To: Maidstone Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 8th July 2020
Subject: Highway Forward Works Programme – 2020/21 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2020/21 and 2021/22) and Year Three to Five (2022/23 to 2024/25) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2020/21, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
- Casualty Reduction Measures
- Externally funded schemes
- Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent
Susan Laporte Maidstone District Manager
Alan Casson Strategic Asset Manager
Earl Bourner Drainage & Structures Asset Manager
Sue Kinsella Street Light Asset Manager
Toby Butler Traffic & Network Solutions Asset Manager
Jamie Hare Development Agreements Manager
Jamie Watson Schemes Programme Manager
Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Mr Byron Lovell |
|||
Road Name |
Parish |
Extent of Works |
Current Status |
A249 Sittingbourne Road |
Maidstone |
Andrew Broughton Way to Bearsted Road |
Completed |
A249 Andrew Broughton Way |
Maidstone |
Between A249 and Square Hill |
Programmed 6th July 2020 |
A20 London Road/A26 Rocky Hill |
Maidstone |
Maidstone Gyratory to Terrace Road |
Programmed 6th October 2020 |
B2012 Lower Boxley Road |
Maidstone |
Between Stacey's Street and Wheeler Street |
Programmed 4th December 2020 |
Square Hill Road |
Maidstone |
A20 Ashford Road to Mote Road |
To be programmed early 2021 |
Mote Avenue |
Maidstone |
A249 Mote Road to Willow Way |
To be programmed early 2021 |
Fishers Estate |
Staplehurst |
Fishers Road/Hurst Close/Newlyn Drive/Fishers Close |
To be programmed early 2021 |
Union Street |
Maidstone |
Between A249 Sittingbourne Road and Wheeler Street |
To be programmed early 2021 |
Footway Improvement - Contact Officer Mr Neil Tree |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Roseleigh Avenue |
Allington |
Full length Including Kenward Road and Glenwood Close (Footway resurfacing) |
To be designed and programmed in coordination with the Virgin Media programme.
|
St. Michaels Road |
Maidstone |
Various sections throughout the entire length. (Footway resurfacing)
|
To be designed and Programmed. |
Sheppey Road |
Loose |
Full length including Lismore Close (Footway Protection) |
Designed and programmed for completion in June 2020
|
Staffa Road |
Loose |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Dane Court |
Coxheath |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Hildenborough Crescent |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Sussex Road |
Maidstone |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Spencer Way |
Maidstone |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Garden Close |
Maidstone |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Freeman Way |
Maidstone |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Wilson Close |
Maidstone |
Full length (Footway Protection) |
Designed and programmed for completion in June 2020
|
Ware Street |
Bearsted |
From Sandy Lane to the vicinity of The White Horse Public House (Footway Protection)
|
Designed and to be programmed |
Mount Avenue |
Yalding |
Full length (Footway Protection) |
Designed and programmed for completion in August 2020.
|
Downs Road |
Yalding |
Full length (Footway Protection) |
Designed and programmed for completion in August 2020.
|
Blunden Lane |
Yalding |
Full length (Footway Protection) |
Designed and programmed for completion in August 2020.
|
Adisham Drive |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Blackmanstone Way |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Cheriton Way |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Chilham Road |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Eastry Close |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Fordwich Close |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Frinstead Walk |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Halstead Walk |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Kilndown Close |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Lamberhurst Close |
Allington |
Full length (Footway Protection) |
Designed and programmed for late July/August in coordination with the Virgin Media programme.
|
Surface Treatments – Contact Officer Mr Jonathan Dean |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Goudhurst Road (inc Winchet Hill) |
Marden |
Lower Ladysden Farm (Pumpkin Farm) to Sherenden Lane |
Completed |
Benover Road and Collier Street |
Yalding |
From LupoFresh to Haviker Street |
Completed |
Heath Road |
Coxheath |
Stockett Lane to Vanity Lane |
Completed |
Heath Road |
Coxheath |
Wood lands to Ewell Lane |
Programmed for 14th June 2020 for 3 days |
Maidstone Road |
Nettlestead |
Wheelbarrow Roundabout to Bow Road |
Programmed for the 9th June for 6 days |
Lenham Road |
Kingswood |
Gravelly Bottom Road to Chegworth Lane |
Completed |
Hackney Road |
Fant |
From Unicumes Lane to Gatland Lane |
To be Programmed |
Gravelly bottom Road |
Lenham |
Lenham Road to Broomfield Road |
Programmed for 17th June 2020 for 3 days |
Sandling Lane |
Penenden Heath |
From Boxley Road to The Gateway |
Programmed for 18th June 2020 for 2 days |
Southernden Road (including Grigg Lane) |
Egerton |
Barhams Mill Road to just past Sherway Road (Horseshoes Farm) |
Programmed for 15th June 2020 for 10 days |
Tilden Lane |
Marden |
Stilebridge Lane to Khernfields Farmhouse |
Programmed for 24th June 2020 for 7 days |
Sheridan Close |
Ringlestone |
From junction of Dickens Road to outside 26 |
Programmed for 18th June 2020 for 1 day |
Bunce Court Road |
Otterden |
Otterden Place (Rigshill Road) to Warren Street (Payden Street) |
Programmed for 22nd June 2020 for 3 days |
Wheelers Lane |
Linton |
Linton Hill to Vanity Lane |
Programmed for 16th June 2020 for 2 days |
Appendix B - Drainage
Drainage Repairs & Improvements - Contact Officer Earl Bourner |
|||
Parish |
Description of Works |
Current Status |
|
Smith’s Hill |
West Farleigh |
Investigation works and clearance of drainage |
Another order was raised to side the edge of carriageway again and clean the drainage system, this was completed on 24/5/20. |
The Broadway |
Maidstone |
Surface water system surcharging o/s Lidl |
Works completed by SWS. Issue appears resolved |
Fairmeadow |
Maidstone |
Long running flooding outside Avis Car Rental. Appears pipes were damaged by third party works |
Works progressing on site to expose damage and repair. |
Sheals Crescent |
Maidstone |
CCTV completed. Broken gully lead has been repaired before resurfacing took place |
Works Complete. |
Green Lane |
Chart Sutton |
Repair the culvert and edge of road/ verge/ ditch |
Works Complete |
Dray Corner Road |
Headcorn |
Drainage issues at junction with Four Oaks Road. Culverts crossing road replaced and ditch cleared to resolve |
Works Complete |
Dunn Street |
Bredhurst |
Repair broken pipe and replace one of the two existing soakaways due to it reaching the end of its useful life. |
Trial holes are being carried out to assist with info for scheme. |
Lower Boxley Road Fisher Street |
Maidstone |
Reports of broken pipes and repairs to be carried out |
CCTV indicates no major defects. Gullies now working following clearing |
Lower Road |
East Farleigh |
Repair broken pipes |
Now complete. |
West Street |
Hunton |
Repair broken pipes |
Remedials carried out (buried catchpit found). Ditch maintenance to be taken up by KCC Flood Water Management team. Now complete. |
Liverton Hill |
Grafty Green |
Drainage cleansing carried out, but some defects identified during course of works. Full CCTV confirmed multiple defects. |
With engineer to raise works order |
The Street |
Boxley |
CCTV Completed, further works required to rectify broken pipe outside pub (bollard installation has broken pipe) and replace defective pipework near Street Farm Cottage |
Repairs and improvements to the highway drainage system and has now been completed. |
Eyhorne/Upper Street/Hollingbourne Hill |
Hollingbourne |
Various repairs to the highway drainage system. |
Order raised and due to start on 1/6/20 for 3 to 4 weeks under a road closure. |
A20 Ashford Rd under rail bridge by Square Hill |
Maidstone |
The existing drainage has been cleaned and surveyed and is working but an improvement scheme is to be developed to reduce risk of blockages and flooding |
Quotation requested for underground utilities survey to inform design. |
Harp Farm Road |
Boxley |
Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered |
Handed over to Schemes |
Redwall Lane, opposite Davis Farm |
Linton |
Broken pipes require repair |
New CCTV to be carried out to mark up for repairs. |
Appendix C – Street Lighting
Structural testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer Sue Kinsella
|
||||
Road Name |
Column |
Parish |
Description of Works |
Status |
Brishing Lane |
KBFE010 |
Maidstone |
Replacement of Street Light |
Completion end September 2020 |
Station Road |
KSFA029 |
Staplehurst |
Replacement of Street Light |
Completion end September 2020 |
Egerton Road |
KEAQ003 |
Ringlestone |
Replacement of Street Light |
Completion end December 2020 |
Howard Drive |
KHFD016 |
Allington |
Replacement of Street Light |
Completion end September 2020 |
Leonard Close |
KLBG004 |
Allington |
Replacement of Street Light |
Completion end September 2020 |
Pembroke Road |
KPAW014 |
Coxheath & Hunton |
Replacement of Street Light |
Completion end September 2020 |
Deringwood Drive |
KDAL007 |
Downswood & Otham |
Replacement of Street Light |
Completion end September 2020 |
Deringwood Drive |
KDAL009 |
Downswood & Otham |
Replacement of Street Light |
Completion end September 2020 |
Deringwood Drive |
KDAL021 |
Downswood & Otham |
Replacement of Street Light |
Completion end September 2020 |
Deringwood Drive |
KDAL022 |
Downswood & Otham |
Replacement of Street Light |
Completion end September 2020 |
Tonbridge Road |
KTBU017 |
Fant |
Replacement of Street Light |
Completed |
Tonbridge Road |
KTBU022 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Tonbridge Road |
KTBU031 |
Fant |
Replacement of Street Light |
Completed |
Tonbridge Road |
KTBU036 |
Fant |
Replacement of Street Light |
Completed |
Tonbridge Road |
KTBU046 |
Fant |
Replacement of Street Light |
Completed |
Tonbridge Road |
KTBU050 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Tonbridge Road |
KTBU051 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Tonbridge Road |
KTBU055 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Mansfield Walk |
KMFW202 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Dover Street |
KDBB004 |
Fant |
Replacement of Street Light |
Completion end September 2020 |
Glebe Lane |
KGAS006 |
Fant |
Replacement of Street Light |
Completed |
Terminus Road |
KTAD009 |
Fant |
Replacement of Street Light |
Completed |
Oakwood Court |
KOAD003 |
Heath |
Replacement of Street Light |
Completed |
Heath Road |
KHCH005 |
Heath |
Replacement of Street Light |
Completion end September 2020 |
Queens Road |
KQAG004 |
Heath |
Replacement of Street Light |
Completion end September 2020 |
Queens Road |
KQAG019 |
Heath |
Replacement of Street Light |
Completion end September 2020 |
Mill Walk |
KMCT002 |
Heath |
Replacement of Street Light |
Completed |
St Peters Bridge |
KSCE001 |
High Street |
Replacement of Street Light |
Completion end December 2020 |
College Road |
KCFC005 |
High Street |
Replacement of Street Light |
Completed |
Lower Road |
KLCU003 |
High Street |
Replacement of Street Light |
Completion end September 2020 |
Upper Road |
KUBR010 |
High Street |
Replacement of Street Light |
Completion end September 2020 |
King Street |
KKAM021 |
High Street |
Replacement of Street Light |
Completion end September 2020 |
Linton Road |
KLBS011 |
Loose |
Replacement of Street Light |
Completion end September 2020 |
Loose Road |
KLCQ094 |
Maidstone |
Replacement of Street Light |
Completion end September 2020 |
Bicknor Road |
KBCG010 |
North Downs |
Replacement of Street Light |
Completion end September 2020 |
Bicknor Road |
KBCG012 |
North Downs |
Replacement of Street Light |
Completion end September 2020 |
Ashford Road |
KABO063 |
North Downs |
Replacement of Street Light |
Completed |
Ashford Road |
KABO064 |
North Downs |
Replacement of Street Light |
Completed |
Wallis Avenue |
KWAD016 |
Park Wood |
Replacement of Street Light |
Completion end September 2020 |
Greenfields |
KGCA002 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Marion Crescent |
KMBK002 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Marion Crescent |
KMBK004 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Marion Crescent |
KMBK009 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Cranborne Avenue |
KCGL014 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Longfield Place |
KLCN001 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Holtye Crescent |
KHER002 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Holtye Crescent |
KHER006 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Holtye Crescent |
KHER007 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Rutland Way |
KRCC002 |
Shepway North |
Replacement of Street Light |
Completion end September 2020 |
Sutton Road |
KSGF007 |
Shepway South |
Replacement of Street Light |
Completion end September 2020 |
Graveney Road |
KGBL009 |
Shepway South |
Replacement of Street Light |
Completion end September 2020 |
Cranbrook Close |
KCGM001 |
Shepway South |
Replacement of Street Light |
Completion end September 2020 |
Westmarsh Close |
KWBT003 |
Shepway South |
Replacement of Street Light |
Completion end September 2020 |
Wingham Close |
KWDI005 |
Shepway South |
Replacement of Street Light |
Completed |
Freeman Way |
KFCN002 |
Shepway South |
Replacement of Street Light |
Completed |
Norrington Road |
KNAR007 |
South |
Replacement of Street Light |
Completed |
Cranbrook Road |
KCGN068 |
Staplehurst |
Replacement of Street Light |
Completed |
Cranbrook Road |
KCGN073 |
Staplehurst |
Replacement of Street Light |
Completed |
Station Road |
KSFA018 |
Staplehurst |
Replacement of Street Light |
Completion end September 2020 |
Station Road |
KSFA021 |
Staplehurst |
Replacement of Street Light |
Completion end September 2020 |
Station Road |
KSFA024 |
Staplehurst |
Replacement of Street Light |
Completion end September 2020 |
High Street |
KHDO057 |
Staplehurst |
Replacement of Street Light |
Completion end September 2020 |
Linden Road |
KLBM014 |
Coxheath |
Replacement of Street Light |
Completed |
Frinsted Walk |
KFCS002 |
Allington |
Replacement of Street Light |
Completion end September 2020 |
Cornwall Close |
KCFR003 |
Shepway South |
Replacement of Street Light |
Completed |
Impton Lane |
KIAC007 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Impton Lane |
KIAC008 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Impton Lane |
KIAC010 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Impton Lane |
KIAC011 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Impton Lane |
KIAC012 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Impton Lane |
KIAC013 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end September 2020 |
Appendix D – Transportation and Safety Schemes
Casualty Reduction Measures
The Schemes Planning & Delivery team is implementing schemes within the Maidstone District, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status update as of 15/6/20.
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
A20 Ashford Road/M20 Slip |
Hollingbourne |
Signing and road marking improvements |
Jennie Watson |
Works handed over to contractor. Awaiting road space to carry out works on site. |
Running Horse Roundabout |
Maidstone |
Virtual lane separation system using road markings & coloured surfacing |
Paul Leary |
Origin/destination & drone traffic surveys currently on hold due to Coronavirus. |
Bishops Way |
Maidstone |
Signing and lining improvements |
Geoff Bineham |
Detailed design stage – Works due to be handed over to contractor 31/7/2020 |
Bishops Way junction Palace Street |
Maidstone |
Signing and lining improvements |
Geoff Bineham |
Detailed design stage – Works due to be handed over to contractor 31/7/2020 |
Chalky Road junction A249 Sittingbourne Road |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020. |
A249 Sittingbourne Road junction Church Hill |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020 |
A249 Sittingbourne Road junction with Hucking U Turn |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works handed over to contractor – Some works due to be carried out 15 June 2020 under High Speed Road lane closure with majority of works to be carried out under a separate road closure July 2020 |
Lidsing Road junction Dunn Street Road |
Boxley |
Signing and lining improvements |
Jennie Watson |
Works handed over to contractor 30/5/2020 – Works on site due to be carried out August 2020 |
Dean Street junction Heath Road crossroads |
Coxheath |
Signing and lining improvements |
Jennie Watson |
Detailed design currently being carried out – Scheme due to be handed over to contractor 31/7/2020 |
Loose Road junction Armstrong Road |
Maidstone |
Signing and lining improvements |
Clare Venner |
Detailed design stage – Due to be handed over to contractor 13/7/2020 |
Lenham Road |
Headcorn |
Signing and lining improvements |
Jennie Watson |
Scheme handed over to contractor 15/4/2020 – Works due to be start on site July 2020 |
Tonbridge Road junction Westree Road |
Maidstone |
Signing and lining improvements |
Clare Venner |
Detailed design stage – Works due to be handed over to contractor 31/8/2020 |
Heath Road – near Stockett Lane junction |
Coxheath |
Upgrade signing and refresh existing lining plus upgrade beacons on northern zebra crossing |
Jennie Watson |
Detailed design stage – Works due to be handed over to contractor 31/7/2020 |
Roundabout at M20 J7 (A249) |
Boxley |
Signing and lining improvements |
Christopher Koningen |
Detailed design stage – Works due to be handed over 13/7/2020 |
Externally Funded Schemes
The Schemes Planning & Delivery team is implementing schemes within the borough of Maidstone funded by external corporations whilst still meeting KCC’s strategic targets with the road network.
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
East Farleigh Bridge |
East Farleigh |
Upgrade of signing and lining for bridge width restriction |
Paul Leary |
Stage 3 road safety audit received for build-out on Farleigh Lane. Contractor to install missing hatching road markings on approach. |
Mote Park Cycleway (Phase 1) |
Maidstone |
Upgrade of cycle route |
Paul Leary |
Works complete on site. Scheme currently being monitored as part of the contractor’s maintenance period. |
Mote Park Cycleway (Phase 2) |
Maidstone |
Signing and road marking improvements between Chancery Lane and Maidstone House |
Paul Leary |
Works complete on site December 2019. Scheme currently being monitored as part of the contractor’s maintenance period. |
Walderslade Woods |
Boxley |
Reduction of speed limit to 50mph and associated traffic calming measures |
Jennie Watson |
Traffic Regulation Order for speed limit Notice of Intent advertised 12 June until 6 July 2020 for consultation – Scheme due to be handed over to contractor 30/10/2020 |
North Street – Outside Sutton Valence School |
Sutton Valence |
Installation of bollards to deter parking and damage to verges |
Whitney Gwillim |
Scheme handed over to contractor 21/5/2020. Works complete on site. Please note that 4 No. additional bollards are to be installed as vehicles are still accessing verges following completion of works |
A229 Cranbrook Road/High Street |
Staplehurst |
Virtual Traffic Calming Scheme |
Paul Leary |
Currently at outline design stage – scheme due to be handed over to contractor 30/9/2020 |
Pheasant Lane |
Maidstone |
New cycle route |
Paul Leary |
Currently at outline design stage - scheme due to be handed over to contractor 28/8/2020 |
Local Growth Fund
Local Growth Fund programme update for the Maidstone District.
The Department for Transport (DfT) added Ł100m to the Local Growth Fund (LGF) pot in order to fund Local Sustainable Transport Fund Style schemes. KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion. The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.
The schemes aim to:
· improve access to employment and services
· reduce the need to travel by the private car
· enhance pedestrian, cycle and public transport facilities
· improve sustainable transport connections
The following schemes have been submitted as part of the successful Kent Thameside/West Kent (delete as applicable) LSTF this financial year.
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
Week Street junction with Station Road |
Maidstone |
A highway improvement consisting of a raised table and improvements to 2 pedestrian crossings to better link Week Street to Maidstone East Rail Station |
Alan Osuoha
|
Detailed design progressing with a view to implement October 2020 pending support approvals |
Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers as listed Jamie Hare, Aaron Divall, Steven Noad, Andy Padgham, Steve A Stickels |
Scheme Name |
File Ref. |
Officer |
Parish |
Description of Works |
Current Status |
BP Tudor Service Station, London Road |
MA003072 |
CV |
Allington |
Alterations to existing access |
Pedestrian crossing point & signage to complete |
Bell Farm, North Street |
MA003098 |
SN |
Barming |
New accesses to split sites, shared surface and new crossing point |
Highway works completed. Stage 3 Safety Audit Awaited. |
Cross Keys |
MA003100 |
JH |
Bearsted |
New access, crossing point and parking area |
Works underway |
Barty Farm, Roundwell, |
MA003278 |
AD |
Bearsted |
New Bellmouth and Lining works |
Works Progressing |
Bicknor Road |
MA003256 |
AP |
Bicknor |
Formation of hard surfaced passing places |
Awaiting technical approval |
Heath Road/Church Street |
MA003111 |
AP |
Boughton Monchelsea |
New access, footway works, yellow lines and crossing upgrade |
Completion of footway still outstanding along with defects picked up. |
Hubbards Lane |
MA003084 |
CV |
Boughton Monchelsea |
Two accesses to minor developments |
Works substantially completed |
Lyewood Farm, Green Lane |
MA3247 MA3248 |
AP |
Boughton Monchelsea |
New housing development and access |
S278 agreement signed, works delayed due to Covid 19, due to continue 7 July 2020
|
Goya Development, St Michaels Close, Aylesford |
MA003123 |
CV |
Boxley |
New access and f/way works to new commercial properties |
Works complete except for new gulley. Works due shortly |
Maidstone Studios, New Cut Road |
MA003110 |
AP |
Boxley |
Zebra crossing and pedestrian crossing points |
High Friction works by KCC at developers’ cost. Now in maintenance. |
St Michaels Close, Aylesford |
MA003103 |
CV |
Boxley |
Waitrose car park, new access |
At end of Maintenance. |
Forstal Lane |
Ma003141 |
AP |
Coxheath |
Widening of road and new footpath with access to new development |
Works completed
|
Heath Road (North side) |
MA003063 |
CV |
Coxheath |
New access and Footway work |
Works in maintenance |
Heath Road, Coxheath |
MA003134 |
CV |
Coxheath |
New access and new footway adj. Medical centre |
Works completed |
Land north of Heath Road Phase 2 |
MA3257 |
AP |
Coxheath |
Access to new development |
Works still outstanding to include resurface of road and build out |
Linden Farm, Stockett Lane |
MA003107 |
AP |
Coxheath |
Access to new development and footway link to community hall |
2 accesses to restore to footway near completion of development. |
Gatland House, Gatland Lane |
MA003081 |
CV |
Fant |
Parking restrictions, signage, road markings and tactile crossings for new school |
Works completed, Remedials to do |
Bell Farm, Ashford Road |
MA003094 |
CV |
Harrietsham |
Realignment of Church Road to form new access onto A20. New footway along A20 |
Works in maintenance. |
Mayfield Nursery, Ashford Road |
MA003135 |
AP |
Harrietsham |
New access and alterations to existing Highway to adjoin upcoming Scheme Works |
Works now in maintenance |
Forge Meadows |
MA3253 |
AP |
Headcorn |
Access to 2 new properties and vehicle crossovers to existing properties |
Agreement signed. Awaiting start date from developer. |
Gibbs Farm Grigg Lane & Wheeler Street |
MA3250 |
SAS |
Headcorn |
Access Gibbs Farm development, zebra crossing on Wheeler Street |
Agreement signed, works commenced. |
Grigg Lane, Lenham Road,
|
MA003050 |
CV |
Headcorn |
Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane |
New accesses Grigg Lane and Lenham Road & new footway Grigg Lane in maintenance |
Kings Road/Millbank |
MA3262 |
AP |
Headcorn |
Signalised crossroads (linked to Ulcombe Road MA3150) |
Works completed. Maintenance period to commence when all requirements have been met. |
Lenham Road (North side) |
MA003062 |
CV |
Headcorn |
New Footway to site and extension of speed limit boundary |
Works in Maintenance |
Lenham Road (South side) |
MA003057 |
CV |
Headcorn |
New footway |
Revised design received |
Oak Lane and Wheeler Street |
MA003048 |
CV |
Headcorn |
New footway plus junction improvements |
Works completed and in maintenance |
Ulcombe Road |
MA003150 |
AP |
Headcorn |
Access to new development |
Defects to be completed. |
Wheeler Street, Headcorn |
MA003137 |
AP |
Headcorn |
New access off Kingsland Grove and footway works on Wheeler Street |
Works in maintenance |
Eyhorne Street |
MA3198 |
AP |
Hollingbourne |
New access to development |
Works completed. First certificate to be issued when requirements have been met. |
Bentletts Yard, Claygate Road, Laddingford |
MA003357 |
AP |
Laddingford |
New footway and replaced surface to existing access |
Surface course to be completed |
8 Faversham Road |
MA003032 |
CV |
Lenham |
New access |
In maintenance, streetlight to replace |
Old Ashford Road |
MA003018 |
CV |
Lenham |
New footway plus access |
Approaching end of maintenance, bus stop location to amend. |
The Paddocks, Ashford Road (Grove House, Old Ashford Road) |
MA3114 |
CV |
Lenham |
New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd |
Works completed, finishing/remedials required. |
Westwood Park, Ham Lane |
MA003305 |
AP |
Lenham |
Main and emergency accesses to new housing dev. |
Technical approval granted. Awaiting completion of agreement. |
Old Ashford Road, Adj Groom Way |
MA003356 |
AP |
Lenham |
New access and footway |
Awaiting Technical Approval |
Heath Road |
MA3326 |
JH |
Linton |
New Access |
Awaiting start date |
Wares Farm, Linton Hill |
MA003353 |
AP |
Linton |
New access |
Works commenced surface course outstanding |
Royal Engineers Rd/Mill Lane |
MA3312 |
JH |
Maidstone |
Access to New Development |
Under Technical Review
|
531 Tonbridge Road |
MA003045 |
CV |
Maidstone |
Service layby for new retail unit |
In maintenance |
Bicknor Green, Gore Court Road |
MA003053 |
AD |
Maidstone |
Change of road priorities and widening / upgrading |
Works complete |
Hartnup Street |
MA003138 |
SP |
Maidstone |
New Access |
Works complete now in maintenance. |
Hermitage Lane, (opp. Maidstone Hospital) |
MA003060 |
AD |
Maidstone |
New Traffic signal junction |
Near to adoption |
Hermitage Lane/ Howard Drive |
MA003070 |
AD |
Maidstone |
New access for development (opposite the quarry entrance) |
Works complete |
Howard Drive |
MA003303 |
AD |
Maidstone |
Junction works to facilitate Bus Gateway entrance to Croudace site |
Works Started |
Maidstone School of Science, New Cut Road |
MA003197 |
AP |
Maidstone |
New access to School and New roundabout and alterations to Highway |
Works completed |
McDonalds drive-through, Hart Street |
MA003013 |
CV |
Maidstone |
New access, improvements to Hart Street. |
Approaching the end of maintenance - remedial works due |
Oakapple Lane/ Hermitage Lane |
MA003046 |
AD |
Maidstone |
New bellmouth junction and associated ancillary works inc. new bus stop, for new development |
Works Complete – in maintenance |
Royal Engineers Road |
MA003127 |
JH |
Maidstone |
New footpaths to development |
Awaiting works start date |
The Poplars, Ashford Road |
MA3254 |
AP |
Maidstone |
Access to new development |
Works completed. Awaiting documents for issue of 1st certificate. |
Wallis Avenue Phase 3, Parkwood |
MA003085 |
CV |
Maidstone |
Stopping up of highway, redevelopment of car park & shops opp. Longshaw Rd |
Works in maintenance |
Week St/Gabriel’s Hill |
MA003120 |
JH |
Maidstone |
Town Centre Public Realm improvements |
Due to start maintenance |
Castle Dene, Maidstone |
MA993352 |
CV |
Maidstone |
New Access and further footway works and repairs |
Awaiting Technical Approval |
Union Street, Car Park |
MA003319 |
CV |
Maidstone |
New Access to development and footway works |
Awaiting Technical Approval |
Medway Street |
MA3326 |
JH |
Maidstone |
Subway Flood Protection Works |
Under Technical review |
Langley Park Farm |
MA003130 |
AD |
Maidstone / Langley |
New Roundabout and associated works for entrance to Countryside Estate |
Works imminent |
Albion Road, Marden |
MA003132 |
CV |
Marden |
New Access & development |
Works on going |
Goudhurst Road, Church Green (Plain Road development) |
MA3118 |
CV |
Marden |
Install Zebra crossing near rail station. |
Works in Maintenance |
Goudhurst Road/West End (Plain Road Development) |
MA3118 |
CV |
Marden |
Refurbish Zebra crossing outside school and Bus Borders to add by Library stops. |
Works in Maintenance |
Howland Road |
MA003088
|
SN |
Marden |
New development access |
Highway works completed. Stage 3 Safety Audit Awaited. |
MAP Depot, Goudhurst Road |
MA003012 |
CV |
Marden |
New bellmouth junction and footway |
Works in maintenance. Remedial works near completed and interactive speed sign awaiting installation |
Napoleon Drive and Plain Road |
MA003079 |
CV |
Marden |
New access on each road for new housing development |
Works in maintenance |
The Parsonage, Goudhurst Road |
MA003066 MA003067 |
CV |
Marden |
New access and associated upgrade works |
Access substantially completed, village gateway to be agreed |
Fishers Farm (East) Headcorn Road (Redrow) |
MA3106 |
AP |
Staplehurst |
Realignment and new access at Headcorn Road/Pile Lane junction |
Realignment complete and Pile Lane open 30mph limit change to implement |
Fishers Farm (West), Headcorn Road (Bovis) |
MA3037 |
AP |
Staplehurst |
New access onto Headcorn Road |
Works commenced on both S278 and S38 |
Hen and Duckhurst Farm, Marden Road |
MA003109 |
CV |
Staplehurst |
New Roundabout for development access |
Works on highway almost completed. HFS delayed by utility works. |
Oliver Road Staplehurst |
MA003019 |
CV |
Staplehurst |
Ped crossing to Marden Road, junction markings and bus boarders |
Works in maintenance |
Woodford Park |
MA003099 |
CV |
Staplehurst |
New access for 9 dwellings |
Works completed and on to maintenance. |
Appleacres, Maidstone Road |
MA003152 |
CV |
Sutton Valence |
Access to new development and footway works |
Technical Approval given awaiting Legal Agreement |
The Oaks, Maidstone Road |
MA003078 |
CV |
Sutton Valence |
Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing. |
Works complete |
Valdene Industrial Estate |
MA003054 |
CV |
Sutton Valence |
Upgrade of existing bellmouth and extension to f/w |
Works completed |
Cripple Street Maidstone |
MA003093 |
CV |
Tovil |
New access to development, widening and footway works |
Due for adoption – remedials due |
Site opposite cottages 129-147 Dean Street/Farleigh Hill |
MA003007 |
CV |
Tovil |
New access speed limit relocation, new footway and bus stop provision |
Works in maintenance |
Tovil Green Lane |
MA003095 |
CV |
Tovil |
New Footway and crossing point to side of site |
Works in maintenance |
Mount Ave/Blunden Lane |
MA3180 |
CV |
Yalding |
New accesses at site entrance |
Works in Maintenance |
Hampstead Lane |
MA3101 |
CV |
Yalding |
Relocate access to new development at old depot adj. station. Minor footway works |
Into maintenance period |
Vicarage Road |
MA003121 |
CV |
Yalding |
New access to development and speed restraints on existing Highway |
New Agreement required due to expiry date and works not carried out. Contents of S278 now reduced. |
Section 106 Schemes
|
||||
File Ref. |
Road Name |
Parish |
Description of Works |
Current Status |
18/19-S106-MA-486 |
A20 Ashford Road |
Harrietsham |
Village improvement works: 2 phase approach. Phase 1 which consisted of narrowing the carriageway, widening footways to allow shared footway/cycleway, altering the controlled crossing, provision of central islands and changes to the speed limits and associated signing and lining. Phase 2 will include relocating street lighting columns to better suit the new road layout and to extend the lighting to include the 30mph limit. Resurfacing of the carriageway to hide the old white lining and then new lining to the recently installed layout. . |
Phase 1 Works completed in June 2019.
Phase 2 Works, the micro surfacing and road markings are now complete. The streetlighting work has started on site. |
18/19-S106-MA-819 |
Linton Crossroads |
Linton/Loose |
Junction/signal upgrade |
No change from previous report - Finalising designs however the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. Environmental Impact Assessment and Ecological appraisal being undertaken. |
TBC |
Hermitage Lane |
Maidstone |
Cycleway improvements between rail station and hospital on east side |
Detailed designs are progressing with a view to implementation in the last quarter of this financial year pending availability of road space. |
Parish Council Funded Schemes |
||||
File Ref. |
Road Name |
Parish |
Description of Works |
Current Status |
2021-EXT-MA-1232
|
Linton Hill |
Linton |
Traffic Calming Scheme |
Detailed Design stage – Scheme is due to be handed over to contractor 30/7/2020 |
2021-CMG-MA-1252
|
Village Centre |
Boughton Monchelsea |
20mph scheme |
Detailed Design stage – Handover date to contractor to be confirmed |
2021-EXT-MA-1000
|
Grafty Green |
Boughton Malherbe |
Traffic Calming Scheme |
Detailed Design stage – Scheme is due to be handed over to contractor 28/9/2020 |
Appendix F – Bridge Works
Bridge Works – Contact Officer: Earl Bourner |
|||
Road Name |
Parish |
Description of Works |
Current Status |
No works planned |
Appendix G – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler
|
||
Location |
Description of Works |
Current Status |
B2162 Twyford Bridge, Yalding |
Refurbishment of traffic signals |
Completed April 2020 |
Heath Road / Hermitage Lane, Barming |
Addition of pedestrian crossing facility |
Summer 2020 |
Appendix H - Combined Member Grant programme update
Member Highway Fund programme update for the Maidstone District.
The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are
· in design
· at consultation stage
· about to be programmed
· Recently completed on site.
The list is up to date as of 16/6/20.
The details given below are for highway projects only. This report does not detail
· Contributions Members have made to other groups such as parish councils
· highway studies
· traffic/ non-motorised user surveys funded by Members.
More information on the schemes listed below can be found by contacting the District Manager for the Maidstone district, Susan Laporte.
Dan Daley and Rob Bird
Details of Scheme |
Status |
2021-CMG-MA-1003 – Hildenborough Crescent, Maidstone
20mph scheme
|
Detailed design being carried out – Scheme due to be handed over to contractor 28/9/2020 – Scheme to be implemented October/November 2020 |
2021-CMG-MA-1000 – Blackmanstone Way Maidstone
Construction of footpath between estates
|
Works handed over to contractor 30/5/2020 |
2021-CMG-MA-1001 – Buckland Hill, Maidstone
20mph scheme
|
TRO currently on hold due to Covid-19 |
Details of Scheme |
Status |
21/21-CMG-MA-1252 – Heath Road, Boughton Monchelsea
Traffic Regulation Order application for speed limit reduction to 30mph |
Notice of Intent sent for advertising and consultation from 12 June until 6 July 2020
|
Shellina Prendergast
Details of Scheme |
Status |
20/21-CMG-MA-1253 – Lenham Road/Chaingate Road, Liverton Hill, Platts Heath, Lenham
Traffic Regulation Order application for speed limit reduction to 30mph
|
TRO sent for sealing – comes into effect 2 July 2020 |
20/21-CMG-MA-1254 – Lenham Road, Ulcombe
Traffic Regulation Order application for speed limit reduction to 30mph |
Notice of Intent sent for advertising and consultation from 12 June until 6 July 2020
|
1.1 Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contacts: Susan Laporte 03000 418181