To:                              Maidstone Joint Transportation Board

 

By:                              KCC Highways and Transportation

 

Date:                           19th October 2022

 

Subject:                      Highways Forward Works Programme: 2022/23 and 2023/24

 

Classification:           Information Only

 

 

Summary: This report updates Members on the identified schemes approved for construction

 

 

1. Introduction

 

This report provides an update and summarises schemes that have been programmed for delivery in 2022/23 and 2023/24.

 

In summer 2021 Kent County Council published a Highways Asset Management Plan (HAMP), which included, as Appendix C, a five-year Forward Works Programme for the years 2021/22 to 2025/26.  this reflected the need to move away from annual programmes and to consider asset management activity a multi-year one.

 

The first part of the programme concerned the two years 2021/22 - 2022/23. Around half of the schemes included in that programme have now been delivered, and as a result we have now produced a new programme covering the years 2022/23 - 2024/24. As before, most of the sites included in this programme have already been verified by our engineers.

 

The second part of our programme related to years three to five of our five-year programme (2023/24 - 2025/26). This too needs revision to cover the years 2024/25 – 2026/27, and the work required to do this is currently in progress. As before, our new year’s three to five programme will be largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.

 

This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, inflationary pressures such as material price increases, conflicting works, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react to keep the highway in a safe and serviceable condition.

 

Further information about how we manage our highway infrastructure, including our county-wide five-year forward works programme, may be found on our website:

 https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways-policies/managing-highway-infrastructure

 

In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way.

 

 

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

           

Drainage Repairs & Improvements – see Appendix B

 

Street Lighting – see Appendix C

 

Transportation and Safety Schemes see Appendix D

  • Casualty Reduction Measures
  • Externally Funded Schemes

 

Developer Funded Works – see Appendix E

 

Bridge Works see Appendix F

 

Traffic Systems – see Appendix G

 

Combined Members Grant – Member Highway Fund – see Appendix H

 

Parish Council Highway Improvement Plans Update – see Appendix I

 

 

 

Conclusion

 

1.    This report is for Members’ information.

 

Contact Officers:

 

The following contact officers can be contacted on 03000 418181

 

Richard Emmet                                 Senior Highway Manager

Susan Laporte                                    Maidstone Highway Manager

Alan Casson                                        Strategic Asset Manager                   

Earl Bourner                                       Drainage Asset Manager

Helen Rowe                                        Structures Asset Manager

Sue Kinsella                                        Street Light Asset Manager

Toby Butler                                         Traffic & Network Solutions Asset Manager

Jamie Hare                                         Development Agreements Manager

Nikola Floodgate                                 Road Safety and Active Travel Group Manager

           


Appendix A – Footway and Carriageway Improvement Schemes

 

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

 

 

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name

Parish

Extent of Works

Current Status

A274 Sutton Road

Maidstone

Wheatsheaf junction to Northumberland Road

 

Completed

A249 Detling Hill

Thurnham

Entry slip to Detling Showground

 

Completed

A20 Ashford Road

Maidstone

Between 30mph/40mph gateway east of Turkey Mill and Huntsman Lane

 

Completed

 

Footway Improvement - Contact Officer Mr Neil Tree

Road Name

Parish

Extent and Description of Works

Current Status

West Walk

Barming

 

Footway Reconstruction

Entire Length (Between the junctions with Queens Road and Cherry Orchard Way). 

 

 

 

Completed

 

Nottingham Avenue

Maidstone

 

Footway Protection Treatment From the junction with Sutton Road to York House/ Llandaff House

 

 

 

Completed

 

 

 

Leicester Road

Maidstone

 

Footway Protection Treatment from the Essex Road roundabout to York House

 

 

 

Completed

 

 

 

Middlesex Road

 

 

Maidstone

 

Footway Protection Treatment from the Essex Road roundabout to Llandaff House

 

 

 

Completed

 

 

 

Old Tovil Road

 

 

Maidstone

 

Footway Protection Treatment From the junction with College Road to Hayle Road including upper footways.

 

 

 

Programmed to be completed in October.

Surface Treatments – Contact Officer Mr Jonathan Dean

Road Name

Parish

Extent and Description of Works

Current Status

CLAYGATE ROAD (PART)

Marden

Jarmons Lane to Claygate Road

(In situ Road Recycling)

 

Complete

JARMONS LANE (PART)

Collier Street

Collier Street to Claygate Road

(In situ Road Recycling)

 

Complete

SPENNY LANE

Collier Street

Claygate Road to Martins Fruit Farm

(In situ Road Recycling)

 

Complete

CHART ROAD

Sutton Valence

Church Road to Chart Hill Road

(In situ Road Recycling)

 

Complete

CRUMPS LANE

Ulcombe

Headcorn Road to Lenham Road

(In situ Road Recycling)

 

Complete

 

TILDEN LANE

Marden

Stilebridge Lane to Underlyn Lane

(Surface Dressing)

Complete

 

GRIGG LANE (PHASE 2)

Headcorn

Grigg Farm/Baker Lane to Oak Lane

(Surface Dressing)

Complete

 

STILEBRIDGE LANE

Marden

Linton Hill to Underlyn Lane

(Surface Dressing)

Complete

 

WHITE HOUSE LANE

Headcorn

Shenley Road to A274 Biddenden Road

(Surface Dressing)

Complete

 

HEATH ROAD

Linton

Brishing Lane to A229 Linton Hill

(Surface Dressing)

Complete

 

TONBRIDGE ROAD

Teston (Barming)

Church Road, Teston to South Lodge Bends

(Surface Dressing)

Complete

 

ASHFORD ROAD

Bearsted

Roundwell to Otham Lane

(Surface Dressing)

Complete

 

MAIDSTONE ROAD

Staplehurst

George Street to Couchman Green Lane

(Surface Dressing)

Complete

UPPER STREET

Leeds

Horseshoes Lane to Blair House

(Micro Surfacing)

 

Complete

MARLEY ROAD (DICKLEY LANE)

Lenham (Harrietsham)

Marley Works to Steeds Hill

(Micro Surfacing)

 

Postponed until 2023

NORTH STREET

Barming

From Heath Road to A26 Tonbridge Road

(Micro Surfacing)

 

Complete

GRIGG LANE (PHASE 3) Section not done due to covid vaccination centre access

Headcorn

Headcorn Surgery (The Hardwicks) to Oak Lane

(Micro Surfacing)

 

Postponed until 2023

MALLING ROAD

Teston

Whole Road

(Micro Surfacing)

 

Complete

LEES ROAD (INC LADDINGFORD & CLAYGATE ROAD)

Laddingford

From Lees Road to 200 metres past Laddingford School

(Micro Surfacing)

 

Complete

PATTENDEN LANE

Marden

Underlyn Lane to West End

(Micro Surfacing)

 

Postponed until 2023

MAIDSTONE ROAD

Marden

 New Barn Cottage to A229

(Micro Surfacing)

 

Complete

THE STREET

Bredhurst

Forge Lane to County Boundary (Medway)

(Micro Surfacing)

 

Complete

ROUNDWELL (& THE STREET)

Bearsted

From A20 Ashford Road to Church Lane (inc The Street)

(Micro Surfacing)

 

Postponed until 2023

TONBRIDGE ROAD

Barming

South Lodge Bends to North Street

(Micro Surfacing)

 

Complete

CHART ROAD

Sutton Valence

A274 Sutton Valence Hill to Church Road

(Micro Surfacing)

 

Complete

MAIDSTONE ROAD

Marden

High Street to Hartridge

(Micro Surfacing)

 

Complete

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B – Drainage Repairs & Improvements

 

Drainage Repairs & Improvements - Contact Officer Earl Bourner 

Road Name

Parish

Description of Works

Current Status

Harp Farm Road

Boxley

Existing soakaway unmaintainable due to location in field. Replacement soakaway(s) to be considered. Permanent Road Liable to Flooding signs have been installed.

New drainage system under construction for completion early October 2022.

Holmoaks

Maidstone

Maintenance to existing system to stop damage to footway in park

Works Completed.

Coldbridge Lane

Boughton Malherbe

Installing 600mm x 600mm chamber over collapsed culvert.

Works Completed.

Mote Road

Maidstone

Repair 1m of pipe causing flooding and sinking block paving.

Works Completed.

Upper Fant Road

Maidstone

Lifting kerbs, increasing the cover size of gully, and resurfacing to alleviate property flooding

Works Completed.

Chatham Road

Maidstone

Replacing broken pipework to alleviate flooding at the bus stops.

Works Completed.

Northumberland Road

Maidstone

Carriageway collapse at junction with Oxford Road. Operations crew dug down and found broken gully lead and broken sewer.

Works Completed.

Eccleston Road

Maidstone

Pipe collapse adjacent to property No.46. Crew required to dig down and replace.

Works required to take place during October school half term due to TM requirements.

Gabriel’s Hill

Maidstone

Non-Return Valves required to be fitted outside shops due to strong sewage smell.

Works completed. Further investigation works required.

Church Road

Boughton Malherbe

Consistent Leak from carriageway, water test has shown chlorine.

Southeast water investigating further.

Woodcock Lane

Boughton Malherbe

Regular flooding, water bypassing ditches.

Works are in conjunction with issue on Church Road.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix C – Street Lighting

 

Column replacement testing of KCC owned streetlights has identified the following as requiring. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.  

 

Road Name

Location

Description of Works

Status

Tonbridge Road KTBU022

Maidstone

 

Replacement Street Light

Completion end February 23

Tonbridge Road KTBU051

Maidstone

 

Replacement Street Light

Completion end February 23

Sutton Road KSGF007

Maidstone

 

Replacement Street Light

Completion end February 23

Farleigh Hill KFAH002

Maidstone

 

Replacement Street Light

Completion end February 23

King Street KKAM013

Maidstone

 

Replacement Street Light

Completion end February 23

Loose Road               KLCQ055

Maidstone

 

Replacement Street Light

Completion end February 23

Ashford Road     KABQ005

Maidstone

 

Replacement Street Light

Completion end February 23

Ashford Road KABQ017

Maidstone

 

Replacement Street Light

Completion end February 23

Ashford Road KABQ019

Maidstone

 

Replacement Street Light

Completion end February 23

Tonbridge Road          KTBU025

 

Maidstone

 

 

Replacement Street Light

 

Completion end February 23

Heath Road KHCH024

Coxheath

 

Replacement Street Light

Completed

Amsbury Road KAAV004

Coxheath

 

Replacement Street Light

Completed

Granville Road KGBG005

Maidstone

 

Replacement Street Light

Completion end February 23

Tower Lane KTCC002

Maidstone

 

Replacement Street Light (RC)

Completion end February 23

Lower Stone Street KLCZ508

Maidstone

 

Replacement Lit sign

Completion end February 23

Loose Road KLCQ552  

Maidstone

 

Replacement Lit sign

Completion end February 23

The Meadows KMAS501

Tovil

 

Replacement Lit sign

Completed

South Park Road KSCX504

Shepway

 

Replacement Lit sign

Completed

Brunswick Street east KBFZ503

Maidstone

 

Replacement Lit sign

Completed

Fairmeadow KFAE509

Maidstone

 

Replacement Lit sign

Completion end February 23

Fairmeadow KFAE512

Maidstone

 

Replacement Lit sign

Completion end February 23

Fairmeadow KFAE508

Maidstone

 

Replacement Lit sign

Completion end February 23

Camden Street KCAD503

Maidstone

 

Replacement Lit sign

Completed

Camden Street KCAD504

Maidstone

 

Replacement Lit sign

Completed

King Street KKAM006

Maidstone

 

Replacement Street Light

Completion end February 23

Station Road KSFA031

Staplehurst

 

Replacement Street Light

Completion end February 23

Station Approach KSES001

Staplehurst

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR002

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR003

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR004

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR005

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR006

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR007

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR008

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR009

Bearsted

 

Replacement Street Light

Completion end February 23

Bell Meadow KBBR010

Bearsted

 

Replacement Street Light

Completion end February 23

Alexandra Street KAAN002

Maidstone

 

Replacement Street Light

Completion end February 23

North View KNBE002

Maidstone

 

Replacement Street Light

Completion end February 23

North View KNBE003

Maidstone

 

Replacement Street Light

Completion end February 23

Oakwood Court KOAD001

Maidstone

 

Replacement Street Light

Completion end February 23

Cross Keys KCGT001

Bearsted

 

Replacement Street Light

Completion end February 23

Bentlif Close KBBZ001

Maidstone

 

Replacement Street Light

Completion end February 23

Bentlif Close KBBZ002

Maidstone

 

Replacement Street Light

Completion end February 23

Maplesden Close KMBE001

Maidstone

 

Replacement Street Light

Completion end February 23

Maplesden Close KMBE002

Maidstone

 

Replacement Street Light

Completion end February 23

Maxwell Drive KMBW004

Allington

 

Replacement Street Light

Completion end February 23

Maxwell Drive KMBW008

Allington

 

Replacement Street Light

Completion end February 23

Maxwell Drive KMBW009

Allington

 

Replacement Street Light

Completion end February 23

Leonard Close KLBG002

Allington

 

Replacement Street Light

Completion end February 23

Ernest Drive KEBA001

Allington

 

Replacement Street Light

Completion end February 23


Appendix D – Transportation and Safety Schemes

 

Casualty Reduction Measures

 

The Schemes Planning & Delivery team is implementing schemes within Maidstone Borough council to meet Kent County Council’s strategic targets (for example, addressing traffic congestion or improving road safety).  Casualty reduction measures have been identified to address a known history of personal injury crashes. Status correct as of 01/06/22.

 

Local Transport Plan Funded Schemes – Contact Officer: Ryan Shield

Road Name

Description of Works

Current Status


Casualty reduction measures (reactive)

A229 Linton Hill jw Stilebridge Lane

Remedial works for CRM scheme

Design

A229 Running Horse Turbo Roundabout

Conversion of existing junction to a turbo roundabout, including all approaches (except for the M20 slip roads, as these are not maintained by Kent County

Council)

Design

LTP Schemes

Hart Street/Barker Road

Experimental one-way scheme - 18-month trial

Ordered

London Road P&R and Hospital Cycle Route

Completion of cycle link

On hold

 

 

Externally Funded Schemes

 

The Schemes Planning & Delivery team is implementing schemes within Maidstone borough council funded by external corporations whilst still meeting Kent County Council’s strategic targets with the road network.

 

Externally Funded Schemes – Contact Officer:

Road Name

Description of Works

Source of

Funding

Current Status

A249 Detling Hill

50mph speed limit

 

Complete

Park & Ride Signage

Removal of existing P&R signage following the closure of the sites by

Maidstone Borough Council (MBC). This work is to be funded by MBC.

 

Investigation


Appendix E – Developer Funded Works

 

Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Sarah Parris

 

Scheme Name

File Ref.

Officer

Parish

Description of Works

Current Status

Bell Farm, North Street

MA003098

SN

Barming

New accesses to split sites, shared surface, and new crossing point

Highway works completed. Stage 3 Safety Audit Awaited.

Barty Farm, Roundwell,

MA003278

AD

Bearsted

New Bellmouth and Lining works

Defects issued

Cross Keys

MA003100

JH

Bearsted

New access, crossing point and parking area

Works Completed

Bicknor Road

MA003256

AP

Bicknor

Formation of hard surfaced passing places

Awaiting technical approval


Lyewood Farm, Green Lane

MA3247

MA3248

AP

Boughton Monchelsea

New housing development and access

Awaiting completion of remedial works

Hubbards Lane

MA003084

CV

Boughton Monchelsea

Two accesses to minor developments

Minor works due prior to adoption

Heath Road/Church Street

MA003111

SP

Boughton Monchelsea

New access, footway works, yellow lines and crossing upgrade

Into maintenance from defect works.

Church Road/Deringwood Drive/Willington Street/Spot Lane

MA003426/ MA003429/ MA003430/ MA003431/MA003436/ MA003437

SP

Boxley

Alterations to existing highway to include traffic signals, widening of road and junction widening/narrowing

Deringwood Drive/Church Road ongoing works, Willington Street works due March 23 Church Road works on hold due to planning issue with width of road and hedges.

Heath Road, Coxheath

MA003134

SP

Coxheath

New access and new footway adj medical centre

Completion Certificate issued.

Heath Road

(North side – Murdoch Chase)

MA003063

CV

Coxheath

New access and Footway work

At Final remedial stage prior to adoption

Forstal Lane

MA003141

SP

Coxheath

Widening of road and new footpath with access to new development

Drainage defects complete into maintenance period.

Land north of Heath Road Phase 2

MA3257

SP

Coxheath

Access to new development

Defective works completed, now in further maintenance.

Gatland House, Gatland Lane

MA003081

CV

Fant

Parking restrictions, signage, road markings and tactile crossings

Due for Adoption

Bell Farm, Ashford Road

MA003094

CV

Harrietsham

Realignment of Church Road to form new access onto A20. New footway along A20

Works in maintenance

Harrietsham Primary School

MA3388

CV

Harrietsham

New access to car park, extend traffic calmed area

Works in maintenance

Forge Meadows

MA3253

AP

Headcorn

Access to 2 new properties and vehicle crossovers to existing properties

Works Adopted

Oak Lane and Wheeler Street

MA003048

CV

Headcorn

New footway plus junction improvements

Works at end of maintenance, final remedials due

Grigg Lane, Lenham Road,

 

MA003050

CV

Headcorn

Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane

Works near end of maintenance

Lenham Road (South side)

MA003057

CV

Headcorn

New access road works and footway.

Footway and speed gateway works done, remedials to do.

Lenham Road (North side)

MA003062

CV

Headcorn

New Footway and site access

At Final remedial stage prior to adoption

Mill Bank Headcorn

MA3119

CV

Headcorn

New bus stops and extend 30mph zone

Works mostly completed before resurfacing. Minor works & additional road markings to complete.

Stonestile Road

MA003412

JH

Headcorn

New access to 12 houses

Works underway

Gibbs Farm Grigg Lane & Wheeler Street

MA3250

SAS

Headcorn

Access Gibbs Farm development, zebra crossing on Wheeler St

Works Complete, RSA3 raised defects, waiting for developer to act on these.

Ulcombe Road

MA003150

SP

Headcorn

Access to new development

Works complete now in maintenance

Woodcut Farm, Ashford Road

MA00

SP

Hollingbourne

Alterations to A20 and access for new development

Technical Approval given, awaiting clarification of internal Bus Stop prior to completion of agreement.

Genco Office

MA003433

SP

Hollingbourne

New Access to Business and carriageway alterations

Works completed, awaiting snagging and Woodcut works to complete.

Ledian Farm

MA003086

JH

Leeds

New access and bus stop works

Works completed and adopted

Westwood Park, Ham Lane

MA003305

AP

Lenham

Main and emergency accesses to new housing dev.

Works Completed. Start of maintenance delayed

Old Ashford Road, Adj Groom Way

MA003356

AP

Lenham

New access and footway

Works in progress

8 Faversham Road

MA003032

CV

Lenham

New access

In maintenance, streetlight to replace

The Paddocks, Ashford Road (Grove House, Old Ashford Road)

MA3114

CV

Lenham

New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd

Remedials required prior to adoption

Headcorn Road

Adj Rail bridge

MA3404

CV

Lenham

New access road and extend 30mph limit

In Maintenance (additional works to improve crossing point at Station approach agreed by Network Rail - to be scheduled)

Loder Close

MA3424

JH

Lenham

New bell mouth access and footway

Under review

Heath Road

MA3326

JH

Linton

New Access

In Maintenance Period

Gleamingwood Drive

MA003441/MA003440

SP

Lordswood

New Access and development

Going through Technical Approval.

Scheme on Hold

Bicknor Green, Gore Court Road

MA003053

AD

Maidstone

Change of road priorities and widening / upgrading

In Maintenance

Oakapple Lane/Robinson Lane

MA003046

AD

Maidstone

New bellmouth junction and associated ancillary works incl new bus stop, for new development

Paperwork outstanding prior to adoption

St Saviours Road, Maidstone

MA003136

AD

Maidstone

Changes to layout for Morrisons Junction

Agreement signed

Buffkyn Way / Sutton Road

MA003218

AD

Maidstone

Signalisation of the junction

Approved – not signed

The Poplars, Ashford Road

MA3254

AP

Maidstone

Access to new development

Works Adopted

Springwood Road Maidstone

MA003438

AP

Maidstone

Stopping up of existing access and provision of new through footway

In Maintenance

531 Tonbridge Road

MA003045

CV

Maidstone

Service layby for new retail unit

Adoption imminent

Wallis Avenue Phase 3, Parkwood

MA003085

CV

Maidstone

Redevelopment of car park & shops opp. Longshaw Rd

Works in maintenance

Maidstone East Station

MA3447

CV

Maidstone

Footway upgrade (& private parking improvement)

Works completed

Royal Engineers Rd/Mill Lane

MA3312

JH

Maidstone

Access to New Development

Revised scheme under Technical Review after comments from local Members awaiting design feedback on comments to date.

Medway Street

MA3326

JH

Maidstone

Subway Flood Protection Works

Awaiting input from scheme promotor – no information rec’d

Howard Drive

MA003303

SP

Maidstone

Junction works to facilitate Bus Gateway entrance to Croudace site

Awaiting completion of Lighting for new signs to place into maintenance.

Hermitage Lane, (opp. Maidstone Hospital)

MA003060

SP

Maidstone

New Traffic signal junction

In Maintenance. Remedials being completed

Union Street, Car Park

MA003319

SP

Maidstone

New Access to development and footway works

Awaiting wall to be removed due to visibility issue.  Then will be adopted.

Castle Dene, Maidstone

MA003352

SP

Maidstone

New Access and further footway work and repairs

Works completed

Perryfield Street

MA3411

SP

Maidstone

New footpath/access to new houses

Works complete now in maintenance.

Oakapple Phase 2A, Hermitage Lane

MA003444

SP

Maidstone

Development adjoining existing development

Going through Technical Approval

Langley Park Farm

MA003130

AD

Maidstone / Langley

New Roundabout and associated works for entrance to Countryside Estate

Works complete

MAP Depot, Goudhurst Road

MA003012

CV

Marden

New bellmouth junction and footway

Final Remedials due, (mini-SID provided to Parish for monitoring traffic flows)

The Parsonage, Goudhurst Road

MA003066

MA003067

CV

Marden

New access and associated upgrade works

In maintenance

Napoleon Drive and Plain Road

MA003079

CV

Marden

New access on each road for new housing development

Adoption imminent

Albion Road, Marden

MA003132

SP

Marden

New Access & development

Snagging works for S278 and S38 ongoing

Fishers Farm (West), Headcorn Road (Bovis) (off-site works)

MA3037/1

AP

Staplehurst

Pedestrian crossovers on Headcorn Road/
Hurst Close

Works completed, remedial works completed, stage 3 road safety audit response required before first certificate issue

Oliver Road Staplehurst

MA003019

CV

Staplehurst

Ped crossing to Marden Road, junction markings and bus boarders

Near end of maintenance – documentation to be received

Hen and Duckhurst Farm, Marden Road

MA003109

CV

Staplehurst

New Roundabout for development access

In maintenance, additional speed roundels completed

High Street Staplehurst

MA3446

CV

Staplehurst

2 x new bus stop upgrades (kerbs and markings)

Works in maintenance

Fishers Farm (East) Headcorn Road (Redrow)

MA3106

SP

Staplehurst

Realignment and new access at Headcorn Rd/Pile Lane junction

Works still ongoing

 

Sainsbury’s new site Station Rd

MA3387

SP

Staplehurst

Roundabout and new access

Defective works awaiting completion re drainage issue.

Pristling Lane

MA3415

SP

Staplehurst

Widened access & Ditch works

Certificate 1 issued in maintenance

Sapphire Kennels Headcorn Road

MA3407

AP

Sutton Valence

Access to new development and 40mph extension

Works in Maintenance

Valdene Industrial Estate

MA003054

CV

Sutton Valence

Upgrade of existing bellmouth and extension to f/w

At final remedials stage prior to adoption

The Oaks, Maidstone Road

MA003078

CV

Sutton Valence

Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing.

In maintenance

Appleacres, Maidstone Road

MA003152

SP

Sutton Valence

Access to new development and footway works

Adoption imminent

Warmlake Nurseries

MA003443

SP

Sutton Valence

New access to small development

Only footway connection outstanding.

Farleigh Hill Tovil

(Opp KCC waste site)

MA3413

AP

Tovil

New access opp Burial Ground Ln KCC Recycling centre

Site now under new ownership. Full S278 agreement being worked on by Legal

Tovil Green Lane

MA003095

CV

Tovil

New Footway and crossing point to side of site

In maintenance

Mount Ave/Blunden Lane

MA3180

CV

Yalding

New accesses at site entrance

Adoption imminent

Vicarage Road

MA003121

SP/JH

Yalding

New access to development and speed restraints on existing Highway

Under review

Yalding Business Park, Hampstead Lane

MA003450

JH

Yalding

New accesses into business park

Under review – stopping up order underway.

Old Ham Lane

MA003448

CV

Lenham

C/W widening and footway for new development

Technical review in progress

Old Ham Lane

MA003452

CV

Lenham

Access and development of 136 properties including Bus link

Initial talks taken place.

 

 

 

Appendix F – Bridge Works

 

Bridge Works – Contact Officer: Helen Rowe

Road Name

Parish/Town

Description of Works

Current Status

 

 

None

 

 

 

 

 

 

 

 

 

 

 

 

Appendix G – Traffic Systems

 

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

 

Traffic Systems - Contact Officer: Toby Butler

Location

Description of Works

Current Status

A229 Loose Road / Armstrong Road
(11-0412)

Modification of existing junction including road widening and pedestrian crossing improvements

Started
October 2022

 A229 Hayle Road / Campbell Road, Maidstone (11-0433)

Refurbish existing traffic signal-controlled junction

Not yet programmed

 

 

 

Appendix H - Combined Members Grant programme update

 

Member Highway Fund programme update for the Maidstone borough council.

 

The following schemes are those, which have been approved for funding by both the relevant Member and by Haroona Chughtai, Director of Highways and Transportation. The list only includes schemes, which are

·         in design

·         at consultation stage

·         about to be programmed

·         recently completed on site.

 

The list is up to date as of 01/06/22

      

The details given below are for highway projects only.  This report does not detail

·         contributions Members have made to other groups such as parish councils

·         highway studies

·         traffic/ non-motorised user surveys funded by Members. 

 

There are no projects of this type to report.

 

 

 

 

 

 

 

 

 

Appendix I – Parish Council Highway Improvement Plans Update

 

Parish Councils can request and fund their own highway improvements to address local concerns that would not otherwise meet Kent County Council's intervention criteria. Parish Councils can highlight any non maintenance issue they would like to address via their Highway Improvement Plan (HIP), which will reviewed by KCC officers on an annual basis. Following this review, KCC will make suggestions as to what engineering measures may be appropriate. There is no dedicated budget to install items identified on the parish HIPS, but KCC can work with the parish to install small scale signing and lining improvements, or larger schemes which the parish may choose to fund themselves.

The following table details when a (HIP) was last received from each parish council. If a parish name is not shown, it means no HIP has been received over the past twelve months. This list is up to date as of 20/09/2022.

 

Parish Council

Last HIP Received

Chart Sutton

18th October 2021

Collier Street

10th November 2021

Langley

17th November 2021

Detling

22nd December 2021

Yalding

19th January 2022

Sutton Valence

24th January 2022

Broomfield and Kingswood

15th February 2022

Thurnham

23rd February 2022

Harrietsham

24th February 2022

Ulcombe

28th February 2022

Boughton Monchelsea

3rd March 2022

Marden

6th April 2022

Hunton

25th April 2022

Loose

21st June 2022

Stockbury

27th June 2022

Bearsted

28th June 2022

 


Legal Implications

1.1.1         Not applicable.

1.2               Financial and Value for Money Considerations

1.2.1         Not applicable.

1.3               Risk Assessment

1.3.1         Not applicable.

Contacts: Richard Emmet / Susan Laporte 03000 418181