Contact your Parish Council


Decision details

Property Acquisition for 1000 homes programme

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The Council has an ambitious housebuilding program that is funded via the Council’s adopted Capital Program. This housebuilding program encompasses homes for: Affordable Housing (AH), Private Rented Sector Housing (PRS) and on occasion a limited amount of exposure to Market Sale (MS) Housing too. The development strategy for this program was approved by the Policy & Resources Committee in January 2022, and the proposals within this report are consistent with delivering that strategy.

Decision:

RESOLVED: That

 

1.  The financial returns for the proposed acquisition as shown in Exempt Appendix 3 to the report, be approved.

 

2.  The Director of Finance, Resources and Business Improvement be granted delegated authority to:

 

a)  Negotiate terms for the purchase of the proposed acquisition for the sum as shown in the Exempt Appendix 3 of this report.

 

b)  Procure and enter into all such deeds, agreements, contracts, and documents which may be required to facilitate the purchase of the site, and the subsequent redevelopment works required to deliver the scheme referred to in this report. Including (but not limited to) any related appointments such as a suitably qualified consultants and Contractor.

 

c)  Subject to satisfactory conclusion of all due diligence to negotiate and finalise and complete all legal formalities, deeds and agreements which may be required to facilitate the purchase.

 

3.  The Head of Mid Kent Legal Services be authorised to appoint the Solicitors required to negotiate and complete the necessary contract documentation, deeds and agreements associated with the purchase and construction works on the terms as agreed by the Director of Finance, Recourses & Business Improvement.

 

4.  Post completion of the procurement process, to appoint a contractor for the works cost detailed in the financial summary Exempt Appendix 3 to the report. If in the event tenders for the works cost are in excess of the agreed sum, then officers will return to the Executive to seek further approval prior to the development itself commencing.

 

Reasons for the decision:

When appraising new housing development opportunities, the New

Business and housing Development Team consider proposals

against the following standard risk headings: -

 

• Site location and ownership.

• Town Planning Status.

• Schedule of accommodation, tenure mix and parking ratio.

• Quality – Maidstone Building for Life 12.

• Housing Management.

• Deal structure.

• Contractor procurement.

• Financial viability.

• Delivery program.

• Professional team.

 

The opportunity proposed in this report is fully appraised against

these standard risk headings in the exempt Appendix 1 to the report.

Alternative options considered:

Option 1: That the purchase of the proposed acquisition is not approved. The Council would however lose an excellent opportunity to purchase a site with full planning permission with access to good transport links and amenities to add to its affordable housing stock. It will assist towards much needed affordable accommodation in the Borough and contribute towards the Council’s 1,000 Affordable Homes delivery target.

 

Option 2: That the purchase of the proposed acquisition is approved on the agreed terms and procures the professional consultants. Following the procurement exercise for a contractor officers will come back to committee to seek approval for the appointment of the preferred contractor to help deliver the scheme. This site when built would assist with affordable housing provision, contributing towards delivering the 1,000 affordable homes target.

Reason Key: Expenditure > £250,000;

Wards Affected: North Ward;

Other reasons / organisations consulted

Notification to ward members. Briefing to executive and Lead Member for PAC

Contact: Philip Morris Email: philipmorris@maidstone.gov.uk.

Publication date: 18/04/2023

Date of decision: 18/04/2023

Decided: 18/04/2023 - Executive

Effective from: 28/04/2023

Accompanying Documents: