Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Sarah Parris |
Scheme Name |
File Ref. |
Officer |
Parish |
Description of Works |
Current Status |
Bell Farm, North Street |
MA003098 |
SN |
Barming |
New accesses to split sites, shared surface, and new crossing point |
Highway works completed. Stage 3 Safety Audit Awaited. |
Barty Farm, Roundwell, |
MA003278 |
AD |
Bearsted |
New Bellmouth and Lining works |
Defects issued |
Cross Keys |
MA003100 |
JH |
Bearsted |
New access, crossing point and parking area |
Works Completed |
Bicknor Road |
MA003256 |
AP |
Bicknor |
Formation of hard surfaced passing places |
Awaiting technical approval |
Lyewood Farm, Green Lane |
MA3247 MA3248 |
AP |
Boughton Monchelsea |
New housing development and access |
Awaiting completion of remedial works |
Hubbards Lane |
MA003084 |
CV |
Boughton Monchelsea |
Two accesses to minor developments |
Minor works due prior to adoption |
Heath Road/Church Street |
MA003111 |
SP |
Boughton Monchelsea |
New access, footway works, yellow lines and crossing upgrade |
Works Adopted |
Church Road/Deringwood Drive/Willington Street/Spot Lane |
MA003426/ MA003429/ MA003430/ MA003431/MA003436/ MA003437 |
SP |
Boxley |
Alterations to existing highway to include traffic signals, widening of road and junction widening/narrowing |
Deringwood Drive/Church Road complete, Willington Street works due March 23 Church Road South works awaiting works date. |
Heath Road (North side – Murdoch Chase) |
MA003063 |
CV |
Coxheath |
New access and Footway work |
At Final remedial stage prior to adoption |
Forstal Lane |
MA003141 |
SP |
Coxheath |
Widening of road and new footpath with access to new development |
Works in maintenance. |
Land north of Heath Road Phase 2 |
MA3257 |
SP |
Coxheath |
Access to new development |
Defective works completed, now in further maintenance. |
Gatland House, Gatland Lane |
MA003081 |
CV |
Fant |
Parking restrictions, signage, road markings and tactile crossings |
Due for Adoption |
Bell Farm, Ashford Road |
MA003094 |
CV |
Harrietsham |
Realignment of Church Road to form new access onto A20. New footway along A20 |
Works in maintenance |
Harrietsham Primary School |
MA3388 |
CV |
Harrietsham |
New access to car park, extend traffic calmed area |
Works in maintenance |
Oak Lane and Wheeler Street |
MA003048 |
CV |
Headcorn |
New footway plus junction improvements |
Works at end of maintenance, final remedials due |
Grigg Lane, Lenham Road,
|
MA003050 |
CV |
Headcorn |
Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane |
Works near end of maintenance |
Lenham Road (South side) |
MA003057 |
CV |
Headcorn |
New access road works and footway. |
Footway and speed gateway works done, remedials to do. |
Lenham Road (North side) |
MA003062 |
CV |
Headcorn |
New Footway and site access |
At Final remedial stage prior to adoption |
Mill Bank Headcorn |
MA3119 |
CV |
Headcorn |
New bus stops and extend 30mph zone |
Works mostly completed before resurfacing. Minor works & additional road markings to complete. |
Stonestile Road |
MA003412 |
JH |
Headcorn |
New access to twelve houses |
Works underway |
Gibbs Farm Grigg Lane & Wheeler Street |
MA3250 |
SAS |
Headcorn |
Access Gibbs Farm development, zebra crossing on Wheeler St |
Works in maintenance. |
Ulcombe Road |
MA003150 |
SP |
Headcorn |
Access to new development |
Defect works required prior to adoption. |
Woodcut Farm, Ashford Road |
MA00 |
SP |
Hollingbourne |
Alterations to A20 and access for new development |
Await works start date. |
Genco Office |
MA003433 |
SP |
Hollingbourne |
New Access to Business and carriageway alterations |
Works in maintenance |
Westwood Park, Ham Lane |
MA003305 |
AP |
Lenham |
Main and emergency accesses to new housing dev. |
Works Completed. Start of maintenance expected January 2023 |
Old Ashford Road, Adj Groom Way |
MA003356 |
AP |
Lenham |
New access and footway |
Works completed. Reduced speed limit not yet implemented. |
8 Faversham Road |
MA003032 |
CV |
Lenham |
New access |
In maintenance, streetlight to replace |
The Paddocks, Ashford Road (Grove House, Old Ashford Road) |
MA3114 |
CV |
Lenham |
New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd |
Remedials required prior to adoption |
Headcorn Road Adj Rail bridge |
MA3404 |
CV |
Lenham |
New access road and extend 30mph limit |
Works completed and in Maintenance |
Loder Close |
MA3424 |
JH |
Lenham |
New bell mouth access and footway |
Under review |
Heath Road |
MA3326 |
JH |
Linton |
New Access |
Works now adopted. |
Gleamingwood Drive |
MA003441/MA003440 |
SP |
Lordswood |
New Access and development |
Going through Technical Approval. Scheme on Hold |
Bicknor Green, Gore Court Road |
MA003053 |
AD |
Maidstone |
Change of road priorities and widening / upgrading |
In Maintenance |
Oakapple Lane/ Hermitage Lane |
MA003046 |
AD |
Maidstone |
New bellmouth junction and associated ancillary works incl new bus stop, for new development |
Works now Adopted. |
St Saviours Road, Maidstone |
MA003136 |
AD |
Maidstone |
Changes to layout for Morrisons Junction |
Agreement signed |
Buffkyn Way / Sutton Road |
MA003218 |
AD |
Maidstone |
Signalisation of the junction |
Approved – not signed |
Springwood Road Maidstone |
MA003438 |
AP |
Maidstone |
Stopping up of existing access and provision of new through footway |
In Maintenance |
531 Tonbridge Road |
MA003045 |
CV |
Maidstone |
Service layby for new retail unit |
Adoption imminent |
Wallis Avenue Phase 3, Parkwood |
MA003085 |
CV |
Maidstone |
Redevelopment of car park & shops opp. Longshaw Rd |
Works in maintenance |
Maidstone East Station |
MA3447 |
CV |
Maidstone |
Footway upgrade (& private parking improvement) |
Works in maintenance |
Royal Engineers Rd/Mill Lane |
MA3312 |
JH |
Maidstone |
Access to New Development |
Revised scheme under Technical Review after comments from local Members awaiting design feedback on comments to date. |
Medway Street |
MA3326 |
JH |
Maidstone |
Subway Flood Protection Works |
Awaiting input from scheme promotor – no information rec’d |
Howard Drive |
MA003303 |
SP |
Maidstone |
Junction works to facilitate Bus Gateway entrance to Croudace site |
Awaiting TRO for yellow lines. |
Hermitage Lane, (opp. Maidstone Hospital) |
MA003060 |
SP |
Maidstone |
New Traffic signal junction |
In Maintenance. Remedials being completed |
Union Street, Car Park |
MA003319 |
SP |
Maidstone |
New Access to development and footway works |
Awaiting wall to be removed due to visibility issue. Then will be adopted. |
Castle Dene, Maidstone |
MA003352 |
SP |
Maidstone |
New Access and further footway work and repairs |
Works completed |
Perryfield Street |
MA3411 |
SP |
Maidstone |
New footpath/access to new homes |
Works complete now in maintenance. |
Oakapple Phase 2A, Hermitage Lane |
MA003444 |
SP |
Maidstone |
Development adjoining existing development |
Going through Technical Approval |
Langley Park Farm |
MA003130 |
AD |
Maidstone / Langley |
New Roundabout and associated works for entrance to Countryside Estate |
Works complete |
MAP Depot, Goudhurst Road |
MA003012 |
CV |
Marden |
New bellmouth junction and footway |
Final Remedials due, (mini-SID provided to Parish for monitoring traffic flows) |
The Parsonage, Goudhurst Road |
MA003066 MA003067 |
CV |
Marden |
New access and associated upgrade works |
In maintenance |
Napoleon Drive and Plain Road |
MA003079 |
CV |
Marden |
New access on each road for new housing development |
Adoption imminent |
Albion Road, Marden |
MA003132 |
SP |
Marden |
New Access & development |
Works in maintenance |
Fishers Farm (West), Headcorn Road (Bovis) (off-site works) |
MA3037/1 |
AP |
Staplehurst |
Pedestrian crossovers on Headcorn Road/ |
Works completed, remedial works completed, stage 3 road safety audit response required before first certificate issue |
Oliver Road Staplehurst |
MA003019 |
CV |
Staplehurst |
Ped crossing to Marden Road, junction markings and bus boarders |
Near end of maintenance – documentation to be received |
Hen and Duckhurst Farm, Marden Rd |
MA003109 |
CV |
Staplehurst |
New Roundabout for development access |
In Maintenance |
High Street Staplehurst |
MA3446 |
CV |
Staplehurst |
2 x new bus stop upgrades (kerbs and markings) |
Works in maintenance |
Fishers Farm (East) Headcorn Road (Redrow) |
MA3106 |
SP |
Staplehurst |
Realignment and new access at Headcorn Road/Pile Lane junction |
Works still ongoing
|
Sainsbury’s new site Station Rd |
MA3387 |
SP |
Staplehurst |
Roundabout and new access |
Works now adopted. |
Pristling Lane |
MA3415 |
SP |
Staplehurst |
Widened access & Ditch works |
Awaiting defect completion prior to adoption. |
Sapphire Kennels Headcorn Road |
MA3407 |
AP |
Sutton Valence |
Access to new development and 40mph extension |
Awaiting remedial works to be implemented. |
Valdene Industrial Estate |
MA003054 |
CV |
Sutton Valence |
Upgrade of existing bellmouth and extension to f/w |
At final remedials stage prior to adoption |
The Oaks, Maidstone Road |
MA003078 |
CV |
Sutton Valence |
Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing. |
In maintenance |
Appleacres, Maidstone Road |
MA003152 |
SP |
Sutton Valence |
Access to new development and footway works |
Works Adopted. |
Warmlake Nurseries |
MA003443 |
SP |
Sutton Valence |
New access to small development |
Works in maintenance |
Farleigh Hill Tovil (opp. KCC waste site) |
MA3413 |
AP |
Tovil |
New access opp Burial Ground Ln KCC Recycling centre |
Site now under new ownership. Full S278 agreement being prepared by Legal |
Tovil Green Lane |
MA003095 |
CV |
Tovil |
New Footway and crossing point to side of site |
In maintenance |
Mount Ave/Blunden Lane |
MA3180 |
CV |
Yalding |
New accesses at site entrance |
Adoption imminent |
Vicarage Road |
MA003121 |
SP/JH |
Yalding |
New access to development and speed restraints on existing Highway |
Under review |
Yalding Business Park, Hampstead Lane |
MA003450 |
JH |
Yalding |
New accesses into business park |
Under review – stopping up order underway. |
Old Ham Lane |
MA003448 |
CV |
Lenham |
C/W widening and footway for new development |
Technical review in progress |