The Local Economy
Project Officer presented the report providing an update on the
scheme to create a cycle path along the River Medway from Aylesford
to Barming Bridge, and requesting the
committee’s agreement to commence physical works in advance
of the completion of the Cycle Tracks Conversion Order.
Members were advised
that most landowners affected by the scheme were in support of the
project, however some had requested
movement of the path. Officers had considered this alternative and
concluded that it would compromise the path’s amenity and
security.
In response to
questions it was explained that:
·
Vehicular access would be restricted by a locked gate stationed at
the end of Unicomes Lane, accessible
only to those with vehicular rights. There was enough width to
allow pedestrians the space to move to the side of the path when a
vehicle needed to pass.
·
Signage would be used to encourage mutual respect between cyclists
and pedestrians sharing the pathway.
RESOLVED: That the commencement of physical
works to improve the existing public footpath, prior to the
completion of the Cycle Tracks Conversion Order process, be
agreed.
For – 9 Against – 0
Abstain – 0