To: Maidstone Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 13th January 2021
Subject: Highway Forward Works Programme – 2020/21 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2020/21 and 2021/22) and Year Three to Five (2022/23 to 2024/25) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2020/21, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
- Casualty Reduction Measures
- Externally funded schemes
- Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Winter Report – see Appendix I
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent
Susan Laporte Maidstone District Manager
Alan Casson Strategic Asset Manager
Earl Bourner Drainage & Structures Asset Manager
Sue Kinsella Street Light Asset Manager
Toby Butler Traffic & Network Solutions Asset Manager
Jamie Hare Development Agreements Manager
Jamie Watson Schemes Programme Manager
Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Mr Byron Lovell |
|||
Road Name |
Parish |
Extent of Works |
Current Status |
A20 London Road/A26 Rocky Hill |
Maidstone |
Maidstone Gyratory to Terrace Road |
Completed |
B2012 Lower Boxley Road |
Maidstone |
Between Stacey's Street and Wheeler Street |
Completed |
Square Hill Road |
Maidstone |
A20 Ashford Road to Mote Road |
To be programmed early 2021 |
Mote Avenue |
Maidstone |
A249 Mote Road to Willow Way |
To be programmed early 2021 |
Fishers Estate |
Staplehurst |
Fishers Road/Hurst Close/Newlyn Drive/Fishers Close |
To be programmed early 2021 |
Union Street |
Maidstone |
Between A249 Sittingbourne Road and Wheeler Street |
To be programmed early 2021 |
Footway Improvement - Contact Officer Mr Neil Tree |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Roseleigh Avenue |
Allington |
Full length Including Kenward Road and Glenwood Close (Footway resurfacing) |
Designed and programmed to commence in January 2021.
|
St. Michaels Road |
Maidstone |
Various sections throughout the entire length. (Footway resurfacing)
|
To be designed and Programmed. |
Sheppey Road |
Loose |
Full length including Lismore Close (Footway Protection) |
Completed
|
|
Loose |
Full length (Footway Protection) |
Completed
|
Dane Court |
Coxheath |
Full length (Footway Protection) |
Completed
|
Hildenborough Crescent |
Allington |
Full length (Footway Protection) |
Completed
|
Sussex Road |
Maidstone |
Full length (Footway Protection) |
Completed
|
Spencer Way |
Maidstone |
Full length (Footway Protection) |
Completed
|
Garden Close |
Maidstone |
Full length (Footway Protection) |
Completed
|
Freeman Way |
Maidstone |
Full length (Footway Protection) |
Completed
|
Wilson Close |
Maidstone |
Full length (Footway Protection) |
Completed
|
Ware Street |
Bearsted |
From Sandy Lane to the vicinity of The White Horse Public House (Footway Protection)
|
Completed
|
Mount Avenue |
Yalding |
Full length (Footway Protection) |
Completed
|
Downs Road |
Yalding |
Full length (Footway Protection) |
Completed
|
Blunden Lane |
Yalding |
Full length (Footway Protection) |
Completed
|
Adisham Road |
Allington |
Full length (Footway Protection) |
Completed
|
Blackmanstone Way |
Allington |
Full length (Footway Protection) |
Completed
|
Cheriton Way |
Allington |
Full length (Footway Protection) |
Completed
|
Chilham Road |
Allington |
Full length (Footway Protection) |
Completed
|
Eastry Close |
Allington |
Full length (Footway Protection) |
Completed
|
Fordwich Close |
Allington |
Full length (Footway Protection) |
Completed
|
Frinstead Walk |
Allington |
Full length (Footway Protection) |
Completed
|
Halstead Walk |
Allington |
Full length (Footway Protection) |
Completed
|
Kilndown Close |
Allington |
Full length (Footway Protection) |
Completed
|
Lamberhurst Close |
Allington |
Full length (Footway Protection) |
Completed
|
Surface Treatments – Contact Officer Mr Jonathan Dean |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
GOUDHURST ROAD (INC WINCHET HILL) |
Marden |
Lower Ladysden Farm (Pumpkin Farm) to Sherenden Lane |
Completed |
BENOVER ROAD AND COLLIER STREET |
Yalding |
From LupoFresh to Haviker Street |
Completed |
HEATH ROAD |
Coxheath |
Stockett Lane to Vanity Lane |
Completed |
HEATH ROAD |
Coxheath |
Wood lands to Ewell Lane |
Completed |
MAIDSTONE ROAD |
Nettlestead |
Wheelbarrow Roundabout to Bow Road |
Completed |
LENHAM ROAD |
Kingswood |
Gravelly Bottom Road to Chegworth Lane |
Completed |
HACKNEY ROAD |
Fant |
From Unicumes Lane to Gatland Lane |
Postponed to 2021 |
GRAVELLY BOTTOM ROAD |
Lenham |
Lenham Road to Broomfield Road |
Completed |
SANDLING LANE |
Penenden Heath |
From Boxley Road to The Gateway |
Completed |
SOUTHERNDEN ROAD (INCLUDING GRIGG LANE) |
Egerton |
Barhams Mill Road to just past Sherway Road (Horseshoes Farm) |
Completed |
TILDEN LANE |
Marden |
Stilebridge Lane to Khernfields Farmhouse |
Completed |
SHERIDAN CLOSE |
Ringlestone |
From junction of Dickens Road to outside 26 |
Completed |
BUNCE COURT ROAD |
Otterden |
Otterden Place (Rigshill Road) to Warren Street (Payden Street) |
Completed |
WHEELERS LANE |
|
Linton Hill to Vanity Lane |
Completed |
NORTHDOWN CLOSE |
Maidstone |
Whole Road |
Completed |
Appendix B - Drainage
Drainage Repairs & Improvements - Contact Officer Earl Bourner |
|||
Parish |
Description of Works |
Current Status |
|
Dunn Street |
Bredhurst |
Repair broken pipe and replace one of the two existing soakaways due to it reaching the end of its useful life. |
Job Passed to Contractor. Delivery programmed Easter 2021 due to lack of road space availability |
Eyhorne/Upper Street/Hollingbourne Hill |
Hollingbourne |
Various repairs to the highway drainage system completed. Further work required to reinstate outfall to pond. |
In liaison with landowners to reach agreement on scope of works |
A20 Ashford Rd under rail bridge by Square Hill |
Maidstone |
The existing drainage has been cleaned and surveyed and is working but an improvement scheme is to be developed to reduce risk of blockages and flooding |
Scheme design underway with consultant engineers |
Harp Farm Road |
Boxley |
Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered |
Entered onto Forward Work Programme for FY21/22 |
Fairmeadow Subway (near Medway Street) |
Maidstone |
Faulty non-return valve and damaged Aco channel drainage covers. |
Replacement Aco channels fitted. Still awaiting approval from the EA to replace non-return valve. |
Gravelly Bottom Road |
Kingswood |
Multiple defects found in CCTV survey |
Majority of works have been completed here. One additional section of pipework requires replacing. Job to be raised asap |
Tonbridge Road |
Teston |
Flooding affecting properties between The Orpines and Church Street. Replacement drainage being designed. Underground utilities are main constraint for delivery |
Job Passed to Contractor for delivery mid Jan 2021
|
Appendix C – Street Lighting
Structural testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer Sue Kinsella
|
||||
Road Name |
Column |
Parish |
Description of Works |
Status |
Brishing Lane |
KBFE010 |
Maidstone |
Replacement of Street Light |
Completion end April 21 |
Egerton Road |
KEAQ003 |
Ringlestone |
Replacement of Street Light |
Completion end April 21 |
Tonbridge Road |
KTBU022 |
Fant |
Replacement of Street Light |
Completion end April 21 |
Tonbridge Road |
KTBU051 |
Fant |
Replacement of Street Light |
Completion end April 21 |
Heath Road |
KHCH005 |
Heath |
Replacement of Street Light |
Completed |
St Peters Bridge |
KSCE001 |
High Street |
Replacement of Street Light |
Completion end April 21 |
King Street |
KKAM021 |
High Street |
Replacement of Street Light |
Completion end April 21 |
Loose Road |
KLCQ094 |
Maidstone |
Replacement of Street Light |
Completed |
Bicknor Road |
KBCG010 |
North Downs |
Replacement of Street Light |
Completion end April 21 |
Bicknor Road |
KBCG012 |
North Downs |
Replacement of Street Light |
Completion end April 21 |
Sutton Road |
KSGF007 |
Shepway South |
Replacement of Street Light |
Completion end April 21 |
Station Road |
KSFA021 |
Staplehurst |
Replacement of Street Light |
Completion end April 21 |
Impton Lane |
KIAC012 |
Bluebell Hill Walderslade |
Replacement of Street Light |
Completion end April 21 |
Lullingstone Road |
KLDJ005 |
Allington |
Replacement of Street Light |
Completed |
St Leonards Road |
KSHY003 |
Allington |
Replacement of Street Light |
Completed |
Stansted Close |
KSEM003 |
Allington |
Replacement of Street Light |
Completed |
Rede Wood Road |
KRAN011 |
Barming |
Replacement of Street Light |
Completion end April 21 |
Fir Tree Grove |
KBAF110 |
Boxley |
Replacement of Street Light |
Completed |
Woodlands |
KXEF001 |
Boxley |
Replacement of Street Light |
Completed |
Clement Court |
KCEG001 |
Bridge |
Replacement of Street Light |
Completed |
Bedgebury Close |
KBBK006 |
East |
Replacement of Street Light |
Completed |
Hampton Road |
KHAR021 |
East |
Replacement of Street Light |
Completed |
Hampton Road |
KHAR022 |
East |
Replacement of Street Light |
Completed |
Newenden Close |
KNAM007 |
East |
Replacement of Street Light |
Completed |
Snowdon Avenue |
KSCO015 |
East |
Replacement of Street Light |
Completed |
Rawdon Road |
KRAD001 |
High Street |
Replacement of Street Light |
Completion end April 21 |
Thornhill Place |
KTBG301 |
North |
Replacement of Street Light |
Completion end April 21 |
Cave Hill |
KCAR006 |
South |
Replacement of Street Light |
Completion end April 21 |
Cripple Street |
KCGQ013 |
South |
Replacement of Street Light |
Completion end April 21 |
Cripple Street |
KCGQ014 |
South |
Replacement of Street Light |
Completed |
Cripple Street |
KCGQ015 |
South |
Replacement of Street Light |
Completion end April 21 |
Farleigh Hill |
KFAH002 |
South |
Replacement of Street Light |
Completion end April 21 |
Farleigh Hill |
KFAH008 |
South |
Replacement of Street Light |
Completion end April 21 |
Farleigh Hill |
KFAH009 |
South |
Replacement of Street Light |
Completion end April 21 |
Pheasant Lane |
KPBI021 |
South |
Replacement of Street Light |
Completion end April 21 |
Straw Mill Hill |
KSFT006 |
South |
Replacement of Street Light |
Completion end April 21 |
Tovil Green |
KTBZ002 |
South |
Replacement of Street Light |
Completed |
Badger Road |
KBAF109 |
Boxley |
Replacement Street Light |
Completed |
Boxley Close |
KBEH005 |
North |
Replacement Street Light |
Completed |
South Road |
KSCY006 |
Marden |
Replacement Street Light |
Completed |
College Road |
KCFC008 |
High Street |
Replacement Street Light |
Completed |
Cobham Close |
KCEP001 |
Bridge |
Replacement Street Light |
Completion end April 21 |
Lower Stone Street |
KLCZ002 |
High Street |
Replacement Street Light |
Completion end April 21 |
King Street |
KKAM012 |
High Street |
Replacement Street Light |
Completion end April 21 |
King Street |
KKAM013 |
High Street |
Replacement Street Light |
Completion end April 21 |
Loose Road |
KLCQ055 |
South |
Replacement Street Light |
Completion end April 21 |
Loose Road |
KLCQ202 |
South |
Replacement Street Light |
Completion end April 21 |
Grove Road |
KGCM002 |
Shepway North |
Replacement Street Light |
Completion end April 21 |
Appendix D – Transportation and Safety Schemes
Casualty Reduction Measures
The Schemes Planning & Delivery team is implementing schemes within Maidstone District, to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status correct as of 18/12/20.
APPENDIX D1 – CASUALTY REDUCTION MEASURES - identified to address a known history of personal injury crashes
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
A20 Ashford Road/M20 Slip |
Hollingbourne |
Signing and road marking improvements |
Jennie Watson |
Works complete |
Running Horse Roundabout |
Maidstone |
Virtual lane separation system using road markings & coloured surfacing |
Rebecca Bailey |
Outline design completed November 2020. Traffic modelling required on proposals, along with stakeholder engagement. Currently anticipated for construction late 21/22 financial year. |
Chalky Road junction A249 Sittingbourne Road |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works complete |
A249 Sittingbourne Road junction Church Hill |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works complete |
A249 Sittingbourne Road junction with Hucking U Turn |
Stockbury |
Signing and lining improvements |
Jennie Watson |
Works complete |
Lenham Road |
Headcorn |
Signing and lining improvements |
Jennie Watson |
Works complete |
Tonbridge Road junction Westree Road |
Maidstone |
Signing and lining improvements |
Claire Venner |
Signing works handed over to contractor-due to be programmed. Street lighting signage 50% complete. Lining completed following resurfacing, October 20. |
Heath Road – near Stockett Lane junction |
Coxheath |
Upgrade signing and refresh existing lining plus upgrade beacons on northern zebra crossing |
Jennie Watson |
Works complete |
APPENDIX D2 – INTEGRATED TRANSPORT SCHEMES – all other LTP funded non-casualty reduction schemes
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
East Farleigh Bridge |
East Farleigh |
Upgrade of signing and lining for bridge width restriction |
Paul Leary |
Works complete |
Walderslade Woods |
Boxley |
Reduction of speed limit to 50mph and associated traffic calming measures |
Jennie Watson |
Scheme due to be handed over to contractor 26/2/2021 |
A229 Cranbrook Road/High Street |
Staplehurst |
Virtual Traffic Calming Scheme |
Demi Richards |
Scheme handed over to contractor December works - anticipated to start after April 2021 when workspace will be available. |
Pheasant Lane |
Maidstone |
New cycle route |
Paul Leary |
Scheme handed over to contractor September 2020. Works due to start on 14th December 2020. |
Appendix E – Developer and Other Externally Funded Works
Section 106 Schemes
|
||||
File Ref. |
Road Name |
Parish |
Description of Works |
Current Status |
18/19-S106-MA-486 |
A20 Ashford Road |
Harrietsham |
Village improvement works |
The streetlighting work has been completed although at present a fault has occurred on the cabling which is being investigated. It is anticipated all will be operational in January 2021. |
18/19-S106-MA-819 |
Linton Crossroads |
Linton/Loose |
Junction/signal upgrade |
No change from previous report - Finalising designs however the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. |
TBC |
Hermitage Lane |
Maidstone |
Cycleway improvements between rail station and hospital on east side |
Finalising designs however the estimated cost of the alterations is above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. A meeting has taken place with interested parties to discuss the designs as requested at the previous JTB. Looking at what can be implemented with existing Section 106 funds |
Parish Council Funded Schemes |
||||
File Ref. |
Road Name |
Parish |
Description of Works |
Current Status |
2021-EXT-MA-1232
|
Linton Hill |
Linton |
Traffic Calming Scheme |
Works taking place December 2020 |
2021-CMG-MA-1252
|
Village Centre |
Boughton Monchelsea |
20mph scheme |
Works handed over to contractor – Anticipated start date Spring 2021
|
2021-EXT-MA-1000
|
Grafty Green |
Boughton Malherbe |
Traffic Calming Scheme |
Detailed Design stage – Scheme is due to be handed over to contractor 30 January 2020 – Anticipated start date Spring 2021 |
Local Growth Fund
Local Growth Fund programme update for the Maidstone District.
The Department for Transport (DfT) added £100m to the Local Growth Fund (LGF) pot to fund Local Sustainable Transport Fund Style schemes. KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion. The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.
The schemes aim to:
· improve access to employment and services
· reduce the need to travel by the private car
· enhance pedestrian, cycle, and public transport facilities
· improve sustainable transport connections
The following schemes have been submitted as part of the successful Kent Thameside/West Kent (delete as applicable) LSTF this financial year.
Scheme |
Status |
Works on the station improvements commenced in January 2020, with the temporary ticket office installed by South Eastern operational since January 2020. Contract Completion date has been delayed due to emerging changes to designs in some areas and working restrictions due to COVID 19 with an estimated completion of March 2021. While works on the public realm area are progressing, restrictions on internal works in the station building necessitate different working practices, creating inefficiency and slowing progress. Artist impression images of the final design have been attached to the site hoarding to provide the public with a vision for the scheme. KCC Schemes team are working closely with NR, SE, and MBC to co-ordinate the highway & forecourt design with the raised table. A site meeting to take place late 21st December to co-ordinate a start date of the Week Street project in the Feb ’21 school holidays. MBC are progressing with the wayfinding design which will tie in the wider improvement works. SE have awarded the contractor to complete the additional works within the funding timescales. However, they have a strong dependency on the completion of the forecourt works delivered by Network Rail and are working together to monitor progress and will phase their works accordingly. |
|
|
|
Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers as listed Jamie Hare, Aaron Divall, Steven Noad, Andy Padgham, Sarah Parris, Steve A Stickels |
Scheme Name |
File Ref. |
Officer |
Parish |
Description of Works |
Current Status |
BP Tudor Service Station, London Road |
MA003072 |
CV |
Allington |
Alterations to existing access |
Outstanding Pedestrian crossing point & signage being pursued |
Bell Farm, North Street |
MA003098 |
SN |
Barming |
New accesses to split sites, shared surface, and new crossing point |
Highway works completed. Stage 3 Safety Audit Awaited. |
Cross Keys |
MA003100 |
JH |
Bearsted |
New access, crossing point and parking area |
Works underway |
Barty Farm, Roundwell, |
MA003278 |
AD |
Bearsted |
New Bellmouth and Lining works |
Works Complete |
Bicknor Road |
MA003256 |
AP |
Bicknor |
Formation of hard surfaced passing places |
Awaiting technical approval |
Heath Road/Church Street |
MA003111 |
SP |
Boughton Monchelsea |
New access, footway works, yellow lines and crossing upgrade |
Completion of footway still outstanding along with defects picked up, and drainage issues. |
Hubbards Lane |
MA003084 |
CV |
Boughton Monchelsea |
Two accesses to minor developments |
Works substantially completed |
Lyewood Farm, Green Lane |
MA3247 MA3248 |
AP |
Boughton Monchelsea |
New housing development and access |
Works near completed
|
Goya Development, St Michaels Close, Aylesford |
MA003123 |
SP |
Boxley |
New access and f/way works to new commercial properties |
Works complete Await ok from Drainage team re new gully as was not inspected. |
Maidstone Studios, New Cut Road |
MA003110 |
SP |
Boxley |
Zebra crossing and pedestrian crossing points |
Awaiting final info for Cert 2 |
St Michaels Close, Aylesford |
MA003103 |
SP |
Boxley |
Waitrose car park, new access |
Final Defects to be carried out prior to Cert 2 |
Forstal Lane |
Ma003141 |
SP |
Coxheath |
Widening of road and new footpath with access to new development |
Works completed, however drainage issues and defects so one-year maintenance not yet started |
Heath Road (North side) |
MA003063 |
CV |
Coxheath |
New access and Footway work |
Works in maintenance |
Heath Road, Coxheath |
MA003134 |
SP |
Coxheath |
New access and new footway adj Medical centre |
Works completed in maintenance |
Land north of Heath Road Phase 2 |
MA3257 |
SP |
Coxheath |
Access to new development |
Works still outstanding to include resurface of road and some signage |
Linden Farm, Stockett Lane |
MA003107 |
SP |
Coxheath |
Access to new development and footway link to community hall |
Works completed now in maintenance |
Gatland House, Gatland Lane |
MA003081 |
CV |
Fant |
Parking restrictions, signage, road markings and tactile crossings for new school |
Works completed, Remedials to do |
Harrietsham Primary School |
MA3388 |
CV |
Harrietsham |
New access to car park, extend traffic calmed area |
Works completed |
Bell Farm, Ashford Road |
MA003094 |
CV |
Harrietsham |
Realignment of Church Road to form new access onto A20. New footway along A20 |
Works in maintenance. |
Mayfield Nursery, Ashford Road |
MA003135 |
SP |
Harrietsham |
New access and alterations to existing Highway to adjoin upcoming Scheme Works |
Works now in maintenance (lighting as part of Harrietsham improvement scheme) |
Forge Meadows |
MA3253 |
AP |
Headcorn |
Access to 2 new properties and vehicle crossovers to existing properties |
Agreement signed. Works due to start 4 January 2021. |
Gibbs Farm Grigg Lane & Wheeler Street |
MA3250 |
SAS |
Headcorn |
Access Gibbs Farm dev’ment, zebra crossing on Wheeler St |
Agreement signed, works commenced. |
Grigg Lane, Lenham Road,
|
MA003050 |
CV |
Headcorn |
Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane |
New accesses Grigg Lane and Lenham Road & new footway Grigg Lane all in maintenance |
Kings Road/Millbank |
MA3262 |
AP |
Headcorn |
Signalised crossroads (linked to Ulcombe Road MA3150) |
Works completed. Maintenance period to commence when all requirements have been met. |
Lenham Road (North side) |
MA003062 |
CV |
Headcorn |
New Footway to site and extend speed limit boundary |
Works in Maintenance |
Lenham Road (South side) |
MA003057 |
CV |
Headcorn |
New footway |
Revised design received |
Oak Lane and Wheeler Street |
MA003048 |
CV |
Headcorn |
New footway plus junction improvements |
Works completed and in maintenance |
Ulcombe Road |
MA003150 |
SP |
Headcorn |
Access to new development |
Defects to be completed. |
Wheeler Street, Headcorn |
MA003137 |
SP |
Headcorn |
New access off Kingsland Grove and footway works on Wheeler Street |
Maintenance complete awaiting Cert 2 info |
Eyhorne Street |
MA3198 |
AP |
Hollingbourne |
New access to development |
Works in Maintenance |
Bentletts Yard, Claygate Road, Laddingford |
MA003357 |
SP |
Laddingford |
New footway and replaced surface to existing access |
Works near completion |
Headcorn Road Adj Rail bridge |
MA3404 |
CV |
Lenham |
New access road and extend 30mph limit |
Awaiting approval |
8 Faversham Road |
MA003032 |
CV |
Lenham |
New access |
In maintenance, streetlight to replace |
Old Ashford Road |
MA003018 |
CV |
Lenham |
New footway plus access |
Approaching end of maintenance, bus stop location to amend. |
The Paddocks, Ashford Road (Grove House, Old Ashford Road) |
MA3114 |
CV |
Lenham |
New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd |
Works completed, finishing/remedials required. |
Westwood Park, Ham Lane |
MA003305 |
AP |
Lenham |
Main and emergency accesses to new housing dev. |
Technical approval granted. Awaiting completion of agreement. |
Old Ashford Road, Adj Groom Way |
MA003356 |
AP |
Lenham |
New access and footway |
Awaiting Technical Approval |
Heath Road |
MA3326 |
JH |
Linton |
New Access |
In Maintenance Period |
Wares Farm, Linton Hill |
MA003353 |
SP |
Linton |
New access |
Awaiting info for Cert 1 for maintenance to commence |
St Saviours Road, Maidstone |
MA003136 |
AD |
Maidstone |
Changes to layout for Morrisons Junction |
Agreement due to be signed |
Buffkyn Way / Sutton Road |
MA003218 |
AD |
Maidstone |
Signalisation of the junction |
Approved – not signed |
Royal Engineers Rd/Mill Lane |
MA3312 |
JH |
Maidstone |
Access to New Development |
Start date to be agreed subject to Major Project Schemes |
531 Tonbridge Road |
MA003045 |
CV |
Maidstone |
Service layby for new retail unit |
In maintenance |
Bicknor Green, Gore Court Road |
MA003053 |
AD |
Maidstone |
Change of road priorities and widening / upgrading |
Works complete |
Hartnup Street |
MA003138 |
SP |
Maidstone |
New Access |
Cert 2 issued and now adopted |
Hermitage Lane, (opp. Maidstone Hospital) |
MA003060 |
AD |
Maidstone |
New Traffic signal junction |
Remedials being completed |
Hermitage Lane/ Howard Drive |
MA003070 |
AD |
Maidstone |
New access for development (opposite the quarry entrance) |
Remedial List issued |
Howard Drive |
MA003303 |
AD |
Maidstone |
Junction works to facilitate Bus Gateway entrance to Croudace site |
Works mostly complete |
Maidstone School of Science, New Cut Road |
MA003197 |
SP |
Maidstone |
New access to School and New roundabout and alterations to Highway |
In maintenance |
McDonalds drive-through, Hart Street |
MA003013 |
CV |
Maidstone |
New access, improvements to Hart Street. |
Approaching the end of maintenance - remedial works due |
Oakapple Lane/ Hermitage Lane |
MA003046 |
AD |
Maidstone |
New bellmouth junction and associated ancillary works incl new bus stop, for new development |
Works Complete – in maintenance |
Royal Engineers Road |
MA003127 |
SP |
Maidstone |
New footpaths to development |
Awaiting works start date |
The Poplars, Ashford Road |
MA3254 |
AP |
Maidstone |
Access to new development |
Works in Maintenance |
Wallis Avenue Phase 3, Parkwood |
MA003085 |
CV |
Maidstone |
Redevelopment of car park & shops opp. Longshaw Rd |
Works in maintenance |
Week St/Gabriel’s Hill |
MA003120 |
SP |
Maidstone |
Town Centre Public Realm improvements |
In Maintenance Period |
Castle Dene, Maidstone |
MA993352 |
CV |
Maidstone |
New Access and further footway work and repairs |
Works completed |
Union Street, Car Park |
MA003319 |
SP |
Maidstone |
New Access to development and footway works |
Footway works started but scheme not completed |
Medway Street |
MA3326 |
JH |
Maidstone |
Subway Flood Protection Works |
Under Technical review |
Langley Park Farm |
MA003130 |
AD |
Maidstone / Langley |
New Roundabout and associated works for entrance to Countryside Estate |
Works mostly complete |
Albion Road, Marden |
MA003132 |
SP |
Marden |
New Access & development |
Works on going |
Goudhurst Road, Church Green (Plain Road development) |
MA3118 |
CV |
Marden |
Install Zebra crossing near rail station. |
Works in Maintenance |
Goudhurst Road/West End (Plain Road Development) |
MA3118 |
CV |
Marden |
Refurbish Zebra crossing outside school and Bus Borders to add by Library stops. |
Works in Maintenance |
MAP Depot, Goudhurst Road |
MA003012 |
CV |
Marden |
New bellmouth junction and footway |
Works in maintenance. Remedial works near completed and interactive speed sign awaiting installation |
Napoleon Drive and Plain Road |
MA003079 |
CV |
Marden |
New access on each road for new housing development |
Works in maintenance |
The Parsonage, Goudhurst Road |
MA003066 MA003067 |
CV |
Marden |
New access and associated upgrade works |
Access substantially completed, village gateway to be agreed |
Sainsbury’s new site Station Rd |
MA3387 |
SP |
Staplehurst |
Roundabout and new access |
Crossing point in Marden Road started and awaiting start date for remaining works on Station Road |
Fishers Farm (East) Headcorn Road (Redrow) |
MA3106 |
SP |
Staplehurst |
Realignment and new access at Headcorn Road/Pile Lane junction |
Works still ongoing
|
Fishers Farm (West), Headcorn Road (Bovis) |
MA3037 |
AP |
Staplehurst |
New access onto Headcorn Road |
Works completed |
Fishers Farm (West), Headcorn Road (Bovis) (off-site works) |
MA3037/1 |
AP |
Staplehurst |
Pedestrian crossovers on Headcorn Road/ |
Works completed; remedial works required before first certificate issue |
Hen and Duckhurst Farm, Marden Road |
MA003109 |
CV |
Staplehurst |
New Roundabout for development access |
Works completed. |
Oliver Road Staplehurst |
MA003019 |
CV |
Staplehurst |
Ped crossing to Marden Road, junction markings and bus boarders |
In maintenance |
Woodford Park |
MA003099 |
SP |
Staplehurst |
New access for 9 dwellings |
Awaiting final info for Cert 2 |
Appleacres, Maidstone Road |
MA003152 |
SP |
Sutton Valence |
Access to new development and footway works |
Works complete, however ditch issues outstanding |
Sapphire Kennels Headcorn Road |
MA3407 |
AP |
Sutton Valence |
Access to new development and 40mph extension |
Awaiting technical approval |
The Oaks, Maidstone Road |
MA003078 |
CV |
Sutton Valence |
Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing. |
Works complete |
Valdene Industrial Estate |
MA003054 |
CV |
Sutton Valence |
Upgrade of existing bellmouth and extension to f/w |
Works completed |
Farleigh Hill Tovil (opp KCC waste site) |
MA3413 |
AP |
Tovil |
New access opp Burial Ground Ln KCC Recycling centre |
Awaiting technical approval |
Cripple Street Maidstone |
MA003093 |
CV |
Tovil |
New access to development, widening and footway works |
Due for adoption – remedials due |
Site opposite cottages 129-147 Dean Street/Farleigh Hill |
MA003007 |
CV |
Tovil |
New access speed limit relocation, new footway, and bus stop provision |
In maintenance |
Tovil Green Lane |
MA003095 |
CV |
Tovil |
New Footway and crossing point to side of site |
In maintenance |
Mount Ave/Blunden Lane |
MA3180 |
CV |
Yalding |
New accesses at site entrance |
Footway works to install crossing points imminent |
Hampstead Lane |
MA3101 |
SP |
Yalding |
Relocate access to new development at old depot adj. station. Minor footway works |
Awaiting final info for Cert 2 |
Vicarage Road |
MA003121 |
SP/JH |
Yalding |
New access to development and speed restraints on existing Highway |
New Agreement in progress. Contents of S278 now reduced. |
Appendix F – Bridge Works
Bridge Works – Contact Officer David Aspinall
|
|||
Road Name |
Parish |
Description of Works |
Current Status |
Buckland Road |
Maidstone |
Network Rail Buckland Road Bridge - footway protection from accidental wheel loading. It will require a road closure. |
Scheme designed; discussions ongoing with NR in relation to delivery. Road closure and crew programmed in for start of works on Monday 4th January 2021 for 2 weeks. |
A20 Maidstone Road |
Maidstone |
Raigersfield East Bridge (180m west of Willington Street junction), strengthening / renewal of bridge. Works will not affect traffic flow. |
Scheme currently in design phase, likely start Spring 2021 |
Appendix G – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler
|
||
Location |
Description of Works |
Current Status |
B2162 Twyford Bridge, Yalding |
Refurbishment of traffic signals |
Completed April 2020 |
Heath Road / Hermitage Lane, Barming |
Addition of pedestrian crossing facility |
Completed August 2020 |
Appendix H - Combined Member Grant programme update
Member Highway Fund programme update for the Maidstone District.
The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are
· in design
· at consultation stage
· about to be programmed
· Recently completed on site.
The list is up to date as of 18/12/20.
The details given below are for highway projects only. This report does not detail
· Contributions Members have made to other groups such as parish councils
· highway studies
· traffic/ non-motorised user surveys funded by Members.
More information on the schemes listed below can be found by contacting the District Manager for the Maidstone District, Susan Laporte.
Dan Daley and Rob Bird
Details of Scheme |
Status |
2021-CMG-MA-1003 – Hildenborough Crescent, Maidstone
20mph scheme
|
Works complete |
2021-CMG-MA-1001 – Buckland Hill, Maidstone
20mph scheme
|
Traffic Regulation Order (TRO) has been sealed – Works to install associated signs and roundels to be carried out 2021/22 |
Shellina Prendergast
Details of Scheme |
Status |
20/21-CMG-MA-1003 – Shenley Road, Headcorn
Installation of pedestrian warning signs
|
Works complete |
2021-CMG-MA-08 – Upper Street, Hollingbourne
Gateway to village to be enhanced
|
Works handed over to contractor – Due to be carried out Sunday 24 January 2021 |
Appendix I – Winter Report
Summary: This report outlines the arrangements that have been made between Kent County Council and Maidstone Borough Council to provide a local winter service in the event of an operational snow alert in the borough/district
- Introduction
1 (1) Kent County Council Highways, Transportation & Waste (KCC HTW) takes its winter service responsibilities very seriously and is proactive as well as reactive to winter weather conditions. Winter service costs KCC in the region of £3.3m every winter and needs careful management to achieve safety for the travelling public and to be efficient. The Highways Operations teams in HTW work to ensure that the winter service standards and decisions made are consistent across the whole county.
1(2) HTW prepares an annual Winter Service policy and plan which are used to determine actions that will be taken to manage its winter service operations. The policy was presented to the Environment and Transport Cabinet Committee on 15th September 2020 and subsequently approved by the Cabinet Member.
- District based winter service plans
2(1) The Local Winter Service Plan for the Maidstone District is a working document which will evolve and be revised as necessary throughout the year. This document complements the KCC Winter Service Policy and Plan 2020/21; the Policy is available on the KCC website.
2(2) Following successful work in previous years with district councils, arrangements have again been put in place this year whereby labour from district councils can be used during snow days. Additionally, HTW will supply a quantity of a salt/sand mixture to district councils to use on the highway network. The details are contained in the plan which enhances the work that HTW will continue to do in providing a countywide winter service. The local plan comes into effect when a snow emergency is declared that affects the district of Maidstone.
- Pavement clearance
3 (3) Areas for clearing pavements have been identified in the local plan. These are the areas where local knowledge has indicated that people are concerned and would most like to be kept clear when there is snow and ice.
- Farmers
4(1) The work that our contracted farmers have done in recent years is greatly appreciated and has made a big difference in keeping rural areas clear on snow days. Again, this year farmers will have predetermined local routes and will use their own tractor and KCC ploughs for clearing snow. The ploughs supplied are serviced by KCC each year. Each farmer will have plans detailing the roads that that they are responsible for ploughing. When snow reaches a depth of 50mm on roads in their areas the farmers will commence ploughing notifying KCC as agreed in their contract. A list of farmers and their contact details can be found in the local plan, (although some personal information will not be available via this report or the website due to General Data Protection Regulations).
5. Conclusion
5(1) Working in partnership with the district councils will enable HTW to provide an effective winter service across the county.
6. Recommendations
6(1) Members are asked to note this report.
______________________________________________________________
Background documents:
Kent County Council Winter Service Policy and Plan 2020/21
Contact officer: Susan Laporte, District Manager Maidstone
Tel: 03000 41 81 81
Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contacts: Kirstie Williams/ Susan Laporte 03000 418181