinsella                                        Street Light Asset Manager

Toby Butler                                         Traffic & Network Solutions Asset Manager

Jamie Hare                                         Development Agreements Manager

Jamie Watson                                     Schemes Programme Manager

                                   


Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

 

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

 

 

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name

Parish

Extent of Works

Current Status

A249 Sittingbourne Road

Maidstone

Andrew Broughton Way to Bearsted Road

 

Completed

A249 Andrew Broughton Way

Maidstone

Between A249 and Square Hill

 

Programmed 6th July 2020

A20 London Road/A26 Rocky Hill

Maidstone

Maidstone Gyratory to Terrace Road

 

Programmed 6th October 2020

B2012 Lower Boxley Road

Maidstone

Between Stacey's Street and Wheeler Street

 

Programmed 4th December 2020

Square Hill Road

Maidstone

A20 Ashford Road to Mote Road

 

To be programmed early 2021

Mote Avenue

Maidstone

A249 Mote Road to Willow Way

 

To be programmed early 2021

Fishers Estate

Staplehurst

Fishers Road/Hurst Close/Newlyn Drive/Fishers Close

 

To be programmed early 2021

Union Street

Maidstone

Between A249 Sittingbourne Road and Wheeler Street

 

To be programmed early 2021

 

Footway Improvement - Contact Officer Mr Neil Tree

Road Name

Parish

Extent and Description of Works

Current Status

Roseleigh Avenue

Allington

Full length Including Kenward Road and Glenwood Close (Footway resurfacing)

 

To be designed and programmed in

coordination with the Virgin Media programme.

 

St. Michaels Road

Maidstone

 

Various sections throughout the entire length.

(Footway resurfacing)

 

 

 

To be designed and Programmed.

Sheppey Road

Loose

 

Full length including Lismore Close

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Staffa Road

Loose

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Dane Court

Coxheath

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Hildenborough Crescent

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Sussex Road

Maidstone

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Spencer Way

Maidstone

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Garden Close

Maidstone

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Freeman Way

Maidstone

Full length

(Footway Protection)

Designed and programmed for completion in June 2020

 

Wilson Close

Maidstone

Full length

(Footway Protection)

 

Designed and programmed for completion in June 2020

 

Ware Street

Bearsted

 

From Sandy Lane to the vicinity of The White Horse Public House

(Footway Protection)

 

 

 

Designed and to be programmed

Mount Avenue

Yalding

Full length

(Footway Protection)

 

Designed and programmed for completion in August 2020.

 

Downs Road

Yalding

Full length

(Footway Protection)

 

Designed and programmed for completion in August 2020.

 

Blunden Lane

Yalding

Full length

(Footway Protection)

 

Designed and programmed for completion in August 2020.

 

Adisham Drive

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Blackmanstone Way

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Cheriton Way

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Chilham Road

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Eastry Close

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Fordwich Close

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Frinstead Walk

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Halstead Walk

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Kilndown Close

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

Lamberhurst Close

Allington

Full length

(Footway Protection)

 

Designed and programmed for late July/August in coordination with the Virgin Media programme.

 

 

 

Surface Treatments – Contact Officer Mr Jonathan Dean

Road Name

Parish

Extent and Description of Works

Current Status

Goudhurst Road (inc Winchet Hill)

Marden

Lower Ladysden Farm (Pumpkin Farm) to Sherenden Lane

Completed

Benover Road and Collier Street

Yalding

From LupoFresh to Haviker Street

Completed

Heath Road

Coxheath

Stockett Lane to Vanity Lane                                          

Completed

Heath Road

Coxheath

Wood lands to Ewell Lane

Programmed for 14th June 2020 for 3 days

Maidstone Road

Nettlestead

Wheelbarrow Roundabout to Bow Road

Programmed for the 9th June for 6 days

Lenham Road

Kingswood

Gravelly Bottom Road to Chegworth Lane

Completed

Hackney Road

Fant

From Unicumes Lane to Gatland Lane

To be Programmed

Gravelly bottom Road

Lenham

Lenham Road to Broomfield Road

Programmed for 17th June 2020 for 3 days

Sandling Lane

Penenden Heath

From Boxley Road to The Gateway

Programmed for 18th June 2020 for 2 days

Southernden Road (including Grigg Lane)

Egerton

Barhams Mill Road to just past Sherway Road (Horseshoes Farm)

Programmed for 15th June 2020 for 10 days

Tilden Lane

Marden

Stilebridge Lane to Khernfields Farmhouse

Programmed for 24th June 2020 for 7 days

Sheridan Close

Ringlestone

From junction of Dickens Road to outside 26

Programmed for 18th June 2020 for 1 day

Bunce Court Road

Otterden

Otterden Place (Rigshill Road) to Warren Street (Payden Street)

Programmed for 22nd June 2020 for 3 days

Wheelers Lane

Linton

Linton Hill to Vanity Lane

Programmed for 16th June 2020 for 2 days

 

 

 


Appendix B - Drainage

 

Drainage Repairs & Improvements - Contact Officer Earl Bourner 

Road Name

Parish

Description of Works

Current Status

Smith’s Hill

West Farleigh

Investigation works and clearance of drainage

Another order was raised to side the edge of carriageway again and clean the drainage system, this was completed on 24/5/20.

The Broadway

Maidstone

Surface water system surcharging o/s Lidl

Works completed by SWS. Issue appears resolved

Fairmeadow

Maidstone

Long running flooding outside Avis Car Rental. Appears pipes were damaged by third party works

Works progressing on site to expose damage and repair.

Sheals Crescent

Maidstone

CCTV completed. Broken gully lead has been repaired before resurfacing took place

Works Complete.

Green Lane

Chart Sutton

Repair the culvert and edge of road/ verge/ ditch

Works Complete

Dray Corner Road

Headcorn

Drainage issues at junction with Four Oaks Road. Culverts crossing road replaced and ditch cleared to resolve

Works Complete

Dunn Street

Bredhurst

Repair broken pipe and replace one of the two existing soakaways due to it reaching the end of its useful life.

Trial holes are being carried out to assist with info for scheme.

Lower Boxley Road

Fisher Street

Maidstone

Reports of broken pipes and repairs to be carried out

CCTV indicates no major defects. Gullies now working following clearing

Lower Road

East Farleigh

Repair broken pipes

Now complete.

West Street

Hunton

Repair broken pipes

Remedials carried out (buried catchpit found). Ditch maintenance to be taken up by KCC Flood Water Management team.  Now complete.

Liverton Hill

Grafty Green

Drainage cleansing carried out, but some defects identified during course of works. Full CCTV confirmed multiple defects.

With engineer to raise works order

The Street

Boxley

CCTV Completed, further works required to rectify broken pipe outside pub (bollard installation has broken pipe) and replace defective pipework near Street Farm Cottage

Repairs and improvements to the highway drainage system and has now been completed.

Eyhorne/Upper Street/Hollingbourne Hill

Hollingbourne

Various repairs to the highway drainage system.

Order raised and due to start on 1/6/20 for 3 to 4 weeks under a road closure.

A20 Ashford Rd under rail bridge by Square Hill

Maidstone

The existing drainage has been cleaned and surveyed and is working but an improvement scheme is to be developed to reduce risk of blockages and flooding

Quotation requested for underground utilities survey to inform design.

Harp Farm Road

Boxley

Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered

Handed over to Schemes

Redwall Lane, opposite Davis Farm

Linton

Broken pipes require repair

New CCTV to be carried out to mark up for repairs.

 


Appendix C – Street Lighting

 

Structural testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.

 

 

Street Lighting Column Replacement – Contact Officer Sue Kinsella

 

Road Name

Column

Parish

Description of Works

Status

Brishing Lane

KBFE010

Maidstone

Replacement of Street Light

Completion end September 2020

Station Road

KSFA029

Staplehurst

Replacement of Street Light

Completion end September 2020

Egerton Road

KEAQ003

Ringlestone

Replacement of Street Light

Completion end December 2020

Howard Drive

KHFD016

Allington

Replacement of Street Light

Completion end September 2020

Leonard Close

KLBG004

Allington

Replacement of Street Light

Completion end September 2020

Pembroke Road

KPAW014

Coxheath & Hunton

Replacement of Street Light

Completion end September 2020

Deringwood Drive

KDAL007

Downswood & Otham

Replacement of Street Light

Completion end September 2020

Deringwood Drive

KDAL009

Downswood & Otham

Replacement of Street Light

Completion end September 2020

Deringwood Drive

KDAL021

Downswood & Otham

Replacement of Street Light

Completion end September 2020

Deringwood Drive

KDAL022

Downswood & Otham

Replacement of Street Light

Completion end September 2020

Tonbridge Road

KTBU017

Fant

Replacement of Street Light

Completed

Tonbridge Road

KTBU022

Fant

Replacement of Street Light

Completion end September 2020

Tonbridge Road

KTBU031

Fant

Replacement of Street Light

Completed

Tonbridge Road

KTBU036

Fant

Replacement of Street Light

Completed

 

Tonbridge Road

 

KTBU046

 

Fant

 

 

Replacement of Street Light

 

Completed

Tonbridge Road

KTBU050

Fant

Replacement of Street Light

Completion end September 2020

Tonbridge Road

KTBU051

Fant

Replacement of Street Light

Completion end September 2020

Tonbridge Road

KTBU055

Fant

Replacement of Street Light

Completion end September 2020

Mansfield Walk

KMFW202

Fant

Replacement of Street Light

Completion end September 2020

Dover Street

KDBB004

Fant

Replacement of Street Light

Completion end September 2020

Glebe Lane

KGAS006

Fant

Replacement of Street Light

Completed

Terminus Road

KTAD009

Fant

Replacement of Street Light

Completed

Oakwood Court

KOAD003

Heath

Replacement of Street Light

Completed

Heath Road

KHCH005

Heath

Replacement of Street Light

Completion end September 2020

Queens Road

KQAG004

Heath

Replacement of Street Light

Completion end September 2020

Queens Road

KQAG019

Heath

Replacement of Street Light

Completion end September 2020

Mill Walk

KMCT002

Heath

Replacement of Street Light

Completed

St Peters Bridge

KSCE001

High Street

Replacement of Street Light

Completion end December 2020

College Road

KCFC005

High Street

Replacement of Street Light

Completed

Lower Road

KLCU003

High Street

Replacement of Street Light

Completion end September 2020

Upper Road

KUBR010

High Street

Replacement of Street Light

Completion end September 2020

King Street

KKAM021

High Street

Replacement of Street Light

Completion end September 2020

Linton Road

KLBS011

Loose

Replacement of Street Light

Completion end September 2020

Loose Road

KLCQ094

Maidstone

Replacement of Street Light

Completion end September 2020

Bicknor Road

KBCG010

North Downs

Replacement of Street Light

Completion end September 2020

Bicknor Road

KBCG012

North Downs

Replacement of Street Light

Completion end September 2020

Ashford Road

KABO063

North Downs

Replacement of Street Light

Completed

Ashford Road

KABO064

North Downs

Replacement of Street Light

Completed

Wallis Avenue

KWAD016

Park Wood

Replacement of Street Light

Completion end September 2020

Greenfields

KGCA002

Shepway North

Replacement of Street Light

Completion end September 2020

Marion Crescent

KMBK002

Shepway North

Replacement of Street Light

Completion end September 2020

Marion Crescent

KMBK004

Shepway North

Replacement of Street Light

Completion end September 2020

Marion Crescent

KMBK009

Shepway North

Replacement of Street Light

Completion end September 2020

Cranborne Avenue

KCGL014

Shepway North

Replacement of Street Light

Completion end September 2020

Longfield Place

KLCN001

Shepway North

Replacement of Street Light

Completion end September 2020

Holtye Crescent

KHER002

Shepway North

Replacement of Street Light

Completion end September 2020

Holtye Crescent

KHER006

Shepway North

Replacement of Street Light

Completion end September 2020

Holtye Crescent

KHER007

Shepway North

Replacement of Street Light

Completion end September 2020

Rutland Way

KRCC002

Shepway North

Replacement of Street Light

Completion end September 2020

Sutton Road

KSGF007

Shepway South

Replacement of Street Light

Completion end September 2020

Graveney Road

KGBL009

Shepway South

Replacement of Street Light

Completion end September 2020

Cranbrook Close

KCGM001

Shepway South

Replacement of Street Light

Completion end September 2020

Westmarsh Close

KWBT003

Shepway South

Replacement of Street Light

Completion end September 2020

Wingham Close

KWDI005

Shepway South

Replacement of Street Light

Completed

Freeman Way

KFCN002

Shepway South

Replacement of Street Light

Completed

Norrington Road

KNAR007

South

Replacement of Street Light

Completed

Cranbrook Road

KCGN068

Staplehurst

Replacement of Street Light

Completed

Cranbrook Road

KCGN073

Staplehurst

Replacement of Street Light

Completed

Station Road

KSFA018

Staplehurst

Replacement of Street Light

Completion end September 2020

Station Road

KSFA021

Staplehurst

Replacement of Street Light

Completion end September 2020

Station Road

KSFA024

Staplehurst

Replacement of Street Light

Completion end September 2020

High Street

KHDO057

Staplehurst

Replacement of Street Light

Completion end September 2020

Linden Road

KLBM014

Coxheath

Replacement of Street Light

Completed

Frinsted Walk

KFCS002

Allington

Replacement of Street Light

Completion end September 2020

Cornwall Close

KCFR003

Shepway South

Replacement of Street Light

Completed

Impton Lane

KIAC007

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

Impton Lane

KIAC008

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

Impton Lane

KIAC010

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

Impton Lane

KIAC011

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

Impton Lane

KIAC012

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

Impton Lane

KIAC013

Bluebell Hill Walderslade

Replacement of Street Light

Completion end September 2020

 


Appendix D – Transportation and Safety Schemes

 

Casualty Reduction Measures

 

The Schemes Planning & Delivery team is implementing schemes within the Maidstone District, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety).  Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status update as of 15/6/20.

 

Location

Parish

Description of Works

Lead officer

Current Status

A20 Ashford Road/M20 Slip

Hollingbourne

Signing and road marking improvements

Jennie Watson

Works handed over to contractor.  Awaiting road space to carry out works on site.

Running Horse Roundabout

Maidstone

Virtual lane separation system using road markings & coloured surfacing

Paul Leary

Origin/destination & drone traffic surveys currently on hold due to Coronavirus.

Bishops Way

Maidstone

Signing and lining improvements

Geoff Bineham

Detailed design stage – Works due to be handed over to contractor 31/7/2020

Bishops Way junction Palace Street

Maidstone

Signing and lining improvements

Geoff Bineham

Detailed design stage – Works due to be handed over to contractor 31/7/2020

Chalky Road junction A249 Sittingbourne Road

Stockbury

Signing and lining improvements

Jennie Watson

Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020.

A249 Sittingbourne Road junction Church Hill

Stockbury

Signing and lining improvements

Jennie Watson

Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020

A249 Sittingbourne Road junction with Hucking U Turn

Stockbury

Signing and lining improvements

Jennie Watson

Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020

Lidsing Road junction Dunn Street Road

Boxley

Signing and lining improvements

Jennie Watson

Works handed over to contractor 30/5/2020 – Works on site due to be carried out August 2020

Dean Street junction Heath Road crossroads

Coxheath

Signing and lining improvements

Jennie Watson

Detailed design currently being carried out – Scheme due to be handed over to contractor 31/7/2020

Loose Road junction Armstrong Road

Maidstone

Signing and lining improvements

Clare Venner

Detailed design stage – Due to be handed over to contractor 13/7/2020

Lenham Road

Headcorn

Signing and lining improvements

Jennie Watson

Scheme handed over to contractor 15/4/2020 – Works due to be start on site July 2020

Tonbridge Road junction Westree Road

Maidstone

Signing and lining improvements

Clare Venner

Detailed design stage – Works due to be handed over to contractor 31/8/2020

Heath Road – near Stockett Lane junction

Coxheath

Upgrade signing and refresh existing lining plus upgrade beacons on northern zebra crossing

Jennie Watson

Detailed design stage – Works due to be handed over to contractor 31/7/2020

Roundabout at M20 J7 (A249)

Boxley

Signing and lining improvements

Christopher Koningen

Detailed design stage – Works due to be handed over 13/7/2020

Externally Funded Schemes

 

The Schemes Planning & Delivery team is implementing schemes within the borough of Maidstone funded by external corporations whilst still meeting KCC’s strategic targets with the road network.

 

Location

Parish

Description of Works

Lead officer

Current Status

East Farleigh Bridge

East Farleigh

Upgrade of signing and lining for bridge width restriction

Paul Leary

Stage 3 road safety audit received for build-out on Farleigh Lane. Contractor to install missing hatching road markings on approach.

Mote Park Cycleway (Phase 1)

Maidstone

Upgrade of cycle route

Paul Leary

Works complete on site. Scheme currently being monitored as part of the contractor’s maintenance period.

Mote Park Cycleway

(Phase 2)

Maidstone

Signing and road marking improvements between Chancery Lane and Maidstone House

Paul Leary

Works complete on site December 2019. Scheme currently being monitored as part of the contractor’s maintenance period.

Walderslade Woods

Boxley

Reduction of speed limit to 50mph and associated traffic calming measures

Jennie Watson

Traffic Regulation Order for speed limit Notice of Intent advertised 12 June until 6 July 2020 for consultation – Scheme due to be handed over to contractor 30/10/2020

North Street – Outside Sutton Valence School

Sutton Valence

Installation of bollards to deter parking and damage to verges

Whitney Gwillim

Scheme handed over to contractor 21/5/2020.  Works complete on site.  Please note that 4 No. additional bollards are to be installed as vehicles are still accessing verges following completion of works

A229 Cranbrook Road/High Street

Staplehurst

Virtual Traffic Calming Scheme

Paul Leary

Currently at outline design stage – scheme due to be handed over to contractor 30/9/2020

Pheasant Lane

Maidstone

New cycle route

Paul Leary

Currently at outline design stage - scheme due to be handed over to contractor 28/8/2020

 

Local Growth Fund

 

Local Growth Fund programme update for the Maidstone District.

 

The Department for Transport (DfT) added Ł100m to the Local Growth Fund (LGF) pot in order to fund Local Sustainable Transport Fund Style schemes.  KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion.  The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.

 

The schemes aim to:

 

·         improve access to employment and services

·         reduce the need to travel by the private car

·         enhance pedestrian, cycle and public transport facilities

·         improve sustainable transport connections 

 

The following schemes have been submitted as part of the successful Kent Thameside/West Kent (delete as applicable) LSTF this financial year.

 

 

Location

Parish

Description of Works

Lead officer

Current Status

Week Street junction with Station Road

Maidstone

A highway improvement consisting of a raised table and improvements to 2 pedestrian crossings to better link Week Street to Maidstone East Rail Station

 

Alan Osuoha

 

Detailed design progressing with a view to implement October 2020 pending support approvals


Appendix E – Developer Funded Works

 

Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers as listed Jamie Hare, Aaron Divall, Steven Noad, Andy Padgham, Steve A Stickels

 

Scheme Name

File Ref.

Officer

Parish

Description of Works

Current Status

BP Tudor Service Station, London Road

MA003072

CV

Allington

Alterations to existing access

Pedestrian crossing point & signage to complete

 

Bell Farm, North Street

MA003098

SN

Barming

New accesses to split sites, shared surface and new crossing point

Highway works completed. Stage 3 Safety Audit Awaited.

Cross Keys

MA003100

 

JH

Bearsted

New access, crossing point and parking area

Works underway

Barty Farm, Roundwell,

MA003278

AD

Bearsted

New Bellmouth and Lining works

Works Progressing

Bicknor Road

MA003256

AP

Bicknor

Formation of hard surfaced passing places

Awaiting technical approval

Heath Road/Church Street

MA003111

AP

Boughton Monchelsea

New access, footway works, yellow lines and crossing upgrade

Completion of footway still outstanding along with defects picked up.

Hubbards Lane

MA003084

CV

Boughton Monchelsea

Two accesses to minor developments

Works substantially completed


Lyewood Farm, Green Lane

MA3247

MA3248

AP

Boughton Monchelsea

New housing development and access

S278 agreement signed, works delayed due to Covid 19, due to continue

 7 July 2020

 

Goya Development, St Michaels Close, Aylesford

MA003123

 

CV

Boxley

New access and f/way works to new commercial properties

Works complete except for new gulley.

Works due shortly

Maidstone Studios, New Cut Road

MA003110

AP

Boxley

Zebra crossing and pedestrian crossing points

High Friction works by KCC at developers’ cost. Now in maintenance.

St Michaels Close, Aylesford

MA003103

CV

Boxley

Waitrose car park, new access

At end of Maintenance.

Forstal Lane

Ma003141

AP

Coxheath

Widening of road and new footpath with access to new development

Works completed

 

Heath Road (North side)

MA003063

CV

Coxheath

New access and Footway work

Works in maintenance

Heath Road, Coxheath

MA003134

CV

Coxheath

New access and new footway adj. Medical centre

Works completed

Land north of Heath Road Phase 2

MA3257

AP

Coxheath

Access to new development

Works still outstanding to include resurface of road and build out

Linden Farm, Stockett Lane

MA003107

 AP

Coxheath

Access to new development and footway link to community hall

2 accesses to restore to footway near completion of development.

Gatland House, Gatland Lane

MA003081

CV

Fant

Parking restrictions, signage, road markings and tactile crossings for new school

Works completed, Remedials to do

Bell Farm, Ashford Road

MA003094

CV

Harrietsham

Realignment of Church Road to form new access onto A20. New footway along A20

Works in maintenance.

Mayfield Nursery, Ashford Road

MA003135

AP

Harrietsham

New access and alterations to existing Highway to adjoin upcoming Scheme Works

Works now in maintenance

Forge Meadows

MA3253

 

AP

Headcorn

Access to 2 new properties and vehicle crossovers to existing properties

Agreement signed. Awaiting start date from developer.

Gibbs Farm Grigg Lane & Wheeler Street

MA3250

SAS

Headcorn

Access Gibbs Farm development, zebra crossing on Wheeler Street

Agreement signed, works commenced.

Grigg Lane, Lenham Road,

 

MA003050

CV

Headcorn

Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane

New accesses Grigg Lane and Lenham Road & new footway Grigg Lane in maintenance

Kings Road/Millbank

MA3262

 

AP

Headcorn

Signalised crossroads (linked to Ulcombe Road MA3150)

Works completed. Maintenance period to commence when all requirements have been met.

Lenham Road (North side)

MA003062

CV

Headcorn

New Footway to site and extension of speed limit boundary

Works in Maintenance

Lenham Road (South side)

MA003057

CV

Headcorn

New footway

Revised design received

Oak Lane and Wheeler Street

MA003048

CV

Headcorn

New footway plus junction improvements

Works completed and in maintenance

Ulcombe Road

MA003150

AP

Headcorn

Access to new development

Defects to be completed.

Wheeler Street, Headcorn

MA003137

 

AP

Headcorn

New access off Kingsland Grove and footway works on Wheeler Street

Works in maintenance

Eyhorne Street

MA3198

AP

Hollingbourne

New access to development

Works completed. First certificate to be issued when requirements have been met.

Bentletts Yard, Claygate Road, Laddingford

MA003357

AP

Laddingford

New footway and replaced surface to existing access

Surface course to be completed

8 Faversham Road

MA003032

CV

Lenham

New access

In maintenance, streetlight to replace

Old Ashford Road

MA003018

CV

Lenham

New footway plus access

Approaching end of maintenance, bus stop location to amend.

The Paddocks, Ashford Road (Grove House, Old Ashford Road)

MA3114

CV

Lenham

New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd

Works completed, finishing/remedials required.

Westwood Park, Ham Lane

MA003305

AP

Lenham

Main and emergency accesses to new housing dev.

Technical approval granted. Awaiting completion of agreement.

Old Ashford Road, Adj Groom Way

MA003356

AP

Lenham

New access and footway

Awaiting Technical Approval

Heath Road

MA3326

JH

Linton

New Access

Awaiting start date

Wares Farm, Linton Hill

MA003353

AP

Linton

New access

Works commenced surface course outstanding

Royal Engineers Rd/Mill Lane

MA3312

JH

Maidstone

Access to New Development

Under Technical Review

 

531 Tonbridge Road

MA003045

CV

Maidstone

Service layby for new retail unit

In maintenance

Bicknor Green, Gore Court Road

MA003053

 

AD

Maidstone

Change of road priorities and widening / upgrading

Works complete

Hartnup Street

MA003138

SP

Maidstone

New Access

Works complete now in          maintenance.

Hermitage Lane, (opp. Maidstone Hospital)

MA003060

AD

Maidstone

New Traffic signal junction

Near to adoption


Hermitage Lane/ Howard Drive

MA003070

AD

Maidstone

New access for development (opposite the quarry entrance)

Works complete

Howard Drive

MA003303

 

AD

Maidstone

Junction works to facilitate Bus Gateway entrance to Croudace site

Works Started

Maidstone School of Science, New Cut Road

MA003197

 

AP

Maidstone

New access to School and New roundabout and alterations to Highway

Works completed

McDonalds drive-through, Hart Street

MA003013

CV

Maidstone

New access, improvements to Hart Street.

Approaching the end of maintenance - remedial works due

Oakapple Lane/ Hermitage Lane

MA003046

AD

Maidstone

New bellmouth junction and associated ancillary works inc. new bus stop, for new development

Works Complete – in maintenance

Royal Engineers Road

MA003127

JH

Maidstone

New footpaths to development

Awaiting works start date

The Poplars, Ashford Road

MA3254

AP

Maidstone

Access to new development

Works completed. Awaiting documents for issue of 1st certificate.

Wallis Avenue Phase 3, Parkwood

MA003085

 

CV

Maidstone

Stopping up of highway, redevelopment of car park & shops opp. Longshaw Rd

 

Works in maintenance

Week St/Gabriel’s Hill

MA003120

JH

Maidstone

Town Centre Public Realm improvements

Due to start maintenance

Castle Dene, Maidstone

MA993352

CV

Maidstone

New Access and further footway works and repairs

Awaiting Technical Approval

Union Street, Car Park

MA003319

CV

Maidstone

New Access to development and footway works

Awaiting Technical Approval

Medway Street

MA3326

JH

Maidstone

Subway Flood Protection Works

Under Technical review

Langley Park Farm

MA003130

 

 

AD

Maidstone / Langley

New Roundabout and associated works for entrance to Countryside Estate

Works imminent

Albion Road, Marden

MA003132

CV

Marden

New Access & development

Works on going

Goudhurst Road, Church Green (Plain Road development)

MA3118

CV

Marden

Install Zebra crossing near rail station.

Works in Maintenance

Goudhurst Road/West End (Plain Road Development)

MA3118

CV

Marden

Refurbish Zebra crossing outside school and Bus Borders to add by Library stops.

Works in Maintenance

Howland Road

 

MA003088

 

SN

Marden

New development access

Highway works completed. Stage 3 Safety Audit Awaited.

MAP Depot, Goudhurst Road

MA003012

CV

Marden

New bellmouth junction and footway

Works in maintenance. Remedial works near completed and interactive speed sign awaiting installation

Napoleon Drive and Plain Road

MA003079

CV

Marden

New access on each road for new housing development

Works in maintenance

The Parsonage, Goudhurst Road

MA003066

MA003067

CV

Marden

New access and associated upgrade works

Access substantially completed, village gateway to be agreed

Fishers Farm (East) Headcorn Road (Redrow)

MA3106

AP

Staplehurst

Realignment and new access at Headcorn Road/Pile Lane junction

Realignment complete and Pile Lane open

30mph limit change to implement

Fishers Farm (West), Headcorn Road (Bovis)

MA3037

AP

Staplehurst

New access onto Headcorn Road

Works commenced on both S278 and S38

Hen and Duckhurst Farm, Marden Road

MA003109

CV

Staplehurst

New Roundabout for development access

Works on highway almost completed. HFS delayed by utility works.

Oliver Road Staplehurst

MA003019

CV

Staplehurst

Ped crossing to Marden Road, junction markings and bus boarders

Works in maintenance

Woodford Park

MA003099

CV

Staplehurst

New access for 9 dwellings

Works completed and on to maintenance.

Appleacres, Maidstone Road

MA003152

CV

Sutton Valence

Access to new development and footway works

Technical Approval given awaiting Legal Agreement

The Oaks, Maidstone Road

MA003078

CV

Sutton Valence

Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing.

Works complete

Valdene Industrial Estate

MA003054

CV

Sutton Valence

Upgrade of existing bellmouth and extension to f/w

Works completed

Cripple Street Maidstone

MA003093

CV

Tovil

New access to development, widening and footway works

Due for adoption – remedials due

Site opposite cottages 129-147 Dean Street/Farleigh Hill

MA003007

CV

Tovil

New access speed limit relocation, new footway and bus stop provision

Works in maintenance

Tovil Green Lane

MA003095

CV

Tovil

New Footway and crossing point to side of site

Works in maintenance

Mount Ave/Blunden Lane

MA3180

CV

Yalding

New accesses at site entrance

Works in Maintenance

Hampstead Lane

MA3101

CV

Yalding

Relocate access to new development at old depot adj. station. Minor footway works

Into maintenance period

Vicarage Road

MA003121

CV

Yalding

New access to development and speed restraints on existing Highway

New Agreement required due to expiry date and works not carried out.  Contents of S278 now reduced.

 

 

 

 

Section 106 Schemes

 

File Ref.

Road Name

Parish

Description of Works

Current Status

18/19-S106-MA-486

A20 Ashford Road

Harrietsham

Village improvement works: 2 phase approach.

Phase 1 which consisted of narrowing the carriageway, widening footways to allow shared footway/cycleway, altering the controlled crossing, provision of central islands and changes to the speed limits and associated signing and lining.

Phase 2 will include relocating street lighting columns to better suit the new road layout and to extend the lighting to include the 30mph limit. Resurfacing of the carriageway to hide the old white lining and then new lining to the recently installed layout.

.

Phase 1 Works completed in June 2019.

 

Phase 2 Works, the micro surfacing and road markings are now complete. The streetlighting work has started on site.

18/19-S106-MA-819

Linton Crossroads

Linton/Loose

Junction/signal upgrade

No change from previous report - Finalising designs however the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. Environmental Impact Assessment and Ecological appraisal being undertaken.

TBC

Hermitage Lane

Maidstone

Cycleway improvements between rail station and hospital on east side

Detailed designs are progressing with a view to implementation in the last quarter of this financial year pending availability of road space.

 

 

 

 

 

Parish Council Funded Schemes

 

File Ref.

Road Name

Parish

Description of Works

Current Status

2021-EXT-MA-1232

 

Linton Hill

Linton

Traffic Calming Scheme

Detailed Design stage – Scheme is due to be handed over to contractor 30/7/2020

2021-CMG-MA-1252

 

Village Centre

Boughton Monchelsea

20mph scheme

Detailed Design stage – Handover date to contractor to be confirmed

2021-EXT-MA-1000

 

Grafty Green

Boughton Malherbe

Traffic Calming Scheme

Detailed Design stage – Scheme is due to be handed over to contractor 28/9/2020


Appendix F – Bridge Works

 

Bridge Works – Contact Officer: Earl Bourner

Road Name

Parish

Description of Works

Current Status

No works planned

 


Appendix G – Traffic Systems

 

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

 

Traffic Systems - Contact Officer: Toby Butler

 

Location

Description of Works

Current Status

B2162 Twyford Bridge, Yalding

Refurbishment of traffic signals

Completed

April 2020

Heath Road / Hermitage Lane, Barming

Addition of pedestrian crossing facility

Summer 2020


Appendix H - Combined Member Grant programme update

 

Member Highway Fund programme update for the Maidstone District.

 

The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are

·         in design

·         at consultation stage

·         about to be programmed

·         Recently completed on site.

 

The list is up to date as of 16/6/20.

      

The details given below are for highway projects only.  This report does not detail

·         Contributions Members have made to other groups such as parish councils

·         highway studies

·         traffic/ non-motorised user surveys funded by Members.  

 

More information on the schemes listed below can be found by contacting the District Manager for the Maidstone district, Susan Laporte.

 

Dan Daley and Rob Bird

 

Details of Scheme

Status

2021-CMG-MA-1003 – Hildenborough Crescent, Maidstone

 

20mph scheme

 

Detailed design being carried out – Scheme due to be handed over to contractor 28/9/2020 – Scheme to be implemented October/November 2020

2021-CMG-MA-1000 – Blackmanstone Way Maidstone

 

Construction of footpath between estates

 

Works handed over to contractor 30/5/2020

2021-CMG-MA-1001 – Buckland Hill, Maidstone

 

20mph scheme

 

TRO currently on hold due to Covid-19

 

Eric Hotson         

 

Details of Scheme

Status

21/21-CMG-MA-1252 – Heath Road, Boughton Monchelsea

 

Traffic Regulation Order application for speed limit reduction to 30mph

 

Notice of Intent sent for advertising and consultation from 12 June until 6 July 2020

 

 

 

 

 

Shellina Prendergast

 

Details of Scheme

Status

20/21-CMG-MA-1253 – Lenham Road/Chaingate Road, Liverton Hill, Platts Heath, Lenham

 

Traffic Regulation Order application for speed limit reduction to 30mph

 

 

 

TRO sent for sealing – comes into effect 2 July 2020

20/21-CMG-MA-1254 – Lenham Road, Ulcombe

 

Traffic Regulation Order application for speed limit reduction to 30mph

 

Notice of Intent sent for advertising and consultation from 12 June until 6 July 2020

 

 


1.1               Legal Implications

1.1.1         Not applicable.

1.2               Financial and Value for Money Considerations

1.2.1         Not applicable.

1.3               Risk Assessment

1.3.1         Not applicable.

Contacts: Susan Laporte 03000 418181