Executive Summary .2
Revenue Spending 3
Significant Variances ..7
Capital Spending . ..9
Executive Summary
This report is intended to provide Members with an overview of performance against revenue and capital budgets and outturn for the 2018/19 financial year for the services that fell within the remit of the Heritage, Culture and Leisure (HCL) Committee.
Robust budget monitoring is a key part of effective internal financial control, and therefore is one of the elements underpinning good corporate governance.
The aim of reporting financial information to service committees at quarterly intervals is to ensure that underlying trends can be identified at an early stage, and that action is taken to combat adverse developments or seize opportunities.
It is advisable for these reports to be considered in conjunction with quarterly performance monitoring reports, as this may provide the context for variances identified with the budget and general progress towards delivery of the Councils strategic priorities.
Headline messages for this year are as follows:
§ For this Committee, there is an underspend against the revenue budget of £22,000.
§ Capital expenditure totalling £3.203m has been incurred during 2018/19 for the projects which sat within the remit of the HCL Committee. This represents slippage of £0.611m.
![]() |
At the end of the year, there is an overall positive variance of £22,000 against the revenue budget for the HCL Committee.
The budgets for each service committee now include a figure for assumed salary slippage to reflect the forecast level of vacant posts across the year. This was previously shown as a figure for the whole Council as part of the budget monitoring report for this Committee.
As illustrated by the chart below all committees stayed within their expenditure budgets with the exception of Policy & Resources Committee, although this is offset by income in excess of the budget figure. The remaining committees have all underachieved on their income budgets.
Chart 1 Performance against budget analysed by service committee (Expenditure)
Chart 2 Performance against budget analysed by service committee (Income)
The table on the following page details the budget and expenditure position for the HCL Committees services at the end of 2018/19. These figures represent the net budget for each cost centre. The actual position includes expenditure for goods and services which we have received but not yet paid for.
The columns of the table show the following detail:
a) The cost centre description;
b) The value of the total budget for the year;
c) The actual spend to that date;
d) The variance between expected and actual spend;
The table shows that £2.016m was spent against a net annual expenditure budget of £2.038m, representing an underspend of £22,000.
Revenue Budget Summary Q4 2018/19
Cost Centre (a) |
Budget for Year (b) |
Outturn (c) |
Variance (d) |
|
£000 |
£000 |
£000 |
Cultural Development Arts |
13 |
10 |
3 |
Museum |
326 |
284 |
41 |
Carriage Museum |
29 |
29 |
-1 |
Museum-Grant Funded Activities |
61 |
59 |
2 |
Museum Cafe |
0 |
4 |
-4 |
Hazlitt Arts Centre |
268 |
268 |
-0 |
Festivals and Events |
-21 |
-14 |
-7 |
Lettable Halls |
-3 |
-7 |
4 |
Community Halls |
83 |
59 |
24 |
Leisure Centre |
-222 |
-235 |
13 |
Mote Park Adventure Zone |
-57 |
0 |
-57 |
Cobtree Golf Course |
-53 |
-48 |
-6 |
Parks & Open Spaces |
1,017 |
1,074 |
-57 |
Playground Maintenance & Improvements |
128 |
85 |
43 |
Parks Pavilions |
24 |
20 |
4 |
Mote Park |
232 |
283 |
-51 |
Mote Park Cafe |
-43 |
-25 |
-18 |
Allotments |
13 |
11 |
2 |
Tourism |
31 |
29 |
3 |
Museum Shop |
-19 |
-4 |
-14 |
Leisure Services Other Activities |
34 |
22 |
13 |
Cemetery |
61 |
51 |
10 |
National Assistance Act |
-0 |
-0 |
-0 |
Crematorium |
-754 |
-855 |
101 |
Maintenance of Closed Churchyards |
6 |
2 |
3 |
Community Environmental Engagement |
9 |
9 |
0 |
Market |
-132 |
-93 |
-39 |
Leisure Services Section |
55 |
37 |
18 |
Cultural Services Section |
579 |
537 |
43 |
Visitor Economy Section |
128 |
121 |
7 |
Bereavement Services Section |
208 |
218 |
-9 |
Market Section |
87 |
85 |
2 |
Salary Slippage |
-50 |
0 |
-50 |
|
2,038 |
2,016 |
22 |
Table 1 Revenue Budget Position 2018/19 Heritage, Culture & Leisure Committee
Significant Variances
Within these headline figures, there are a number of adverse and favourable variances for individual service areas. This report draws attention to the most significant variances, i.e. those exceeding £30,000 , and the table below provides further detail regarding these variances.
|
Positive Variance Q4 |
Adverse Variance Q4 |
Year End Variance |
Heritage, Culture & Leisure Committee |
£000 |
||
Museum This variance has arisen from an underspend on running costs, with the most significant element being repair and maintenance costs. These costs fluctuate between years and it is expected that they will even out over time. |
41 |
|
|
Mote Park Adventure Zone The facility did not open during 2018/19 as planned, however it has now opened. |
|
-57 |
|
Parks & Open Spaces A budget saving was planned in this area which is being achieved through increased income from the Grounds Maintenance service. This income is accounted for within the remit of the Communities, Housing & Environment Committee but the saving is accounted for here and therefore appears as an overspend. |
|
-57 |
|
Playground Maintenance & Improvements Funding had been set aside for spare/replacement equipment. However resources were available in the capital budget for this expenditure. |
43 |
|
|
Mote Park This variance covers several areas, the most significant of which were insurance claim excesses, additional sewage costs following the leak in the park and a shortfall in income from fairs and circuses. |
|
-51 |
|
Crematorium There was significant additional income achieved, particularly from memorial subscriptions and renewals and cremation fees. |
101 |
|
|
Market This variance is a combination of additional running costs from increased trade refuse collection charges and additional service charge costs, and a shortfall in income from the markets. |
|
-39 |
|
Cultural Services Section - This variance is mainly due to staff vacancies. Underspends of this nature were anticipated when setting the budget and are reflected in the line salary slippage (see below) |
43 |
|
|
Salary Slippage- Assumed saving from normal level of turnover in staff. The actual savings are reflected in individual cost centres. |
|
-50 |
|
Table 2 Significant Variances Heritage, Culture & Leisure Committee
![]() |
Capital Spending
The five year capital programme for 2018/19 onwards was approved by Council on 7 March 2018. Funding for the programme remains consistent with previous decisions of Council in that the majority of capital resources come from New Homes Bonus along with a small grants budget.
The outturn position for 2018/19 is set out in the table below. For the year expenditure totaling £3.203m has been incurred against a budget of £3.814m, which represents slippage of £0.611m.
Capital Budget Summary 2018/19
Capital Programme Heading |
Revised Estimate 2018/19 |
Outturn 2018/19 |
Budget Remaining |
Budget Not Required |
|
£000 |
£000 |
£000 |
£000 |
|
|
|
||
Continued Improvements to Play Areas |
574 |
152 |
422 |
|
Commercial Projects - Crematorium Projects |
416 |
536 |
-120 |
|
Commercial Projects - Mote Park Adventure Zone |
1,957 |
2,233 |
-276 |
|
Mote Park Improvements |
391 |
17 |
374 |
|
Mote Park Visitor Centre |
150 |
118 |
32 |
|
Mote Park Lake - Dam Works |
200 |
133 |
67 |
|
Other Parks Improvements |
100 |
100 |
|
|
Museum Development Plan |
25 |
14 |
11 |
|
Total |
3,814 |
3,203 |
611 |
|
|
|
|
|
|
Table 3 Capital Expenditure 2018/19
§ The overspend at the Crematorium has arisen due to greater than forecast costs for the new car park element of the project. The background to this and the future funding of the project was the subject of a report to the HCL Committee on 2 April 2019.
§ Members will be aware from previous reports to the HCL Committee that substantial additional costs were incurred as a result of the sewage leak that occurred in the park. These costs are included above but it is hoped that some or all of them may be recovered via a claim that the Council has made against Southern Water.