PI: First Quarter Performance Report

 

Key to performance ratings

 

Direction

Performance has improved

Performance has been sustained

Performance has declined

N/A

No previous data to compare

 

RAG Rating

Target not achieved

Target slightly missed (within 10%)

Target met

Data Only

 

 

 

 

 

 

 

 

 

 

Performance Summary

 

RAG Rating

Green

Amber

Red

N/A[1]

Total

KPIs

5

1

0

5

11

Direction

Up

No Change

Down

N/A

Total

Last Quarter

5

1

2

3

11

Last Year

5

1

2

3

11

 

·         83.3% (5 of 6) targetable quarterly key performance indicators (KPIs) reportable to this Committee achieved their Quarter 1 (Q1) target1.

·         Compared to last quarter (Q4 2021/22), performance for 62.5% (5 of 8) KPIs have improved, 12.5% (1 of(8) had no change and for 25% (2 of 8) have declined1.

·         Compared to last year (Q1 2021/22), performance for 62.5% (5 of 8) KPIs have improved, 12.5% (1 of 8) had no change and 25% (2 of 8) have declined1.

 

Embracing Growth & Enabling Infrastructure

Performance Indicator

Q1 2022/23

Value

Target

Status

Short Trend

(Last Quarter)

Long Trend

(Last Year)

Percentage of priority 1 enforcement cases dealt with in time

100%

95%

Percentage of Priority 2 enforcement cases dealt with in time

86.78%

90%

Number of enforcement complaints received

125

Processing of planning applications: Major applications (NI 157a)

108.33%

90%

 

 

Processing of planning applications: Minor applications (NI 157b)

100.96%

95%

Processing of planning applications: Other applications (NI 157c)

100.68%

98%

Number of affordable homes delivered (Gross)

118

50

Affordable homes as a percentage of all new homes

Annual KPI

Net additional homes provided (NI 154)

Annual KPI

 

 

Open planning enforcement cases (as of the start of each month)

Value

Target

Status

Short Trend (Last Month)

Long Trend (Last Year)

April 2022

373

May 2022

365

June 2022

366

 

Planning Enforcement Caseload

April 2022 – June 2022

 



[1] PIs rated N/A are not included in the summary calculations.