Strategic Planning, Sustainability &Transportation Committee

13 SEPTEMBER 2016

Is the final decision on the recommendations in this report to be made at this meeting?

Yes

 

First Quarter Budget Monitoring 2016/17

 

Final Decision-Maker

Strategic Planning, Sustainability & Transportation Committee

Lead Head of Service

Director of Finance and Business Improvement

Lead Officer and Report Author

Ellie Dunnet, Chief Accountant

Classification

Public

Wards affected

All

 

 

This report makes the following recommendations to this Committee:

That the committee:

1.   Notes the revenue position at the end of the first quarter and the actions being taken or proposed to improve the position where significant variances have been identified.

 

 

This report relates to the following corporate priorities:

The budget is a statement, in financial terms, of the priorities set out in the strategic plan. It reflects the Council’s decisions on the allocation of resources to all objectives of the strategic plan. The issues raised in this report identify areas where financial performance is at variance with priority outcomes.

 

 

Timetable

Meeting

Date

Strategic Planning, Sustainability and Transportation Committee

13 September 2016



First Quarter Budget Monitoring 2016/17

 

 

1.        PURPOSE OF REPORT AND EXECUTIVE SUMMARY

 

1.1     This report provides the committee with an overview of the revenue budget and outturn for the first quarter of 2016/17, and highlights financial matters which may have a material impact on the medium term financial strategy or the balance sheet.

 

1.2     As at the 30 June 2016, this committee was showing a minor adverse variance of £2,560 overall.  The individual variances for each service area are detailed within Appendix I.

 

 

2.        INTRODUCTION AND BACKGROUND

 

2.1     The Director of Finance & Business Improvement is the Responsible Financial Officer, and has overall responsibility for budgetary control and financial management.  However in practice, day to day budgetary control is delegated to service managers, with assistance and advice from their director and the finance section.

 

2.2     The medium term financial strategy for 2016/17 onwards was agreed by full Council on 2 March 2016.  This report advises and updates the committee on the current position with regards to revenue expenditure against the approved budgets.

 

2.3     Attached at Appendix I is a table detailing the current budget and

expenditure position for this Committee’s services in relation to the first

quarter of 2016/17, to June 2016. The appendix details net budget per

cost centre for this Committee. Actual expenditure is shown to the end of June 2016 and includes accruals for goods and services received but not yet

paid for.

 

2.4     The columns of the table in the Appendix show the following detail:

 

a)   The cost centre description;

b)   The value of the total budget for the year;

c)   The amount of the budget expected to be spent by the end of June 2016;

d)   The actual spend to that date;

e)   The variance between expected and actual spend;

f)    The forecast spend to year end; and

g)   The expected significant variances at 31 March 2017.

 

2.5      Appendix I shows that of an annual budget of -£944,030 there was an expectation that net income of -£17,002 would be achieved in the first quarter of the year. At this point in time the budget position for this committee as a whole is a minor overspend of £2,560.  However, the full year forecast indicates that there is expected to be a net underspend of £250,000 by 31 March 2017.  This is based on current assumptions around income levels from pay and display parking.  While it should be noted that one car park (Mote Park) is not expected to achieve its income target this year, leaving a shortfall in the region of £50,000 by 31 March 2017, this will be offset by the performance of Lockmeadow and King Street car parks leaving an overall positive variance in this cost centre, forecast at £250,000 based on the information available to date.

 

2.6     A separate report detailing the shortfall for Mote Park car park was considered by Heritage, Culture and Leisure committee on 6 September.

 

2.7     Explanations for variances within individual cost centres which exceed or are expected to exceed £30,000 have been provided in accordance with the council’s constitution.

 

 

 

3     AVAILABLE OPTIONS

 

 

3.1     In considering the current position on the revenue budget at the end of

June 2016 the committee can chose to note those actions and reconsider the outcomes at the end of the second quarter or it could chose to take further action.

 

 

4         PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS

 

4.1     The committee is requested to note the content of the report and agree on any necessary action to be taken in relation to the budget position.

 

 

5         CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK

 

5.1     This report is not expected to lead to any consultation.

 

 

6         NEXT STEPS: COMMUNICATION AND IMPLEMENTATION OF THE DECISION

 

6.1     The second quarter’s budget monitoring reports will be presented to service committees for their consideration in November 2016.

 

 

6.2     Currently there are no matters which require a decision from this committee.  Significant variances which require action to be taken will be regularly reported to this committee through later versions of this report.

 

 

7         CROSS-CUTTING ISSUES AND IMPLICATIONS

 

Issue

Implications

Sign-off

Impact on Corporate Priorities

This report monitors actual activity against the revenue budget and other financial matters set by Council for the financial year.  The budget is set in accordance

with the Council’s medium term

financial strategy which is linked to the strategic plan and corporate priorities.

Director of Finance & Business Improvement

Risk Management

The Council has produced a

balanced budget for both capital and revenue expenditure and income for 2016/17 This budget is

set against a backdrop of limited resources and an difficult economic climate. Regular and comprehensive monitoring of the type included in this report ensures early warning of significant issues

that may place the Council at

financial risk. This gives this

committee the best opportunity to take actions to mitigate such risks.

The issues set out in this report do not exhibit the level of potential risk identified in previous years.

Director of Finance & Business Improvement

Financial

Financial implications are the focus of this report through high level budget monitoring. The process of budget monitoring ensures that

services can react quickly to

potential resource problems. The process ensures that the Council is not faced by corporate financial problems that may prejudice the delivery of strategic priorities.

Director of Finance & Business Improvement

Staffing

The budget for staffing represents approximately 50% of the direct spend of the council and is carefully

monitored. Any issues in relation to employee costs will be raised in this and future monitoring reports.

Director of Finance & Business Improvement

Legal

The Council has a statutory

obligation to maintain a balanced budget this monitoring process

enables the committee to remain aware of issues and the process to be taken to maintain a balanced budget for the year.

Team Leader Corporate Governance

Equality Impact Needs Assessment

The budget ensures the focus of resources into areas of need as identified in the Council’s strategic priorities. This monitoring report ensures that the budget is delivering services to meet those needs.

Director of Finance & Business Improvement

Environmental/Sustainable Development

No specific issues arise.

Director of Finance & Business Improvement

Community Safety

No specific issues arise.

Director of Finance & Business Improvement

Human Rights Act

No specific issues arise.

Director of Finance & Business Improvement

Procurement

No specific issues arise.

Director of Finance & Business Improvement

Asset Management

Resources available for asset

management are contained within both revenue and capital budgets and do not represent a significant problem at this time.

Director of Finance & Business Improvement

 

8         REPORT APPENDICES

 

The following documents are to be published with this report and form part of the report:

·         Appendix I: First Quarter 2016/17 Revenue Monitoring – Strategic Planning, Sustainability and Transportation

 

 

9         BACKGROUND PAPERS

 

None