Subject: Highway Works Programme 2011/12

To:                              Maidstone Joint Transportation Board

 

By:                              KCC Highways, Transportation & Waste

 

Date:                           6th April 2022

 

Subject:                      Highways Forward Works Programme: 2021/22 and 2022/23

 

Classification:           Information Only

 

 

Summary: This report updates Members on the identified schemes approved for construction

 

 

1. Introduction

 

This report provides an update and summarises schemes that have been programmed for delivery in 2021/22 and 2022/23.

 

Kent County Council has recently published a forward works programme for the next five years covering planned maintenance of our highway assets. It is in two parts: the first concerns the next two years (2021/22 - 2022/23), and most of the sites included have already been verified by our engineers. The second part relates to years three to five of our five-year programme (2023/24 - 2025/26) and is based on data from our asset management systems, so may be subject to more changes as the schemes are verified.

 

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react to keep the highway in a safe and serviceable condition.

 

Further information about how we manage our highway infrastructure, including our county-wide five-year forward works programme, may be found on our website:

 https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways-policies/managing-highway-infrastructure

 

In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way.

 

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

           

Drainage Repairs & Improvements – see Appendix B

 

Street Lighting – see Appendix C

 

Transportation and Safety Schemes see Appendix D

  • Casualty Reduction Measures
  • Externally funded schemes

 

Developer Funded Works – see Appendix E

 

Bridge Works see Appendix F

 

Traffic Systems – see Appendix G

 

Combined Members Grant – Member Highway Fund – see Appendix H

 

 

 

Conclusion

 

1.    This report is for Members’ information.

 

Contact Officers:

 

The following contact officers can be contacted on 03000 418181

 

Richard Emmett                                Highway Manager Mid Kent

Susan Laporte                                     Maidstone District Manager

Alan Casson                                        Strategic Asset Manager                   

Earl Bourner                                       Drainage Asset Manager

Neill Coppin                                        Structures Operations Team Leader

Sue Kinsella                                        Street Light Asset Manager

Toby Butler                                         Traffic & Network Solutions Asset Manager

Jamie Hare                                         Development Agreements Manager

Jamie Watson                                     Schemes Programme Manager

           


Appendix A – Footway and Carriageway Improvement Schemes

 

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

 

 

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name

Parish

Extent of Works

Current Status

Kings Road

Headcorn

Between A274 and Forge Lane

 

Programmed 30th March 2022

A274 Maidstone Road

Headcorn

Kings Road to Stonestile Road

 

Programmed 11th April 2022

A20 Ashford Road

Hollingbourne

M20 Junction 8 roundabout to east of B2163

 

Programmed 6th June 2022

A249 Wat Tyler Way

Maidstone

Between A229 Upper Stone Street and A20 Ashford Road

 

Programmed 6th July 2022

 

Footway Improvement - Contact Officer Mr Neil Tree

Road Name

Parish

Extent and Description of Works

Current Status

Coombe Road

Tovil

 

Footway Reconstruction

Two Sections

1. Old Tovil Rd to Quarry Rd

2. Courtney Rd to o/s No. 72. 

 

 

 

Completed

 

A20 Ashford Road

Harrietsham

 

Footway Reconstruction

Sections from the junction with Church Road to the Junction with Marley Road (Petrol Station)

 

 

 

 

Completed

 

Heathfield Road

 

Penenden Heath

 

Footway Protection Treatment Full extent

 

 

Completed.

 

 

Hedley Street (including Lucerne)

 

Maidstone

 

Footway Protection Treatment Full extent

 

 

Completed.

 

Foley Street

 

Maidstone

 

Footway Protection Treatment Full extent

 

 

Completed.

Surface Treatments – Contact Officer Mr Jonathan Dean

Road Name

Parish

Extent and Description of Works

Current Status

CLAYGATE ROAD (PART)

Marden

Jarmons Lane to Claygate Road

(In situ Road Recycling)

 

Programmed for May 2022

JARMONS LANE (PART)

Collier Street

Collier Street to Claygate Road

(In situ Road Recycling)

 

Programmed for May 2022

SPENNY LANE

Collier Street

Claygate Road to Martins Fruit Farm

(In situ Road Recycling)

 

Programmed for May 2022

CHART ROAD

Sutton Valence

Church Road to Chart Hill Road

(In situ Road Recycling)

 

Programmed for May 2022

CRUMPS LANE

Ulcombe

Headcorn Road to Lenham Road

(In situ Road Recycling)

 

Programmed for May 2022

 

TILDEN LANE

Marden

Stilebridge Lane to Underlyn Lane

(Surface Dressing)

Programmed for Late July / Early August 2022

 

GRIGG LANE (PHASE 2)

Headcorn

Grigg Farm/Baker Lane to Oak Lane

(Surface Dressing)

Programmed for Late July / Early August 2022

 

STILEBRIDGE LANE

Marden

Linton Hill to Underlyn Lane

(Surface Dressing)

Programmed for Late July / Early August 2022

 

WHITE HOUSE LANE

Headcorn

Shenley Road to A274 Biddenden Road

(Surface Dressing)

Programmed for Late July / Early August 2022

 

HEATH ROAD

Linton

Brishing Lane to A229 Linton Hill

(Surface Dressing)

Programmed for Late July / Early August 2022

 

TONBRIDGE ROAD

Teston (Barming)

Church Road, Teston to South Lodge Bends

(Surface Dressing)

Programmed for Late July / Early August 2022

 

ASHFORD ROAD

Bearsted

Roundwell to Otham Lane

(Surface Dressing)

Programmed for Late July / Early August 2022

 

MAIDSTONE ROAD

Staplehurst

George Street to Couchman Green Lane

(Surface Dressing)

Programmed for Late July / Early August 2022

UPPER STREET

Leeds

Horseshoes Lane to Blair House

(Micro Surfacing)

 

Programmed for August 2022

MARLEY ROAD (DICKLEY LANE)

Lenham (Harrietsham)

Marley Works to Steeds Hill

(Micro Surfacing)

 

Programmed for May 2022

NORTH STREET

Barming

From Heath Road to A26 Tonbridge Road

(Micro Surfacing)

 

Programmed for May 2022

GRIGG LANE (PHASE 3) Section not done due to covid vaccination centre access

Headcorn

Headcorn Surgery (The Hardwicks) to Oak Lane

(Micro Surfacing)

 

Programmed for May 2022

MALLING ROAD

Teston

Whole Road

(Micro Surfacing)

 

Programmed for May 2022

LEES ROAD (INC LADDINGFORD & CLAYGATE ROAD)

Laddingford

From Lees Road to two hundred metres past Laddingford School

(Micro Surfacing)

 

Programmed for May 2022

PATTENDEN LANE

Marden

Underlyn Lane to West End

(Micro Surfacing)

 

Programmed for May 2022

MAIDSTONE ROAD

Marden

 New Barn Cottage to A229

(Micro Surfacing)

 

Programmed for May 2022

THE STREET

Bredhurst

Forge Lane to County Boundary (Medway)

(Micro Surfacing)

 

Programmed for May 2022

ROUNDWELL (& THE STREET)

Bearsted

From A20 Ashford Road to Church Lane (incl. The Street)

(Micro Surfacing)

 

Programmed for May 2022

TONBRIDGE ROAD

Barming

South Lodge Bends to North Street

(Micro Surfacing)

 

Programmed for May 2022

CHART ROAD

Sutton Valence

A274 Sutton Valence Hill to Church Road

(Micro Surfacing)

 

Programmed for May 2022

MAIDSTONE ROAD

Marden

High Street to Hartridge

(Micro Surfacing)

 

Programmed for August 2022

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B - Drainage

 

 

Drainage Repairs & Improvements - Contact Officer Earl Bourner 

Road Name

Parish

Description of Works

Current Status

Eyhorne/Upper Street/Hollingbourne Hill

Hollingbourne

Various repairs to the highway drainage system completed. Further work required to reinstate outfall to pond.

Further landowner liaison required. Anticipate undertaking further works in Summer.

A20 Ashford Rd under rail bridge by Square Hill

Maidstone

The existing drainage has been cleaned and surveyed and is working but an improvement scheme is to be developed to reduce risk of blockages and flooding

All works within highway boundary now complete

Harp Farm Road

Boxley

Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered

Permanent Road liable to flooding signs have been installed in the interim. Awaiting confirmation of capital budget to prioritise sites for scheme works.

Lenham Road

Headcorn

Ditch overflowing onto carriageway

Land drainage team to reassess when water subsides

Rawdon Road

Maidstone

Large void in footway

Works complete

Neville Close

Maidstone

Investigate broken pipework in rear garden of no 5 to prevent further flooding of property

Works complete

Marden Road

Staplehurst

Ditching works and culvert replacement due to historical flooding issues in area

Works complete

Chalky Road

Stockbury

Installation of new gully and inspection chamber

Works complete

Lughorse Lane

Hunton

Replace collapsed headwall and pipework

Works complete

Lenham road

Platts Heath

New gully installation and replace damaged pipework to rear of property

Works complete

Benover road

Yalding

Replaced broken pipework to ditch outfall

Works complete

Warmlake road

Chart Sutton

Replace entire length of broken mainline to outfall

Works ongoing – SGN damage to pipework – due for completion 01/04/2022

Holmoaks

Maidstone

Maintenance to existing system to stop damage to footway in park

Due for completion 23/03/2022

Ashford road

Weavering

Additional gully added to alleviate flooding into Poplar Close

Works complete

The Street

Ulcombe

Repair broken pipework leading to stream

Works programmed for 19/04/2022

Buckland road

Maidstone

Repair broken pipework at entrance to school

Works programmed for 04/04/2022

Trapfield close

Bearsted

Repair section of broken pipe to alleviate property flooding

Works programmed for 30/03/2022

The Green

Bearsted

Repair section of broken pipework to stop voids in village green

Works complete

East Street

Hunton

Investigate cause of sunken driveway – 600mm piped culvert running underneath

Works programmed for 25/04/2022

 

 


Appendix C – Street Lighting

 

Column replacement testing of KCC owned streetlights has identified the following as requiring. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.  

 

 

Street Lighting Column Replacement – Contact Officer Sue Kinsella

 

Road Name

Column

Parish

Description of Works

Status

Tonbridge Road

KTBU022

Fant

Replacement of Street Light

Completion end July 22

Tonbridge Road

KTBU051

Fant

Replacement of Street Light

Completion end July 22   

Sutton Road

KSGF007

Shepway South

Replacement of Street Light

Completion end July 22

Thornhill Place

KTBG002

North

Replacement of Street Light

Completion end July 22

Farleigh Hill

KFAH002

South

Replacement of Street Light

Completion end July 22

King Street

KKAM013

High Street

Replacement Street Light

Completion end July 22

     Loose Road

KLCQ055

       South

 

Replacement Street Light

Completion end            July 22

 

Brishing Lane

 

KBFE010

 

Park Wood

 

 

Replacement Street Light

 

Completion end July 22

 

Ashford Road

 

KABQ005

 

Boxley

 

 

Replacement Street Light

 

Completion end July 22

Ashford Road

KABQ007

Boxley

Replacement Street Light

Completed

Ashford Road

KABQ009

Boxley

Replacement Street Light

Completed

Ashford Road

KABQ017

Boxley

Replacement Street Light

Completion end April 22

Ashford Road

KABQ019

Boxley

Replacement Street Light

Completion end July 22

 

Brownelow Copse

 

KBHO005

 

Boxley

 

 

Replacement Street Light

 

Completed

Faversham Road

KFAQ007

Harrietsham

Replacement Street Light

Completion end July 22

Old Ashford Road

KOAG011

Harrietsham

Replacement Street Light

Completion end July 22

Old Ashford Road

KOAG012

Harrietsham

Replacement Street Light

Completion end July 22

Tonbridge Road

KTBU025

Fant

Replacement Street Light

Completion end July 22

Westerhill Road

KWBP001

Coxheath

Replacement Street Light

Completion end July 22

Heath Road

KHCH024

Coxheath

Replacement Street Light

Completion end July 22

Amsbury Road

KAAV004

Coxheath

Replacement Street Light

Completion end July 22

Granville Road

KGBG005

North

Replacement Street Light

Completion end July 22

Tower Lane

KTCC002

Bearsted

Replacement Street Light

Completion end July 22

Willington Street

KWCY317

Shepway North

Replacement Street Light

Completion end July 22

Forstal Lane

KFCB008

Coxheath

Replacement Street Light

Completion end July 22

 


Appendix D – Transportation and Safety Schemes

 

Casualty Reduction Measures

 

The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough, to meet Kent County Council’s strategic targets (for example, addressing traffic congestion or improving road safety).  Casualty reduction measures have been identified to address a known history of personal injury crashes. Status correct as of 22nd March 2022.

 

 

Location

Parish

Description of Works

Lead officer

Current Status

Running Horse Roundabout

Maidstone

Virtual lane separation system using road markings & coloured surfacing

Christopher Koningen

Traffic modelling completed, showing a reduction in congestion if the scheme is implemented as proposed.

 

Funding needs to be sought to enable construction, which has meant the scheme is now likely to be implemented in the 23/24 financial year. Once the required budget is secured the detailed design and appropriate stakeholder liaison will be carried out.

 

 

APPENDIX D2 – INTEGRATED TRANSPORT SCHEMES – all other LTP funded non-casualty reduction schemes

 

Location

Parish

Description of Works

Lead officer

Current Status

Buckland Hill

Maidstone

New Zebra Crossing

Jennie Watson

Scheme due to be constructed in April 2022

Hart Street/Barker Road

Maidstone

Experimental Traffic Regulation Order for One-Way System

Jennie Watson

As recommended at the January JTB meeting, we will be looking to implement the one-way system in Summer/Autumn 2022

PROW KB18 North of Maidstone Hospital

Maidstone

Upgrading of route to allow cycling and improve wayfinding signs.

Jennie Watson

 

Scheme complete

Cycle route Link between London Road Park and Ride site and Maidstone Hospital

Maidstone

Signed cycle route linking London Road Park and Ride site with Maidstone Hospital

Jennie Watson

Scheme is currently at design stage

 

Externally Funded Schemes

 

The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough funded by external corporations whilst still meeting Kent County Council’s strategic targets with the road network.

 

 

Section 106 Schemes

 

File Ref.

Road Name

Parish

Description of Works

Current Status

S106-MA-819

Linton Crossroads

Linton/Loose

Junction/signal upgrade

KCC investigating how any funding gap can be dealt with. At present there is not a programme for construction. A consultation on existing designs is planned for June/July 2022 with a meeting between local Parishes to be arranged prior to the consultation.

S106-MA-1104

Hermitage Lane and M20 junction 5 lining

Maidstone

Cycleway improvements between rail station and hospital on east side

Croudace development for 330 homes off Hermitage Lane if planning permission is to be granted will deliver via a S278 the section between the train station and Chapelfield Way. The remaining section to the hospital may well also be funded by a S106 agreement with Croudace.

M20 Junction 5 lining has been implemented with directions signs still to be installed.

 

 

 

 

 

 

 

 

 

Parish Council Funded Schemes

 

File Ref.

Road Name

Parish

Description of Works

Current Status

2122-PAR-MA-09

 

Lenham Square

Lenham

20mph scheme

TRO due to go out to consultation – Scheme currently in design

2122-PAR-MA-07

West Street/Church Road

Harrietsham

20mph scheme

TRO due to go out to consultation – Scheme currently in design

 

 

 

Other External Schemes

File Ref

Road Name

Parish

Description of Works

Status

 

2122-EXT-MA-3001

A249 Detling Hill

Detling

Extension of 50mph speed limit

TRO has been advertised.  Scheme has been passed to Contractor, Bouygues in October 2021.  Contractor have advised scheme to be delivered in June 2022 under lane closures.

 


Appendix E – Developer Funded Works

 

Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Sarah Parris

 

Scheme Name

File Ref.

Officer

Parish

Description of Works

Current Status

Bell Farm, North Street

MA003098

SN

Barming

New accesses to split sites, shared surface and new crossing point

Highway works completed. Stage 3 Safety Audit Awaited.

Barty Farm, Roundwell,

MA003278

AD

Bearsted

New Bellmouth and Lining works

Defects issued

Cross Keys

MA003100

JH

Bearsted

New access, crossing point and parking area

Phase 1 works due 14/03/22, Phase 2 works due 11/04/22.

Bicknor Road

MA003256

AP

Bicknor

Formation of hard surfaced passing places

Awaiting technical approval


Lyewood Farm, Green Lane

MA3247

MA3248

AP

Boughton Monchelsea

New housing development and access

Awaiting remedial works

Hubbards Lane

MA003084

CV

Boughton Monchelsea

Two accesses to minor developments

Works substantially completed

Heath Road/Church Street

MA003111

SP

Boughton Monchelsea

New access, footway works, yellow lines and crossing upgrade

Completion of footway still outstanding along with defects picked up, and drainage issues.

Church Road/Deringwood Drive/Willington Street/Spot Lane

MA003426/ MA003429/ MA003430/ MA003431/MA003436/ MA003437

SP

Boxley

Alterations to existing highway to include traffic signals, widening of road and junction widening/narrowing

Received and going through Technical Approval Process

Heath Road

(North side)

MA003063

CV

Coxheath

New access and Footway work

At Final remedial stage prior to adoption

Linden Farm, Stockett Lane

MA003107

SP

Coxheath

Access to new development and footway link to community hall

Adopted

 

 

Heath Road, Coxheath

 

 

MA003134

 

 

SP

 

 

Coxheath

 

 

New access and new footway adj medical centre

 

 

Awaiting completion of snagging for adoption

Forstal Lane

MA003141

SP

Coxheath

Widening of road and new footpath with access to new development

Works completed, however drainage issues and defects so 1 year maintenance not yet started

Land north of Heath Road Phase 2

MA3257

SP

Coxheath

Access to new development

Still awaiting defective works to be completed

Gatland House, Gatland Lane

MA003081

CV

Fant

Parking restrictions, signage, road markings and tactile crossings for new school

Works completed, Remedials to do

Bell Farm, Ashford Road

MA003094

CV

Harrietsham

Realignment of Church Road to form new access onto A20. New footway along A20

Works in maintenance

Harrietsham Primary School

MA3388

CV

Harrietsham

New access to car park, extend traffic calmed area

Works completed, in maintenance

Mayfield Nursery, Ashford Road

MA003135

SP

Harrietsham

New access and alterations to existing Highway to adjoin upcoming Scheme Works

Adopted

Forge Meadows

MA3253

AP

Headcorn

Access to two new properties and vehicle crossovers to existing properties

Works in Maintenance

Kings Road/Millbank

MA3262

AP

Headcorn

Signalised crossroads (linked to Ulcombe Road MA3150)

Works Adopted

Oak Lane and Wheeler Street

MA003048

CV

Headcorn

New footway plus junction improvements

Works at end of maintenance, final remedials due

Grigg Lane, Lenham Road,

 

MA003050

CV

Headcorn

Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane

New accesses Grigg Lane and Lenham Road & new footway Grigg Lane all in maintenance

Lenham Road (South side)

MA003057

CV

Headcorn

New footway

Footway and speed gateway works due for completion over Easter Hols

Lenham Road (North side)

MA003062

CV

Headcorn

New Footway to site and extend speed limit boundary

At Final remedial stage prior to adoption

Mill Bank Headcorn

MA3119

CV

Headcorn

New bus stops and extend 30mph zone

Works commenced, to complete March ’22 (before resurfacing)

Stonestile Road

MA003412

JH

Headcorn

New access to twelve houses

Works underway

Gibbs Farm Grigg Lane & Wheeler Street

MA3250

SAS

Headcorn

Access Gibbs Farm dev’ment, zebra crossing on Wheeler St

Works Complete, RSA3 raised defects, waiting for developer to act on these.

Ulcombe Road

MA003150

SP

Headcorn

Access to new development

Works complete now in maintenance

Woodcut Farm, Ashford Road

MA00

SP

Hollingbourne

Alterations to A20 and access for new development

Still going through Technical Approval

Genco Office

MA003433

SP

Hollingbourne

New Access to Business and carriageway alterations

Going through Technical Approval

Ledian Farm

MA003086

JH

Leeds

New access and bus stop works

Access in maintenance period, bus stop to be started in due course

Westwood Park, Ham Lane

MA003305

AP

Lenham

Main and emergency accesses to new housing dev.

Works Completed

Old Ashford Road, Adj Groom Way

MA003356

AP

Lenham

New access and footway

Awaiting start of works on site

8 Faversham Road

MA003032

CV

Lenham

New access

In maintenance, streetlight to replace

The Paddocks, Ashford Road (Grove House, Old Ashford Road)

MA3114

CV

Lenham

New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd

Adoption imminent

Headcorn Road

Adj Rail bridge

MA3404

CV

Lenham

New access road and extend 30mph limit

Complete – In maintenance

Loder Close

MA3424

JH

Lenham

New bell mouth access and footway

Under review

Heath Road

MA3326

JH

Linton

New Access

In Maintenance Period

Gleamingwood Drive

MA003441/MA003440

SP

Lordswood

New Access and development

Going through Technical Approval

Bicknor Green, Gore Court Road

MA003053

AD

Maidstone

Change of road priorities and widening / upgrading

In Maintenance

Oakapple Lane/ Hermitage Lane

MA003046

AD

Maidstone

New bellmouth junction and associated ancillary works incl new bus stop, for new development

Paperwork outstanding prior to adoption

St Saviours Road, Maidstone

MA003136

AD

Maidstone

Changes to layout for Morrisons Junction

Agreement signed

Buffkyn Way / Sutton Road

MA003218

AD

Maidstone

Signalisation of the junction

Approved – not signed

The Poplars, Ashford Road

MA3254

AP

Maidstone

Access to new development

Works Adopted

Springwood Road Maidstone

MA003438

AP

Maidstone

Stopping up of existing access and provision of new through footway

Works Completed

531 Tonbridge Road

MA003045

CV

Maidstone

Service layby for new retail unit

Adoption imminent

Wallis Avenue Phase 3, Parkwood

MA003085

CV

Maidstone

Redevelopment of car park & shops opp. Longshaw Rd

Works in maintenance

Maidstone East Station

MA3447

CV

Maidstone

Footway upgrade (& private parking improvement)

Works in progress

Royal Engineers Rd/Mill Lane

MA3312

JH

Maidstone

Access to New Development

Revised scheme under Technical Review after comments from local Members

Medway Street

MA3326

JH

Maidstone

Subway Flood Protection Works

Awaiting input from scheme promotor – no information rec’d

Howard Drive

MA003303

SP

Maidstone

Junction works to facilitate Bus Gateway entrance to Croudace site

TRO going through

Hermitage Lane, (opp. Maidstone Hospital)

MA003060

SP

Maidstone

New Traffic signal junction

In Maintenance. Remedials being completed


Hermitage Lane/ Howard Drive

MA003070

SP

Maidstone

New access for development (opposite the quarry entrance)

Awaiting final snagging items

Royal Engineers Road

MA003127

SP

Maidstone

New footpaths to development

Awaiting works start date

Union Street, Car Park

MA003319

SP

Maidstone

New Access to development and footway works

Works complete now in maintenance

Castle Dene, Maidstone

MA003352

SP

Maidstone

New Access and further footway work and repairs

Works completed

Perryfield Street

MA3411

SP

Maidstone

New footpath/access to new houses

Awaiting works start date

Oakapple Phase 2A, Hermitage Lane

MA003444

SP

Maidstone

Development adjoining existing development

Going through Technical Approval

Langley Park Farm

MA003130

AD

Maidstone / Langley

New Roundabout and associated works for entrance to Countryside Estate

Works complete

MAP Depot, Goudhurst Road

MA003012

CV

Marden

New Bellmouth junction and footway

Final Remedials due

The Parsonage, Goudhurst Road

MA003066

MA003067

CV

Marden

New access and associated upgrade works

In maintenance

Napoleon Drive and Plain Road

MA003079

CV

Marden

New access on each road for new housing development

Adoption imminent

Goudhurst Road/West End (Plain Road Development)

MA3118

CV

Marden

Refurbish Zebra crossing outside school and Bus Borders to add by Library stops.

Works in Maintenance, near adoption

Albion Road, Marden

MA003132

SP

Marden

New Access & development

Snagging works for S278 and S38 ongoing

Fishers Farm (West), Headcorn Road (Bovis) (off-site works)

MA3037/1

AP

Staplehurst

Pedestrian crossovers on Headcorn Road/
Hurst Close

Works completed, remedial works completed, stage 3 road safety audit response required before first certificate issue

Oliver Road Staplehurst

MA003019

CV

Staplehurst

Ped crossing to Marden Road, junction markings and bus boarders

Near end of maintenance

Hen and Duckhurst Farm, Marden Road

MA003109

CV

Staplehurst

New Roundabout for development access

In Maintenance, additional speed roundels etc to be added

High Street Staplehurst

MA3446

CV

Staplehurst

2 x new bus stop upgrades (kerbs and markings)

Agreement due for signing – works will be undertaken shortly

Fishers Farm (East) Headcorn Road (Redrow)

MA3106

SP

Staplehurst

Realignment and new access at Headcorn Road/Pile Lane junction

Works still ongoing

 

Sainsbury’s new site Station Rd

MA3387

SP

Staplehurst

Roundabout and new access

Cert 1 issued in maintenance period

Pristling Lane

MA3415

SP

Staplehurst

Widened access & Ditch works

Cert 1 issued in maintenance

Sapphire Kennels Headcorn Road

MA3407

AP

Sutton Valence

Access to new development and 40mph extension

Works in Maintenance

Valdene Industrial Estate

MA003054

CV

Sutton Valence

Upgrade of existing bellmouth and extension to f/w

Adoption imminent

The Oaks, Maidstone Road

MA003078

CV

Sutton Valence

Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing.

Works complete

Appleacres, Maidstone Road

MA003152

SP

Sutton Valence

Access to new development and footway works

Works complete, however ditch issues outstanding

Warmlake Nurseries

MA003443

SP

Sutton Valence

New access to small development

Access works booked in then resurfacing/HFS to be completed separately

Farleigh Hill Tovil

(Opp KCC waste site)

MA3413

AP

Tovil

New access opp Burial Ground Ln KCC Recycling centre

Technical approval granted. Site being sold to new developer

Site opposite cottages 129-147 Dean Street/Farleigh Hill

MA003007

CV

Tovil

New access speed limit relocation, new footway and bus stop provision

At Final remedial stage prior to adoption

Cripple Street Maidstone

MA003093

CV

Tovil

New access to development, widening and footway works

Due for adoption – remedials due

Tovil Green Lane

MA003095

CV

Tovil

New Footway and crossing point to side of site

In maintenance

Mount Ave/Blunden Lane

MA3180

CV

Yalding

New accesses at site entrance

In maintenance

Vicarage Road

MA003121

SP/JH

Yalding

New access to development and speed restraints on existing Highway

Under review

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix F – Bridge Works

 

Bridge Works – Contact Officer: Helen Rowe

Road Name

Parish/Town

Description of Works

Current Status

 

 

None

 

 


Appendix G – Traffic Systems

 

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

 

Traffic Systems - Contact Officer: Toby Butler

 

Location

Description of Works

Current Status

A249 Bearsted Road near Hampton Road, Maidstone

Renewal and upgrade of signal controller crossing

Completed August 2021

A299 Palace Avenue near Gabriels Hill, Maidstone

Renewal and upgrade of signal controller crossing

Completed October 2021

 

 


Appendix H - Combined Members Grant programme update

 

Member Highway Fund programme update for the Maidstone Borough Council

 

The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are

·         in design

·         at consultation stage

·         about to be programmed

·         recently completed on site.

 

The list is up to date as of 24th March 2022

      

The details given below are for highway projects only.  This report does not detail

·         contributions Members have made to other groups such as parish councils

·         highway studies

·         traffic/ non-motorised user surveys funded by Members.  

 

More information on the schemes listed below can be found by contacting the District Manager for the Maidstone Borough Council.

 

[  ]

Details of Scheme

Status

None

 

 

[  ]  

Details of Scheme

Status

 

 


Legal Implications

1.1.1         Not applicable.

1.2               Financial and Value for Money Considerations

1.2.1         Not applicable.

1.3               Risk Assessment

1.3.1         Not applicable.

Contacts: Richard Emmett/ Susan Laporte 03000 418181