AUDIT, GOVERNANCE & STANDARDS COMMITTEE |
18 NOVEMBER 2019 |
|||
|
||||
Internal Audit Interim Report 2019/20 |
||||
|
||||
Final Decision-Maker |
Audit, Governance & Standards Committee |
|||
Lead Head of Service |
Rich Clarke, Head of Audit Partnership |
|||
Lead Officer and Report Author |
Rich Clarke, Head of Audit Partnership |
|||
Classification |
Public |
|||
Wards affected |
All |
|||
|
||||
Executive Summary and Purpose of Report |
||||
The report summarises, for Member information, progress towards delivering the 2019/20 Audit & Assurance Plan approved by this Committee on 19 March 2019.
|
||||
|
||||
This report makes the following recommendations to this Committee: |
||||
1. That progress so far on completing the 2019/20 Audit and Assurance Plan be noted.
|
||||
|
|
|||
Timetable |
||||
Meeting |
Date |
|||
Audit, Governance & Standards Committee |
18 November 2019 |
|||
Internal Audit Interim Report 2019/20 |
|
1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Issue |
Implications |
Sign-off |
Impact on Corporate Priorities |
We do not expect the recommendations will by themselves materially affect achievement of corporate priorities. However, they will support the Council’s overall achievement of its aims by promoting good governance. |
Rich Clarke Head of Audit Partnership
7 November 2019 |
Cross Cutting Objectives |
The report recommendation supports achievement of cross cutting objectives by supporting good governance. |
|
Risk Management |
No additional implications.
|
|
Financial |
We will continue towards delivering the plan within already agreed budgets. |
|
Staffing |
We will continue towards delivering the plan within agreed staffing levels. |
|
Legal |
Accepting the recommendation will help the Council towards meeting its obligations under the Accounts & Audit Regulations 2015. |
|
Privacy and Data Protection |
No new implications. |
|
Equalities |
No new implications |
|
Public Health |
No new implications |
|
Crime and Disorder |
No new implications |
|
Procurement |
No further procurement exercises required. |
2. INTRODUCTION AND BACKGROUND
2.1 This Committee approved the 2019/20 Audit and Assurance Plan at its meeting on 19 March 2019. This report summarises progress towards delivering the plan up to the end of October, as it works towards culminating in a Head of Audit Opinion in July 2020.
3. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
3.1 We present the report for Member information and for noting.
4. CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK
4.1 The format and information presented in the report builds on Committee feedback to previous audit summary reports.
5. REPORT APPENDICES
· Appendix 1: Internal Audit Interim Report 2019/20
6. BACKGROUND PAPERS
Full audit reports supporting the summarised findings are available on request.