Contact your Parish Council
Decision details
Budget Strategy 2011/12 Onwards
Decision Maker: Cabinet.
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To agree a draft Council Tax and Budget
Strategy for 2011/12 onwards
Decision:
1. That a provisional spending level of £20.21 million for 2011/12 and a Council Tax freeze in line with the Government’s proposal be agreed.
2. That working balances be set at £2.3million at this time and to monitor this level as part of the standard budget monitoring during 2011/12.
3. That the draft medium term financial strategy as set out in Appendix G of the report of Management Team and its connection to the draft strategic plan be noted.
4. That the results of the budget consultation be noted.
5. That the changes to the budget pressures as set out below be agreed:-
|
2011/12 £000 |
2012/13 £000 |
2013/14 £000 |
2014/15 £000 |
Reduced Income from Regeneration |
|
|
-230 |
+230 |
Pension Fund Valuation |
-500 |
-500 |
-500 |
|
Concessionary Fares |
-150 |
|
|
|
Refuse & Recycling |
|
|
-300 |
|
Local Development Framework |
-400 |
|
|
|
Homelessness Strategy |
-70 |
|
|
|
Cost of Borrowing |
-150 |
|
+150 |
|
Loss of Income |
-50 |
|
|
|
Growth Provision |
+100 |
|
|
|
|
-1,120 |
-500 |
-880 |
+230 |
6. That the revised strategic projection, as set out in Appendix A of the report of Management Team be agreed.
7. That payment by annual instalment of the Council’s contribution to fund the pension fund deficit for the three years 2011/12 to 2013/14 as set out below be agreed:-
|
£,000 |
2011/12 |
1,206 |
2012/13 |
1,260 |
2013/14 |
1,325 |
8. That the savings identified in Appendix B of the report of Management Team be agreed.
9. That the proposed additional use of balances, as detailed in Appendix D of the report of Management Team, be agreed.
10. That the provisional Capital Programme, as detailed in Appendix C of the report of Management Team, be agreed.
Reasons for the decision:
At the July meeting, Cabinet considered the initial budget projection for 2011/12 onwards, based on the financial information available at that time, and agreed the following:
a)
That for planning purposes, the Council Tax increase
for 2011/12 and future years be set at 2.5% to inform the strategic
projections provided in Appendix F of the report of Management
Team;
b)
That the scenario to be adopted is the “most
likely” as outlined in the strategic projections in the
report of Management Team;
c)
That the extent of the Capital Programme for 2011/12
onwards be noted;
d) That the timetable for the Budget Strategy 2011/12 be noted.
The initial financial projection was selected by Cabinet as the most likely of three scenarios. The key assumptions from that scenario were:
a) An inflation rate of 2% per annum over the period, but dropping to 1% in years 2 and 3;
b) Anticipated grant reductions of £3.2m or 32% over four years. This was assumed to be evenly spread over the four years;
c) Additional resources would be required for a number of initiatives including the Local Development Framework, the homelessness strategy and the leisure centre;
d) A continuation of the annual increase in the national concessionary fares scheme, to facilitate transitional costs of the transfer of the scheme to KCC;
e) The use of all available capital receipts to fund the capital programme, reducing the level of investment income;
f) A need to borrow up to £2.0m to finance capital expenditure, creating a need for revenue resources to service the debt;
g) That the current policy to maintain a minimum balance of 10% of net revenue spend is maintained;
h) That future Council Tax increases be equivalent to the 2010/11 increase for the purpose of developing the strategy;
i)
That a 0.5% increase in the Council Tax Base be
assumed;
j) That the triennial review of the pension fund would produce a valuation that required an increase in the Council’s contribution equivalent to £0.5m per annum for three years.
A number of risks were identified as part of the initial projection as follows:
a) The uncertainty surrounding the spending review and its effect upon the formula grant assumptions made in the strategy;
b) The potential non-delivery of the capital receipts from the sale of assets assumed during the programme period, leading to the possible need for additional borrowing to finance the capital programme.
c) The potential future loss of Homes and Community Agency (HCA) grant aid to the Council’s capital programme following the intensive investment programme since 2008/09.
d) The continuing risk of an income shortfall on the revenue budget due to the recession.
Following these decisions a further report to agree the approach to budget consultation for 2010/11, was approved by Cabinet.
Economic Background
The
recession has had a significant impact upon the Council over the
past three years. This impact has led
to major changes in the Council’s financial
strategy. This is most noticeable in
its effect upon the income levels achieved by Council
services.
By the
end of 2010/11 the Council will have reduced budgeted expectations
of income generation by £2.1m per annum. The mid year projection suggests that this reduced
target will be achieved. The projection
was previously reported to Cabinet as part of the second
quarter’s budget monitoring report.
The
economic indicators for October 2010, the most up to date
indicators available at the time of writing, give a mixed message
on the strength of the economy.
a) Consumer Price Index (CPI) inflation rose to 3.2% (3.1% previous month)
b) Retail Price Index (RPI) inflation fell to 4.5% (4.6% previous month)
c) In the quarter to September 2010, the economy grew by 0.8% (1.2% in previous quarter)
d)
Unemployment fell to 2.45m or 7.7% of the
economically active population in September 2010 (down 17,000 from
a year earlier)
The CPI reported above is more than 1% above the Government’s 2% target. To place the current position into context with the recession the chart below plots CPI and RPI as annual percentage increases (or decreases) over the period since April 2008. As can be seen, the indices have fluctuated but have recently remained above 2% for a significant period.
At the time of writing the Office of Budget Responsibility predicts current year growth as 1.8%, then 2.1% and 2.6% in the following two years, 2011 and 2012. The CBI, however, see these figures as optimistic.
The
economy will be affected by the Government’s actions as part
of the spending review announced in October 2010. The expectation nationally is that borrowing will
be held just below £150 billion for the year. In future years public sector spending reductions
will remove £103 billion of this annual borrowing.
The
intended result of the combined effect of economic growth and a
reduced annual deficit is to stabilise the economy and enable a
rise out of the recession. The major
risk to government strategy is that reduced public sector spending
may adversely affect economic growth. Economists’ views on
this matter are very mixed at this time.
Review of 2010/11 to date
Cabinet
has received two quarterly monitoring reports for 2010/11 in August
and October 2010. It is clear from
these reports that management action has ensured the current
year’s budget is resilient, enabling a stable base for future
financial pressures to be addressed by the Council.
The mid
year variance was reported to Cabinet in October 2010 as a
favourable variance of £0.75m. A
number of significant issues were identified that, in the main,
related to time limited issues.
Examples included an underspend on concessionary fares which will
be the responsibility of the County Council from April 2011 and a
business rates rebate for the Tonbridge Road property that has been
demolished and will incur no future costs to the point of
sale.
The
Capital Programme, as approved by Council in March 2010, has been
revised during this financial year by Cabinet’s approval of
slippage to future years. The current
programme was last considered by Cabinet in November 2010 and
expected expenditure in year has reduced to £8.2m. In
addition the resources required to finance this reduced level of
capital expenditure in 2010/11 are available to the
Council. This is primarily due to the
fact that the proceeds from the sale of Armstrong Road Depot have
been received.
This
slippage does not affect the overall programme for 2010/11 to
2012/13 as the majority of change relates to the re-profiling of
scheme costs between years. This means prudential borrowing or
additional capital receipts of £2.4m will still be required
by 2012/13 based on current funding assumptions. This issue is
considered further in section 1.9 which discusses the future
Capital Programme.
Revenue
balances continue to achieve the Council’s policy of a
minimum of 10% of net revenue spend after provisional allocation
and use as approved by Council in March 2010. One significant variance to the use approved by
Council in March 2010 is that there is no longer a requirement to
repay VAT on exempt supplies, estimated at £0.2m as a
consequence of the major works at the crematorium in
2009/10. This balance is now an
additional uncommitted resource.
Along with the quarterly budget monitoring reports Cabinet has received quarterly performance reports during the year. At September 2010 the Council’s performance showed that 82% of KPIs and LPIs are forecast to end the year at or above target. This is slightly down on the achievement reported to September 2009.
Review
of Strategic Projection
In July
2010 Cabinet considered three scenarios for the strategic
projection and approved their favoured option. This scenario has been used to complete all work
since that time and all consultation.
Attached at Appendix A to the report of Management Team is a
revised strategic projection. Since July a number of factors have
changed. The major change is that,
following the announcement of the four year spending review, both
the medium term financial strategy and the strategic plan have a
minimum four year outlook. Specific
changes since July 2010 that affect the four year period are given
in the table below:
|
2011/12 £000 |
2012/13 £000 |
2013/14 £000 |
2014/15 £000 |
Reduced Income from Regeneration |
|
|
-230 |
+230 |
Pension Fund Valuation |
-500 |
-500 |
-500 |
|
Concessionary Fares |
-150 |
|
|
|
Refuse & Recycling |
|
|
-300 |
|
Local Development Framework |
-400 |
|
|
|
Homelessness Strategy |
-70 |
|
|
|
Cost of Borrowing |
-150 |
|
+150 |
|
Loss of Income |
-50 |
|
|
|
Growth Provision |
+100 |
|
|
|
|
-1,120 |
-500 |
-880 |
+230 |
Further
detail of each category of change is given below:-
a)
Reduced income from regeneration provided for the
consequences of work on regeneration from a more focused use of
some Council resources. Current plans
no longer require the single year investment of
£0.23m.
b)
Pension fund valuation provided for the expected
increase in employer contributions to the pension fund. A successful year by the pension fund, maintained
by Kent County Council, together with recent changes nationally,
such as connecting future increases to CPI inflation and the move
to increase the state pension age, have meant that the value of the
fund in 2010 is similar to the value in 2007. The consequence of this is that the Council does
not need to increase its contribution towards the
deficit.
c)
Concessionary fares provided for transitional and
residual costs of the transfer of the service to Kent County
Council in 2011/12. Likely residual
costs have been identified and funded from within current resources
and transitional costs, if they occur, can be covered by the
unallocated resources within balances.
d)
Refuse and recycling provided for a future increase
in cost at the time of the new contract. At this time it is considered that the new
contract in 2013 will not require growth, due to the potential for
planned services changes.
e)
Local Development Framework (LDF) work was
previously funded from balances. These balances were transferred to
finance the Council’s work on the Kent International Gateway.
The previous strategic financial projection assumed £0.4m
growth for the LDF, but this is a one-off funding requirement. This
has been removed and replaced with a proposal for a £0.4m
allocation from balances.
f)
Homelessness strategy provided replacement funding
for a grant that was expected to cease in 2011/12. The recent finance settlement announcement that
this grant will not only continue but be enhanced means there is no
requirement to provide alternative funding.
g)
The cost of borrowing provided for the possibility
that up to £2m of prudential borrowing would be required in
2010/11 and again in 2011/12. Although
possibility of prudential borrowing being required to complete the
full capital programme still exists, sale of assets and slippage in
the programme during 2010/11 mean sufficient funding should be
available for this year. This does not
remove the possible future need and the pressure has been moved to
2012/13 and 2013/14 rather than removed.
h) Loss of income provided for non-specific consequences of the recession on various income generating services. The Council has taken action each year of the recession to reduce its reliance on income in areas affected by the recession. As of 31 March 2011 the expected income from fees and charges has been reduced by over £2m since 31 March 2008. The budget monitoring for 2010/11 shows income generation to be matching this reduced target. This suggests the Council has matched expectation to demand and can reduce its assumptions relating to future losses.
i)
The growth provision has been amended to ensure that
the one-off costs of achieving organisational change can be
funded.
Available Resources
The
Council Tax
As part
of its initial consideration of the MTFS in July 2010, Cabinet
agreed to use a 2.5% increase in Council Tax plus a 0.5% increase
in the tax base as working assumptions.
At the
meeting of the General Purposes Group on 9 December 2010, a tax
base of 60,303.1 was set for 2011/12. This represents a 0.9%
increase over the tax base set for 2010/11. The working assumption
agreed by Cabinet in July 2010 was an increase of 0.5% which is
equivalent to a tax base of 60,064.0.
The revised tax base of 60,303.1 results in an increase of
£53,000 in the base Council Tax position for 2011/12 before
consideration of any percentage increase.
As part
of the spending review 2010 the Government announced, in October,
details of its council tax freeze proposal. The proposal is a single year tax freeze (or
reduction). Compensation is available through a central government
grant equivalent to a 2.5% increase in council tax. This
compensation is for four years only and cash limited to the value
of the first year’s grant.
The strategic projection at Appendix A to the report of Management Team uses the tax base agreed by General Purposes Group and assumes a Council Tax freeze in 2011/12 with the receipt of the cash and time limited grant detailed above. When compared to a model with an actual 2.5% increase in Council Tax in 2011/12, the Council’s resources will reduce by £62k which is the loss of that percentage increase over the four years of the grant. In addition, 2015/16 will require additional savings of £380k as a consequence of the loss of grant, a total loss of Council tax funding of £442k.
The
Government is proposing legislation under the localism bill to
ensure Council Tax increases cannot be excessive without approval
through a local referendum. Until that
time it is expected that the government will use capping powers to
limit increases. These matters combined mean that it is unlikely
that a later increase in Council Tax could compensate for the loss
of grant in 2015/16.
Revenue Support Grant
Following the Local Government Finance settlement announcement
on 13 December 2010 there have been significant changes to the
profile of the Revenue Support Grant.
Nationally, the announcement’s headline issues are:
a) A two year settlement with the second year remaining provisional.
b) The announcement of plans to adopt a new system of distributing local government funding from 2013; consultation to commence in early 2011.
c) A total reduction in grant from £28bn to £24.9bn in 2011/12 which is equivalent to a 12.1% real terms reduction.
d) An arrangement for the “tailored” distribution of grants that have previously been ring fenced.
e) An arrangement for transitional grant for authorities where “revenue spending power” reduces by more than 8.9%.
f) Changes to damping provisions including the categorisation of authorities into four groups, dependent upon the ratio of grant to Council Tax.
The Council’s specific settlement issues are:
a) A grant of £6.45m in 2011/12 and a provisional grant of £5.72m in 2012/13.
b) A reduction in grant for concessionary fares of £1.77m coupled with a loss of £0.47m from the Department for Transport.
c) A number of minor adjustments relating to other changes in responsibility, valued at a reduction of £56,495.
d) Damping at the level of the highest floor group creating a final reduction of -16.58% from the adjusted 2010/11 grant.
The two
year settlement can be projected to cover four years, based on the
spending review data announced by central government in October
2010. The grant reduction in each year,
compared to the prediction made in the July 2010 report to Cabinet
is given below:-
|
Reduction in Grant July 2010 £000 |
Reduction in Grant Settlement £000 |
2011/12 |
-800 |
-1,282 |
2012/13 |
-800 |
-734 |
2013/14 |
-800 |
-69 |
2014/15 |
-800 |
-429 |
|
-3,200 |
-2,514 |
There
are two major differences between the initial projection and the
settlement figures:
a) The initial
projection assumed an even spread of grant reductions however the
government has “front-loaded” reductions for local
government in order to protect other public services.
b) The initial projection assumed the reduction to the Council’s grant would be made before the transfer out of the £1.8m concessionary fares sum. The settlement reductions have occurred after the transfer, which has reduced the loss of grant to £0.7m.
Although the tailored distribution of grants previously ring fenced has not directly affected this Council, such changes will have affected Kent County Council. The potential negative impact of the County Council’s funding reduction will need to be considered and actions identified to mitigate the impact.
Budget requirement and Spending Level
Following the detailed analysis of the level of Council Tax and the settlement notification, it is possible to identify a provisional spending level or budget requirement for each year of the spending review as follows:
|
2011/12 £,000 |
2012/13 £000 |
2013/14 £000 |
2014/15 £000 |
Council Tax Collectable |
13,411 |
13,813 |
14,227 |
14,654 |
Council Tax Adjustment |
15 |
- |
- |
- |
Council Tax Grant |
335 |
335 |
335 |
335 |
Revenue Support Grant |
6,449 |
5,715 |
5,646 |
5,217 |
Budget Requirement |
20,210 |
19,863 |
20,208 |
20,206 |
Savings
Target & Efficiency
The
strategic projection approved by Cabinet in July 2010 required a
total savings target of £7.4m over four years to
2014/15. The revised strategic
projection at Appendix A to the report of Management Team takes
account of all the changes detailed earlier in this report and
identifies a four year savings target of £4.3m. Due to the profiling of the reductions this target
is not evenly spread across the four years. The table below compares annual figures from July
2010 with the current projection.
|
July 2010 £,000 |
Current £,000 |
2011/12 |
2,771 |
1,878 |
2012/13 |
1,647 |
1,068 |
2013/14 |
2,168 |
608 |
2014/15 |
844 |
773 |
TOTAL |
7,430 |
4,327 |
Following the July 2010 Cabinet meeting a series of proposals have been developed that will achieve the targeted savings for each of the first three years with a contribution to the fourth year. Attached at Appendix B to the report of Management Team is a summary, by portfolio, of the value of the savings proposals in each year.
If the
budget is set in March 2011 with a Council Tax freeze and the
associated four year grant there will be an increase in the budget
pressure in year five. This is set out above in paragraph 1.8.1.4
and the consequence is included in the financial projection at
Appendix A to the report of Management Team.At this time it would
be prudent for the Council to recognise this additional pressure
and to identify actions to mitigate the additional pressure in
advance of the end of the four year grant.
At this
stage the proposals are being developed and, where they include
organisational change in 2011/12, staff consultation has begun or
will begin in January 2011. At this
time proposals are not fully developed to provide specific
details.
One
major proposal included in the summary at Appendix B to the report
of Management Team relates to the method of contribution to the
back funding element of the pension fund. In the past the Council has contributed through a
percentage on-cost to the contribution by employees. This could continue for the next three years at a
rate based upon predicted employment levels over that
period. Alternatively a lump sum
payment can be agreed for each of the three years as
follows:-
|
£,000 |
2011/12 |
1,206 |
2012/13 |
1,260 |
2013/14 |
1,325 |
The
summary given at Appendix B to the report of Management Team
assumes that the option to pay an annual lump sum as detailed in
the table above is agreed. This option
produces an annual saving of £0.2m to the Council whilst
removing the risk to the fund value from setting the on-cost
percentage too low or too high.
Each of the proposals that make up the four year savings target has been risk rated and a monitoring process has been developed within the Council’s performance management system “Covalent” in order to provide Cabinet and Management Team with detailed progress reports.
Capital Programme
The current Capital Programme 2010/11 to 2012/13 was approved by Council in March 2010 and subsequently amended by Cabinet in response to monitoring reports provided during the year.
As
stated above a number of approved changes have occurred during the
year. In addition, in preparation for this report, the schemes in
the current programme have been reviewed to identify where budgets
could be reduced. During this time no new schemes have been
proposed for inclusion and a number of current schemes have been
identified as requiring a reduced budget. The changes identified
through this review have been made and a proposed programme for the
period 2010/11 to 2014/15 is attached at Appendix C to the report
of Management Team.
The
2010/11 programme is fully funded from resources currently held or
from grant commitments. The 2011/12
programme can be fully funded from the currently approved asset
sales with a small balance being carried forward to 2012/13.
Resources to complete the 2012/13 programme do not currently meet
need. A balance of £2.4m is required from further asset
sales, grants and contributions or prudential borrowing. This level
of prudential borrowing is within the limit approved by Council in
March 2010.
The extension to the programme for future years, by the continuation of ongoing schemes at their 2012/13 levels, would require identification of additional resources or further borrowing of £1.8m per annum. It should be noted that borrowing at this level would mean exceeding the current prudential limit, would place increased pressure on the strategic projection and require the approval of Council.
In accordance with the current MTFS policy, inclusion of a scheme in the programme does not confirm the ability to commence the scheme or permission to incur expenditure unless resources to finance the scheme exist and have been prioritised to that scheme. Cabinet will be required to consider the commencement of individual schemes as future resources become available to the Council.
Further opportunities for funding will continue to be explored and identified. It should be noted that a final recommendation on the Capital Programme 2011/12 to 2014/15 is not required until the February 2011 cabinet meeting. The draft programme is however required for the consultation with Corporate Services Overview and Scrutiny Committee.
Review
of Balances
The
MTFS has, in the past, envisaged that the Council will maintain a
minimum level of revenue balances of £2m and that Cabinet
will set working balances at 10% of net revenue
expenditure.
Based on the current strategic projection this would set a working balance close to or below the minimum level set by Council. It may be appropriate this year to consider the level of both. The table below shows the value of 10% of net revenue expenditure for the four years of the spending review period. It also considers the percentage level of working balance that Cabinet’s current level of £2.3m would represent of the revised net revenue expenditure (NRE):
Year |
Net Revenue Expenditure £,000 |
10% Balance £,000 |
Current balance as % NRE |
2011/12 |
20,210 |
2,021 |
11.4 |
2012/13 |
19,863 |
1,986 |
11.6 |
2013/14 |
20,208 |
2,021 |
11.4 |
2014/15 |
20,202 |
2,020 |
11.4 |
At this
time there is a significant level of unallocated balances available
to the Council; there also remains significant uncertainty in terms
of the economic environment. It is therefore recommended that the
Council takes a prudent approach and maintains a minimum working
balance at a cash value of £2.3m and reviews the position
regularly taking into account strategic risk and the level of
unallocated balances.
Cabinet have recently considered a report on the work of the Carbon Reduction Working Party. This group is developing proposals that will enable the Council to achieve reductions in carbon emissions and achieve long term reductions in energy costs. In order to achieve the necessary changes some schemes require up front investment. It is proposed to allocate resources from within balances to provide funding for an invest to save arrangement to achieve these carbon reduction proposals. At this time costs totalling £55,000 have been identified which all have longer term payback periods than the current invest to save payback period of 5 years. A detailed carbon reduction plan and programme of work is scheduled for presentation to Cabinet in March 2011.
In response to the Government’s localism agenda it is proposed to develop the Council’s role as an enabler of localism related activity through a fund of £0.1m that could be set aside from balances. The fund could enable the borough’s community based groups and residents to deliver the Council’s priorities and achieve efficiencies and improved outcomes. The purpose and use of the fund would be developed through discussion and engagement with Councillors, businesses and voluntary and community groups, which is planned to commence in January 2011, and could include facilitating the establishment of new community based initiatives and social enterprises through direct support and levering funds from other sources including the government and national lottery.
Attached at Appendix D to the report of Management Team is a
summary of the current level of balances including a projection to
31 March 2011. Also shown are the proposals for the use of balances
outlined elsewhere in this report. As at 31 March 2011 balances are
predicted to be £5.8m of which £2.3m is held as minimum
working balance, a further £0.9m is unallocated general
balances and £2m is available from the VAT reclaim. After
incorporation of all uses proposed in this report balances will
total £4.8m and including the VAT reclaim £1.9m of this
will remain unallocated.
Budget Consultation
In August 2010, Cabinet considered a report on options for budget consultation for 2011/12 onwards. Cabinet approved a consultation in line with the programme set out below:
A minimum twelve week consultation to:
· Raise awareness of the budget situation, the statutory services the Council provides, and the savings options considered by Cabinet;
· To find out which discretionary services matter most to local people;
· To encourage comments on the service options considered by Cabinet; and
· To ask for other suggestions for savings.
A road show, website pages and a consultation leaflet was designed with the theme of “MY Council, what matters to ME” to focus the consultation on the issues that matter most to Maidstone people.
The main activity at each road show was designed to encourage respondents to indicate which discretionary areas of service matter most to them. Respondents were given a choice of eight discretionary services and asked to indicate up to four which matter most to them.
The eight discretionary areas were:
· Community Services – community safety, CCTV and community development
· Democratic Representation – civic occasions and events
· Environmental Protection – health promotion and toilets
· Transport Services – bus shelters and rural bus services
· Recreation & Sport – Maidstone Leisure Centre, sports and youth activities
· Open spaces, parks and recreation grounds
· Grants to voluntary and charitable organisations
· Tourism, visitor information centre, town centre management, conference venue marketing and Christmas light
Officers and Members of the Cabinet took the road show to 12 public events at locations such as Tesco Grove Green supermarket, Maidstone Leisure Centre, Staplehurst Library, Yalding Farmers Market and Maidstone Gateway. The events were a mix of rural and urban locations. In all 1,829 respondents completed the discretionary services activity.
In addition to this activity, the road show was taken to the four neighbourhood forums, the Citizens Advice Bureau (CAB) meeting, the Older Person’s Forum and the Voluntary and Community Sector focus group. In addition, at the rural conference, where a briefing on the budget strategy was given, the leaflet was handed to all attendees.
Council staff were consulted through the Staff Forum and at a series of listening days. A briefing was given at the rural conference and delegates were given the explanatory leaflet.
The notes of the neighbourhood forum meetings are set out in Appendix E to the report of Management Team.
More than 50 people completed the consultation leaflet or web form. A full list of the comments is set out in Appendix F to the report of Management Team.
These comments show that there is a consensus of opinion on a number of issues including the need to maximise efficiency through savings on consumables such as paper, envelopes and postage, using buying consortiums and reducing office and buildings costs such as heating and lighting and opening hours.
There is support, particularly at the Neighbourhood Forums, for more partnerships working and outsourcing work and a suggestion that powers and services could be devolved to parish councils to save money.
A number of people have written about concurrent functions with comments about fairness.
Several consultees encouraged the Council to consider raising more income from services. Suggestions include planning, parking, waste collection, planning enforcement, charging entry at the museum, and charging for bus passes.
Democratic services were mentioned at the Neighbourhood Forums and by other consultees. Suggestions included saving money on elections costs, reducing the number of councillors and going to four yearly elections. This area was ranked the least important discretionary area by consultees.
Grants were the second least important area for consultees but there was an acknowledgement in the comments of the part played by the voluntary sector now and in future.
Capital spending was mentioned by some with suggestions that the
programme should be rescheduled or the High Street Regeneration
programme or Museum East Wing project cut or reduced.
Officer and Councillor remuneration and expenses were mentioned by several consultees suggesting savings in salaries and pension costs.
There were several comments in support of the cabinet’s initial thoughts on savings and efficiencies. These included “Cabinet’s proposals to return people to work are a real step in the right direction”. “Focus on central services is the right focus”. “Savings should be focused around lean processes of shared services and procurement”.
The comments and opinions are detailed in the appendices however the key issues that require further review are detailed below:
· Areas requiring more consideration:
o Joint Working, including procurement;
o Central service reductions;
o Staff and Member direct cost reductions.
· New areas for focus:
o Office Accommodation;
o Cost of democracy; and
o Income generation.
· Areas of conflicting public opinion:
o Reductions in grant aid;
o Extent of outsourcing; and
o Extent of localism.
In addition to these issues, the table highlights the result of the survey into discretionary services that matter most to the residents of the borough. This table is reproduced in the order of importance according to the result:
Service Area |
Description |
% of Vote |
Open Spaces |
Parks & open spaces |
20 |
Community Services |
Community Safety, Community Development & CCTV |
19 |
Transport Services |
Support for socially desirable buses & Bus shelter maintenance |
16 |
Recreation & Sport |
Leisure Centre, youth & sport provision |
13 |
Environmental Protection |
Public conveniences and health promotion |
12 |
Visitor Economy |
Tourism and visitor information centre |
10 |
Grants |
Grant aid |
9 |
Democratic Representation |
Town Hall and civic events |
1 |
This result is represented below as a pie chart for ease of comparison:
It should be noted that the number of issues identified through the consultation for further consideration is low. The vast majority of opinion and commentary supports the actions already taken by Cabinet or recommended in this report.
Additional areas for consideration include further efficiency in the use of office space, the cost of democracy and the opportunities for enhancing income generation. Further work on these issues will be undertaken to identify opportunities for savings.
Links to the Strategic Plan
The review of the Strategic Plan in preparation for 2011/12 onwards is presented to Cabinet elsewhere on this agenda. This draft Strategic Plan provides greater simplicity and focus on the priorities of the Council.
The review has been progressed jointly by the Policy & Performance Team and Corporate Finance. The purpose of the co-ordinated approach was to ensure appropriate links between the Strategic Plan and the MTFS.
An updated draft of the MTFS is attached at Appendix G to the report of Management Team and is, in essence, the formal statement of the objectives outlined in this budget strategy report. The final document will be published as an integral part of the budget and will therefore be directly linked to the final approved versions of the strategic projection at Appendix A, the savings proposals at Appendix B and the capital programme at Appendix C of the report of Management Team.
The MTFS has been enhanced by the inclusion of a full risk analysis and it is intended that, along with consultation with Corporate Services Overview and Scrutiny, this risk analysis will form the focus of additional consultation this year with the Audit Committee in relation to its impact on strategic risk and governance. The risk analysis is separately attached at Appendix G to the report of Management Team.
Alternative options considered:
A number of alternative assumptions are included in the report and appendices for Cabinet’s consideration.
The production of the budget for 2011/12 is an element of the statutory process of calculating the Council Tax for 2011/12. In addition the completed and approved document is required to be robust and adequate under the Local Government Act 2003. A statement to this effect must be given by the Chief Financial Officer. On this basis the actions outlined in the report of Management Team were considered.
Reason Key: Expenditure > £250,000;
Wards Affected: (All Wards);
Details of the Committee: Consultation from the Department for Communities and Local Government on Revenue Grant Settlement 2011/12
Representations should be made by: 23 November 2010
Other reasons / organisations consulted
Internal and External
(External - options as agreed by Cabinet in August 2010)
Consultees
Management Team, Heads of Service and
Members
Contact: Email: paulriley@maidstone.gov.uk.
Report author: Paul Riley
Publication date: 23/12/2010
Date of decision: 22/12/2010
Decided: 22/12/2010 - Cabinet.
Effective from: 06/01/2011
Accompanying Documents: