MAIDSTONE BOROUGH COUNCIL
RECORD OF DECISION OF THE Policy and Resources Committee
|
Decision Made: |
21 October 2015 |
MAIDSTONE LEISURE CENTRE SOLAR MICROGENERATION
Issue for Decision
To install a solar microgeneration system at Maidstone Leisure Centre.
Decision Made
1)
That the installation of a solar microgeneration system (solar panels)
at Maidstone Leisure Centre be approved;
2)
That a budget of up to £270,000 is made available for the delivery of
the project;
3)
That Officers be instructed to obtain the necessary permissions and
licences to implement the recommendations, including registration for Feed in
Tariff; sale or export of electricity; and appropriate agreements with the
District Network Operator; and to assign those permissions and licences as
appropriate; and
4) That delegated authority be given to the Head of Commercial and Economic Development, in consultation with the Head of Legal Partnership, to enter into and conclude negotiations with Maidstone Leisure Trust and Serco regarding their purchase of the electricity generated.
Should you wish to refer this decision to Council, please submit a Decision Referral Form, signed by five Councillors, to the Head of Finance and Resources by: 30 October 2015 |