Issue details

Purchase & Repair, Temporary Accommodation Acquisition (phase 6)

There is £32m allocated within the capital programme agreed by Council on 22 February 2023 for a further (6th) phase of investment in purchase and repair properties for use as Temporary Accommodation to help alleviate homelessness. This paper sets out the number and type of accommodation to be acquired.

 

The £32m budget for Temporary Accommodation is profiled over three years in the programme, agreed by Council last week - £12 million in 2023/24, £12 million in 2024/25 and £8 million in 2025/26.   There is also an underspend within the capital programme for Temporary Accommodation of £3.8m, which equals a budget for 2023/24 of £15.8m.

 

The report also details the Local Authority Housing Fund (LAHF) that makes £2.5m of grant funding available to the Council by the Department for Levelling Up, Housing, and Communities that can be used to supplement this overall program.

 

 

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: (All Wards);

Notice of proposed decision first published: 10/02/2023

Decision due: 22 Mar 2023 by Executive

Lead director: Director of Regeneration and Place

Department: Economic Development

Contact: Alison Elliott Email: alisonelliott@maidstone.gov.uk.