To: Maidstone Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 3rd August 2022
Subject: Highways Forward Works Programme: 2022/23
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2022/23.
Kent County Council has recently published a forward works programme for the next five years covering planned maintenance of our highway assets. It is in two parts: the first concerns the two years (2022/23), and most of the sites included have already been verified by our engineers. The second part relates to years three to five of our five-year programme (2023/24 - 2025/26) and is largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.
This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react to keep the highway in a safe and serviceable condition.
Further information about how we manage our highway infrastructure, including our county-wide five-year forward works programme, may be found on our website:
In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
- Casualty Reduction Measures
- Externally funded schemes
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Members Grant – Member Highway Fund – see Appendix H
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Richard Emmett Senior Highway Manager Mid Kent
Susan Laporte Maidstone Highway Manager
Alan Casson Strategic Asset Manager
Earl Bourner Drainage Asset Manager
Neill Coppin Structures Operations Team Leader
Sue Kinsella Street Light Asset Manager
Toby Butler Traffic & Network Solutions Asset Manager
Jamie Hare Development Agreements Manager
Jamie Watson Schemes Programme Manager
Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Mr Byron Lovell |
|||
Road Name |
Parish |
Extent of Works |
Current Status |
Kings Road |
Headcorn |
Between A274 and Forge Lane |
Completed |
A274 Maidstone Road |
Headcorn |
Kings Road to Stonestile Road |
Completed |
A20 Ashford Road |
Hollingbourne |
M20 Junction 8 roundabout to east of B2163 |
Completed |
A249 Wat Tyler Way |
Maidstone |
Between A229 Upper Stone Street and A20 Ashford Road |
Completed |
A274 Sutton Road |
Maidstone |
Wheatsheaf junction to Northumberland Road |
Programmed 14th September 2022 |
A249 Detling Hill |
Thurnham |
Entry slip to Detling Showground |
Programmed 22nd July 2022 |
A20 Ashford Road |
Maidstone |
Between 30mph/40mph gateway east of Turkey Mill and Huntsman Lane |
Programmed 25th July 2022 |
Footway Improvement - Contact Officer Mr Neil Tree |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
West Walk |
Barming |
Footway Reconstruction Entire Length (Between the junctions with Queens Road and Cherry Orchard Way).
|
Designed. Works commenced and ongoing.
|
Nottingham Avenue |
Maidstone |
Footway Protection Treatment From the junction with Sutton Road to York House/ Llandaff House
|
Designed and to be programmed |
Leicester Road |
Maidstone |
Footway Protection Treatment from the Essex Road roundabout to York House
|
Designed and to be programmed |
Middlesex Road |
Maidstone |
Footway Protection Treatment from the Essex Road roundabout to Llandaff House
|
Designed and to be programmed |
Old Tovil Road |
Maidstone |
Footway Protection Treatment From the junction with College Road to Hayle Road including upper footways.
|
Designed and to be programmed |
Surface Treatments – Contact Officer Mr Jonathan Dean |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
CLAYGATE ROAD (PART) |
Marden |
Jarmons Lane to Claygate Road (In situ Road Recycling) |
Complete |
JARMONS LANE (PART) |
Collier Street |
Collier Street to Claygate Road (In situ Road Recycling) |
Complete |
SPENNY LANE |
Collier Street |
Claygate Road to Martins Fruit Farm (In situ Road Recycling) |
Complete |
CHART ROAD |
Sutton Valence |
Church Road to Chart Hill Road (In situ Road Recycling) |
Complete |
CRUMPS LANE |
Ulcombe |
Headcorn Road to Lenham Road (In situ Road Recycling) |
Complete |
TILDEN LANE |
Marden |
Stilebridge Lane to Underlyn Lane (Surface Dressing) |
Programmed for Late July 2022 |
GRIGG LANE (PHASE 2) |
Headcorn |
Grigg Farm/Baker Lane to Oak Lane (Surface Dressing) |
Programmed for Late July 2022 |
STILEBRIDGE LANE |
Marden |
Linton Hill to Underlyn Lane (Surface Dressing) |
Programmed for Late July 2022 |
WHITE HOUSE LANE |
Headcorn |
Shenley Road to A274 Biddenden Road (Surface Dressing) |
Programmed for Late July 2022 |
HEATH ROAD |
Linton |
Brishing Lane to A229 Linton Hill (Surface Dressing) |
Programmed for Late July 2022 |
TONBRIDGE ROAD |
Teston (Barming) |
Church Road, Teston to South Lodge Bends (Surface Dressing) |
Programmed for Late July 2022 |
ASHFORD ROAD |
Bearsted |
Roundwell to Otham Lane (Surface Dressing) |
Programmed for Late July 2022 |
MAIDSTONE ROAD |
Staplehurst |
George Street to Couchman Green Lane (Surface Dressing) |
Programmed for Late July 2022 |
UPPER STREET |
Leeds |
Horseshoes Lane to Blair House (Micro Surfacing) |
Programmed for August 2022 |
MARLEY ROAD (DICKLEY LANE) |
Lenham (Harrietsham) |
Marley Works to Steeds Hill (Micro Surfacing) |
Programmed for August 2022 |
NORTH STREET |
Barming |
From Heath Road to A26 Tonbridge Road (Micro Surfacing) |
Complete |
GRIGG LANE (PHASE 3) Section not done due to covid vaccination centre access |
Headcorn |
Headcorn Surgery (The Hardwicks) to Oak Lane (Micro Surfacing) |
Programmed for August 2022 |
MALLING ROAD |
Teston |
Whole Road (Micro Surfacing) |
Complete |
LEES ROAD (INC LADDINGFORD & CLAYGATE ROAD) |
Laddingford |
From Lees Road to two hundred metres past Laddingford School (Micro Surfacing) |
Complete |
PATTENDEN LANE |
Marden |
Underlyn Lane to West End (Micro Surfacing) |
Programmed for August 2022 |
MAIDSTONE ROAD |
Marden |
New Barn Cottage to A229 (Micro Surfacing) |
Complete |
THE STREET |
Bredhurst |
Forge Lane to County Boundary (Medway) (Micro Surfacing) |
Programmed for August 2022 |
ROUNDWELL (& THE STREET) |
Bearsted |
From A20 Ashford Road to Church Lane (inc The Street) (Micro Surfacing) |
Programmed for August 2022 |
TONBRIDGE ROAD |
Barming |
South Lodge Bends to North Street (Micro Surfacing) |
Programmed for August 2022 |
CHART ROAD |
Sutton Valence |
A274 Sutton Valence Hill to Church Road (Micro Surfacing) |
Programmed for August 2022 |
MAIDSTONE ROAD |
Marden |
High Street to Hartridge (Micro Surfacing) |
Programmed for August 2022 |
Appendix B – Drainage Repairs & Improvements
Drainage Repairs & Improvements - Contact Officer Earl Bourner |
|||
Parish |
Description of Works |
Current Status |
|
Eyhorne/Upper Street/Hollingbourne Hill |
Hollingbourne |
Various repairs to the highway drainage system completed. Further work required to reinstate outfall to pond. |
Further landowner liaison required. Anticipate undertaking further works in Summer. |
Harp Farm Road |
Boxley |
Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered. Permanent Road Liable to Flooding signs have been installed on site. |
Ground investigations for replacement soakaway design being undertaken w/c 20th June 2022. |
Lenham Road |
Headcorn |
Ditch overflowing onto carriageway |
Land drainage team to reassess when water subsides – Ongoing |
Warmlake road |
Chart Sutton |
Replace entire length of broken mainline to outfall |
Works Completed |
Holmoaks |
Maidstone |
Maintenance to existing system to stop damage to footway in park |
Complete however further investigation is required. Site meeting 05/07/2022 |
The Street |
Ulcombe |
Repair broken pipework leading to stream |
Works Cancelled. Being assessed with Southeast Water for repairs. |
Buckland road |
Maidstone |
Repair broken pipework at entrance to school |
Works Completed |
Trapfield close |
Bearsted |
Repair section of broken pipe to alleviate property flooding |
Works Completed |
East Street |
Hunton |
Investigate cause of sunken driveway – 600mm piped culvert running underneath |
Works Competed |
Coldbridge Lane |
Boughton Malherbe |
Installing 600mm x 600mm chamber over collapsed culvert. |
Works programmed for 01/07/2022 |
Mote Road |
Maidstone |
Repair 1m of pipe causing flooding and sinking block paving. |
Works programmed for 27/06/2022 |
Upper Fant Road |
Maidstone |
Lifting kerbs, increasing the cover size of gully, and resurfacing to alleviate property flooding |
Passed to contractor, awaiting date |
Chatham Road |
Maidstone |
Replacing broken pipework to alleviate flooding at the bus stops. |
Works to take place in September due to SGN works |
Northumberland Road |
Maidstone |
Carriageway collapse at junction with Oxford Road. Operations crew dug down and found broken gully lead and broken sewer. |
Drainage team taken over site. Site meeting held with Southern Water 21/06/2022 and remedial works agreed to complete before end of June. |
Appendix C– Street Lighting
Column replacement testing of KCC owned streetlights has identified the following as requiring. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Road Name |
Location |
Description of Works |
Status |
Tonbridge Road KTBU022 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Tonbridge Road KTBU051 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Sutton Road KSGF007 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Thornhill Place KTBG002 |
Maidstone |
Replacement Street Light |
Completed |
Farleigh Hill KFAH002 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
King Street KKAM013 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Loose Road KLCQ055 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Brishing Lane KBFE010 |
Maidstone |
Replacement Street Light |
Completed |
Ashford Road KABQ005 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Ashford Road KABQ017 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Ashford Road KABQ019 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Faversham Road KFAQ007 |
Harrietsham |
Replacement Street Light |
Completed |
Old Ashford Road KOAG011 |
Harrietsham |
Replacement Street Light |
Completed |
Old Ashford Road KOAG012 |
Harrietsham |
Replacement Street Light |
Completed |
Tonbridge Road KTBU025 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Westerhill Road KWBP001 |
Coxheath |
Replacement Street Light |
Completed |
Heath Road KHCH024 |
Coxheath |
Replacement Street Light |
Completion end November 22 |
Amsbury Road KAAV004 |
Coxheath |
Replacement Street Light |
Completion end November 22 |
Granville Road KGBG005 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Tower Lane KTCC002 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Willington Street KWCY317 |
Shepway |
Replacement Street Light |
Completed |
Forstal Lane KFCB008 |
Coxheath |
Replacement Street Light |
Completed |
Lower Stone Street KLCZ508 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Loose Road KLCQ552 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
The Meadows KMAS501 |
Tovil |
Replacement Lit sign |
Completion end November 22 |
South Park Road KSCX504 |
Shepway |
Replacement Lit sign |
Completion end November 22 |
Brunswick Street east KBFZ503 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Fairmeadow KFAE509 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Fairmeadow KFAE512 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Fairmeadow KFAE508 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Camden Street KCAD503 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
Camden Street KCAD504 |
Maidstone |
Replacement Lit sign |
Completion end November 22 |
King Street KKAM006 |
Maidstone |
Replacement Street Light |
Completion end November 22 |
Station Road KSFA031 |
Staplehurst |
Replacement Street Light |
Completion end November 22 |
Station Approach KSES001 |
Staplehurst |
Replacement Street Light |
Completion end November 22 |
Appendix D – Transportation and Safety Schemes
Casualty Reduction Measures
The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough, to meet Kent County Council’s strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Status correct as of 19th July 2022.
Local Transport Plan Funded Schemes – Contact Officer: David Petcher |
||
Road Name |
Description of Works |
Current Status |
Casualty reduction measures (reactive) – Maidstone Borough |
||
Running Horse Turbo Roundabout |
Conversion of existing junction to a turbo roundabout |
Design |
|
|
|
LTP Schemes Maidstone Borough |
||
Hart Street/Barker Road |
Experimental one-way scheme - 18-month trial |
Design |
London Road P&R and Hospital Cycle Route |
Completion of cycle link |
On Hold |
Pheasant Lane, Maidstone |
Shared route improvements |
Investigation |
Externally Funded Schemes
The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough funded by external corporations whilst still meeting Kent County Council’s strategic targets with the road network.
Externally Funded Schemes – Contact Officer: David Petcher |
|||
Road Name |
Description of Works |
Current Status |
|
A249 Detling Hill |
50mph speed limit |
Complete |
|
Boxley Road, Speed Review |
As part of the LPR for Maidstone, it has been identified that there is an AQ issue around the North Downs Woodland. One of the options being explored to mitigate this impact is around a speed reduction on Boxley Road. |
Complete |
|
Appendix E – Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Sarah Parris |
Scheme Name |
File Ref. |
Officer |
Parish |
Description of Works |
Current Status |
Bell Farm, North Street |
MA003098 |
SN |
Barming |
New accesses to split sites, shared surface, and new crossing point |
Highway works completed. Stage 3 Safety Audit Awaited. |
Barty Farm, Roundwell |
MA003278 |
AD |
Bearsted |
New Bellmouth and Lining works |
Defects issued |
Cross Keys |
MA003100 |
JH |
Bearsted |
New access, crossing point and parking area |
Phase 1 works due 14/03/22, Phase 2 works due 11/04/22. |
Bicknor Road |
MA003256 |
AP |
Bicknor |
Formation of hard surfaced passing places |
Awaiting technical approval |
Lyewood Farm, Green Lane |
MA3247 MA3248 |
AP |
Boughton Monchelsea |
New housing development and access |
Awaiting completion of remedial works |
Hubbards Lane |
MA003084 |
CV |
Boughton Monchelsea |
Two accesses to minor developments |
Works near end of maintenance |
Heath Road/Church Street |
MA003111 |
SP |
Boughton Monchelsea |
New access, footway works, yellow lines and crossing upgrade |
Into maintenance from defect works. |
Church Road/Deringwood Drive/Willington Street/Spot Lane |
MA003426/ MA003429/ MA003430/ MA003431/MA003436/ MA003437 |
SP |
Boxley |
Alterations to existing highway to include traffic signals, widening of road and junction widening/narrowing |
Deringwood Drive/Church Road ongoing works, Willington Street works due March 23 Church Road works on hold due to planning issue with width of road and hedges. |
Heath Road, Coxheath |
MA003134 |
SP |
Coxheath |
New access and new footway adj medical centre |
Awaiting completion of snagging for adoption |
Heath Road (North side – Murdoch Chase) |
MA003063 |
CV |
Coxheath |
New access and Footway work |
At Final remedial stage prior to adoption |
Forstal Lane |
MA003141 |
SP |
Coxheath |
Widening of road and new footpath with access to new development |
Drainage defects complete into maintenance period. |
Land north of Heath Road Phase 2 |
MA3257 |
SP |
Coxheath |
Access to new development |
Still awaiting defective works to be completed |
Gatland House, Gatland Lane |
MA003081 |
CV |
Fant |
Parking restrictions, signage, road markings and tactile crossings |
Due for Adoption |
Bell Farm, Ashford Road |
MA003094 |
CV |
Harrietsham |
Realignment of Church Road to form new access onto A20. New footway along A20 |
Works in maintenance |
Harrietsham Primary School |
MA3388 |
CV |
Harrietsham |
New access to car park, extend traffic calmed area |
Works in maintenance |
Forge Meadows |
MA3253 |
AP |
Headcorn |
Access to two new properties and vehicle crossovers to existing properties |
Works Adopted |
Oak Lane and Wheeler Street |
MA003048 |
CV |
Headcorn |
New footway plus junction improvements |
Works at end of maintenance, final remedials due |
Grigg Lane, Lenham Road,
|
MA003050 |
CV |
Headcorn |
Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane |
Works near end of maintenance |
Lenham Road (South side) |
MA003057 |
CV |
Headcorn |
New access road works and footway. |
Footway and speed gateway works scheduled for completion end of July |
Lenham Road (North side) |
MA003062 |
CV |
Headcorn |
New Footway and site access |
At Final remedial stage prior to adoption |
Mill Bank Headcorn |
MA3119 |
CV |
Headcorn |
New bus stops and extend 30mph zone |
Works carried out in spring, before resurfacing. Remaining footway and additional road markings to complete. |
Stonestile Road |
MA003412 |
JH |
Headcorn |
New access to 12 houses |
Works underway |
Gibbs Farm Grigg Lane & Wheeler Street |
MA3250 |
SAS |
Headcorn |
Access Gibbs Farm development, zebra crossing on Wheeler St |
Works Complete, RSA3 raised defects, waiting for developer to act on these. |
Ulcombe Road |
MA003150 |
SP |
Headcorn |
Access to new development |
Works complete now in maintenance |
Woodcut Farm, Ashford Road |
MA00 |
SP |
Hollingbourne |
Alterations to A20 and access for new development |
Technical Approval almost given, and access works already commenced. |
Genco Office |
MA003433 |
SP |
Hollingbourne |
New Access to Business and carriageway alterations |
Works completed, awaiting snagging and Woodcut works to complete. |
Ledian Farm |
MA003086 |
JH |
Leeds |
New access and bus stop works |
Access in maintenance period, bus stop to be started in due course |
Westwood Park, Ham Lane |
MA003305 |
AP |
Lenham |
Main and emergency accesses to new housing dev. |
Works Completed. Start of maintenance delayed |
Old Ashford Road, Adj Groom Way |
MA003356 |
AP |
Lenham |
New access and footway |
Works in progress |
8 Faversham Road |
MA003032 |
CV |
Lenham |
New access |
In maintenance, streetlight to replace |
The Paddocks, Ashford Road (Grove House, Old Ashford Road) |
MA3114 |
CV |
Lenham |
New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd |
Adoption imminent |
Headcorn Road Adj Rail bridge |
MA3404 |
CV |
Lenham |
New access road and extend 30mph limit |
In Maintenance (additional works to improve crossing point at station approach agreed by Network Rail - to be scheduled) |
Loder Close |
MA3424 |
JH |
Lenham |
New bell mouth access and footway |
Under review |
Heath Road |
MA3326 |
JH |
Linton |
New Access |
In Maintenance Period |
Gleamingwood Drive |
MA003441/MA003440 |
SP |
Lordswood |
New Access and development |
Going through Technical Approval |
Bicknor Green, Gore Court Road |
MA003053 |
AD |
Maidstone |
Change of road priorities and widening / upgrading |
In Maintenance |
Oakapple Lane/ Hermitage Lane |
MA003046 |
AD |
Maidstone |
New bellmouth junction and associated ancillary works incl new bus stop, for new development |
Paperwork outstanding prior to adoption |
St Saviours Road, Maidstone |
MA003136 |
AD |
Maidstone |
Changes to layout for Morrisons Junction |
Agreement signed |
Buffkyn Way / Sutton Road |
MA003218 |
AD |
Maidstone |
Signalisation of the junction |
Approved – not signed |
The Poplars, Ashford Road |
MA3254 |
AP |
Maidstone |
Access to new development |
Works Adopted |
Springwood Road Maidstone |
MA003438 |
AP |
Maidstone |
Stopping up of existing access and provision of new through footway |
In Maintenance |
531 Tonbridge Road |
MA003045 |
CV |
Maidstone |
Service layby for new retail unit |
Adoption imminent |
Wallis Avenue Phase 3, Parkwood |
MA003085 |
CV |
Maidstone |
Redevelopment of car park & shops opp. Longshaw Rd |
Works in maintenance |
Maidstone East Station |
MA3447 |
CV |
Maidstone |
Footway upgrade (& private parking improvement) |
Works completed |
Royal Engineers Rd/Mill Lane |
MA3312 |
JH |
Maidstone |
Access to New Development |
Revised scheme under Technical Review after comments from local Members |
Medway Street |
MA3326 |
JH |
Maidstone |
Subway Flood Protection Works |
Awaiting input from scheme promotor – no information received |
Howard Drive |
MA003303 |
SP |
Maidstone |
Junction works to facilitate Bus Gateway entrance to Croudace site |
TRO going through |
Hermitage Lane, (opp. Maidstone Hospital) |
MA003060 |
SP |
Maidstone |
New Traffic signal junction |
In Maintenance. Remedials being completed |
Hermitage Lane/ Howard Drive |
MA003070 |
SP |
Maidstone |
New access for development (opposite the quarry entrance) |
Awaiting final snagging items |
Union Street, Car Park |
MA003319 |
SP |
Maidstone |
New Access to development and footway works |
Works complete now in maintenance |
Castle Dene, Maidstone |
MA003352 |
SP |
Maidstone |
New Access and further footway work and repairs |
Works completed |
Perryfield Street |
MA3411 |
SP |
Maidstone |
New footpath/access to new houses |
Works complete now in maintenance. |
Oakapple Phase 2A, Hermitage Lane |
MA003444 |
SP |
Maidstone |
Development adjoining existing development |
Going through Technical Approval |
Langley Park Farm |
MA003130 |
AD |
Maidstone / Langley |
New Roundabout and associated works for entrance to Countryside Estate |
Works complete |
MAP Depot, Goudhurst Road |
MA003012 |
CV |
Marden |
New bellmouth junction and footway |
Final Remedials due, (mini-SID provided to Parish for monitoring traffic flows) |
The Parsonage, Goudhurst Road |
MA003066 MA003067 |
CV |
Marden |
New access and associated upgrade works |
In maintenance |
Napoleon Drive and Plain Road |
MA003079 |
CV |
Marden |
New access on each road for new housing development |
Adoption imminent |
Goudhurst Road/West End (Plain Road Development) |
MA3118 |
CV |
Marden |
Refurbish Zebra crossing outside school and Bus Borders to add by Library stops. |
Adopted |
Albion Road, Marden |
MA003132 |
SP |
Marden |
New Access & development |
Snagging works for S278 and S38 ongoing |
Fishers Farm (West), Headcorn Road (Bovis) (off-site works) |
MA3037/1 |
AP |
Staplehurst |
Pedestrian crossovers on Headcorn Road/ |
Works completed, remedial works completed, stage 3 road safety audit response required before first certificate issue |
Oliver Road Staplehurst |
MA003019 |
CV |
Staplehurst |
Ped crossing to Marden Road, junction markings and bus boarders |
Near end of maintenance – documentation to be received |
Hen and Duckhurst Farm, Marden Road |
MA003109 |
CV |
Staplehurst |
New Roundabout for development access |
In Maintenance, additional speed roundels etc to be added |
High Street Staplehurst |
MA3446 |
CV |
Staplehurst |
2 x new bus stop upgrades (kerbs and markings) |
Works Completed |
Fishers Farm (East) Headcorn Road (Redrow) |
MA3106 |
SP |
Staplehurst |
Realignment and new access at Headcorn Road/Pile Lane junction |
Works still ongoing
|
Sainsbury’s new site Station Rd |
MA3387 |
SP |
Staplehurst |
Roundabout and new access |
Cert one issued in maintenance period |
Pristling Lane |
MA3415 |
SP |
Staplehurst |
Widened access & Ditch works |
Cert one issued in maintenance |
Sapphire Kennels Headcorn Road |
MA3407 |
AP |
Sutton Valence |
Access to new development and 40mph extension |
Works in Maintenance |
Valdene Industrial Estate |
MA003054 |
CV |
Sutton Valence |
Upgrade of existing bellmouth and extension to f/w |
At final remedials stage prior to adoption |
The Oaks, Maidstone Road |
MA003078 |
CV |
Sutton Valence |
Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing. |
In maintenance |
Appleacres, Maidstone Road |
MA003152 |
SP |
Sutton Valence |
Access to new development and footway works |
Adoption imminent |
Warmlake Nurseries |
MA003443 |
SP |
Sutton Valence |
New access to small development |
Only footway connection outstanding. |
Farleigh Hill Tovil (Opp KCC waste site) |
MA3413 |
AP |
Tovil |
New access opp Burial Ground Ln KCC Recycling centre |
Site now under new ownership. Full S278 agreement being worked on by Legal |
Farleigh Heights opposite cottages 129-147 Dean Street/Farleigh Hill |
MA003007 |
CV |
Tovil |
New access, new footway, and bus stop provision |
Adopted |
Cripple Street Maidstone |
MA003093 |
CV |
Tovil |
New access to development, widening and footway works |
Adopted |
Tovil Green Lane |
MA003095 |
CV |
Tovil |
New Footway and crossing point to side of site |
In maintenance |
Mount Ave/Blunden Lane |
MA3180 |
CV |
Yalding |
New accesses at site entrance |
Adoption imminent |
Vicarage Road |
MA003121 |
SP/JH |
Yalding |
New access to development and speed restraints on existing Highway |
Under review |
Yalding Business Park, Hampstead Lane |
MA003450 |
JH |
Yalding |
New accesses into business park |
Under review |
Old Ham Lane |
MA003448 |
SP |
Lenham |
C/W widening and footway for new development |
Technical review in progress |
Old Ham Lane |
MA003452 |
SP |
Lenham |
Access and development of 136 properties including Bus link |
Initial talks taken place. |
Appendix F – Bridge Works
Bridge Works – Contact Officer: Helen Rowe |
|||
Parish/Town |
Description of Works |
Current Status |
|
|
|
None |
|
Appendix G – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler |
||
Location |
Description of Works |
Current Status |
A229 Loose Road / Armstrong Road |
Modification of existing junction including road widening and pedestrian crossing improvements |
Programmed |
A229 Hayle Road / Campbell Road, Maidstone (11-0433) |
Refurbish existing traffic signal-controlled junction |
Not yet programmed |
Appendix H - Combined Members Grant programme update
Member Highway Fund programme update for the Maidstone Borough Council
The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are
· in design
· at consultation stage
· about to be programmed
· recently completed on site.
The list is up to date as of 19th July 2022 and will not include any schemed completed prior to 1st June 2022
The details given below are for highway projects only. This report does not detail
· contributions Members have made to other groups such as parish councils
· highway studies
· traffic/ non-motorised user surveys funded by Members.
More information on the schemes listed below can be sought by contacting west.highwayimprovements@kent.gov.uk.
Details of Scheme |
Status |
Upper Stone Street, Maidstone – Request for zebra crossing. Member would like a feasibility study carried out |
Investigation |
Details of Scheme |
Status |
Yeomans Lane around Bearsted Green – Request for 20mph speed limit |
Investigation |
Details of Scheme |
Status |
Upper Stone Street, Maidstone - Request for zebra crossing. Member would like a feasibility study conducted. |
Investigation |
Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contacts: Richard Emmett/ Susan Laporte 03000 418181