To: Maidstone Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 16th October 2019
Subject: Highway Forward Works Programme – 2019/20 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
- Casualty Reduction Measures
- Externally funded schemes
- Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent
Susan Laporte Maidstone District Manager
Alan Casson Strategic Asset Manager
Earl Bourner Drainage & Structures Asset Manager
Sue Kinsella Street Light Asset Manager
Toby Butler Traffic & Network Solutions Asset Manager
Jamie Hare Development Agreements Manager
Jamie Watson Schemes Programme Manager
Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Mr Byron Lovell |
|||
Road Name |
Parish |
Extent of Works |
Current Status |
A274 Maidstone Road |
Langley |
From the B2163 Upper Street to Warmlake Road |
Programmed 21st November 2019 |
A20 King Street |
Maidstone |
Watt Tyler Way and Wyke Manor Road |
Programmed 2nd December 2019 |
A229 Linton Road |
Loose |
From Lancet Lane to Rosemount Close |
Programmed 30th November 2019 |
Forstal Road |
Aylesford |
From bridge deck over motorway to Beddow Way |
Programmed 8th November 2019 |
A229 Sheals Crescent |
Maidstone |
From Loose Road (through Hayle Road, College Road, Mill Street) to Bishops Way |
Programmed 14th November 2019 |
A229 Palace Avenue |
Maidstone |
Mill Street and A249 Mote Road |
Programmed 27th November 2019 |
A229 Upper Stone Street |
Maidstone |
A249 Mote Road to Old Tovil Road |
Programmed 11th December 2019 |
A20/A26 Rocky Hill |
Maidstone |
Maidstone Gyratory to Terrace Road |
To be programmed 2020 |
Footway Improvement - Contact Officer Mr Neil Tree |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Mote Road |
Maidstone |
From the junction with Square Hill Road to Willow Way (Northern side) (Footway Reconstruction) |
Completed
|
Winifred Road |
Bearsted |
Entire length (Footway Reconstruction). |
Completed
|
Royston Road |
Bearsted |
Entire length (Footway Reconstruction). |
Completed
|
Rosemary Road |
Bearsted |
Entire length (Footway Reconstruction). |
Completed
|
Trenton Close |
Allington |
Entire length (Footway Reconstruction). |
Designed and to be programmed.
|
Beverley Road |
Barming |
Entire length (Footway Protection) |
Completed
|
Egremont Road |
Bearsted |
Entire length (Footway Protection) |
Completed
|
Roseholme |
Maidstone |
Entire length (Footway Protection) |
Completed
|
Wesley Close |
Barming |
Entire length (Footway Protection) |
Completed
|
Broomshaw Road
|
Barming |
Entire length (Footway Protection) |
Completed
|
Surface Treatments – Contact Officer Mr Jonathan Dean |
|||
Micro Surfacing |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Glebe Lane
|
Maidstone (Barming) |
Tonbridge Road to Farleigh Lane
|
Completed |
Gatland Lane
|
Maidstone (Barming) |
Farleigh Lane to Fant Lane
|
Completed |
Faversham Road
|
Lenham
|
Whole Road
|
Completed
|
West Street
|
Lenham |
Faversham Road to Flint Lane (West Street) Lenham
|
Completed |
Marden Road
|
Marden |
Battle Lane to "Mountain Farmhouse"
|
Completed |
Maidstone Road
|
Marden |
"Hartridge" to 150m north of j/w Milebush Lane (Kiln Farm)
|
Completed |
Headcorn Road
|
Platts Heath / Lenham |
Chain Gate Road to Station Approach, Lenham
|
Completed |
Headcorn Road
|
Sandway |
Headcorn Road to Sandway Road
|
Completed |
Sandway Road
|
Sandway |
Headcorn Road to "Little Biggen"
|
Completed |
Gallants Lane
|
East Farleigh |
Lower Road to Heath Road
|
Completed |
Hunton Road
|
Marden |
River Beult bridge (Clapper Green) to "Reed Court Cottages"
|
Completed |
Old Tree Lane/Cliff Hill
|
Boughton Monchelsea |
From The Quarries to Combe Bank House - |
To Be Programmed |
Sandway Road
|
Platts Heath |
Around "Sandway Triangle"
|
Completed |
Kenward Road
|
Yalding |
Hunt Street to Yalding Hill
|
Completed |
Bow Road |
Wateringbury |
Corner after bridge to Hunt Street |
Completed |
Smith’s Hill
|
Yalding |
To Be Confirmed
|
Completed |
Surface Treatments – Contact Officer Mr Jonathan Dean |
|||
Surface Dressing |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
A20 Ashford Road |
Hollingbourne |
Near j/w Old Mill Road to j/w Roundwell
|
Programmed for August 2019 |
A20 Ashford Road
|
Hollingbourne |
Old Ashford Road to Northdown Close
|
Programmed for August 2019 |
Charlton Lane
|
East Sutton |
From Chartway Street to Church Lane
|
Programmed for August 2019 |
Appendix B - Drainage
Drainage Repairs & Improvements - Contact Officer Earl Bourner |
|||
Parish |
Description of Works |
Current Status |
|
Green Lane |
Chart Sutton |
Repair the culvert and edge of road/ verge/ ditch. |
Work is in progress. Hopefully completed by 1/9/19. |
Tufa Close |
Walderslade |
Relocation of soakaway |
Completed |
Smith’s Hill |
West Farleigh |
Investigation works |
Cleansing works complete further investigation required at Shingle Barn Lane. |
The Broadway |
Maidstone |
Surface water system surcharging |
It has been identified that the issue is due to the Southern Water system. Southern Water will now be responsible for this site |
Dray Corner Road |
Headcorn |
Further investigation works required |
Awaiting start date |
Dunn Street |
Bredhurst |
Repair broken pipe |
Awaiting start date |
Fisher Street |
Maidstone |
Reports of broken pipes and repairs to be carried out |
Awaiting start date |
Lower Road |
East Farleigh |
Repair broken pipes |
Awaiting start date |
West Street |
Hunton |
Repair broken pipes |
Awaiting start date |
The Street |
Boxley |
To carry out a drainage CCTV survey and cleanse to locate outfall of system and check for defects. |
Originally programmed for 18/8/19, abandoned due to TM issues on the day. New programme date is Sunday 8/9/19. |
Sheals Crescent |
Maidstone |
To carry out drainage CCTV investigation. |
Awaiting start date |
Appendix C – Street Lighting
Column replacement testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer Sue Kinsella
|
||||
Road Name |
Column |
Parish |
Description of Works |
Status |
Warwick Place |
KWAI502 |
Maidstone |
Lit Sign Replacement |
Completion end September 2019 |
Warwick Place |
KWAI501 |
Maidstone |
Lit Sign replacement |
Completion end September 2019 |
Brishing Lane |
KBFE010 |
Maidstone |
Replacement of Street Light |
Completion by December 2019 |
High Street |
KHDO053 |
Staplehurst |
Replacement of Street Light |
Completed |
Milton Street |
KMCW503 |
Maidstone |
Lit Sign replacement |
Completed |
Whitmore Street |
KWCR501 |
Maidstone |
Lit Sign replacement |
Completion by December 2019 |
Station Road |
KSFA029 |
Staplehurst |
Replacement of Street Light |
Completion by December 2019 |
Castle Dene |
KCAO002 |
Maidstone |
Replacement of Street Light |
Completed |
Impton Lane |
KIAC001 |
Boxley |
Replacement of Street Light |
Completed |
Maynards |
KMBY002 |
Marden |
Replacement of Street Light |
Completed |
Egerton Road |
KEAQ003 |
Ringlestone |
Replacement of Street Light |
Completion by December 2019 |
King Street |
KKAM009 |
Maidstone |
Replacement of Street Light |
Completion by December 2019 |
Woodlands |
KXEF107 |
Boxley |
Replacement of Street Light |
Completed |
Howard Drive |
KHFD002 |
Allington |
Replacement of Street Light |
Completion by March 2020
|
Howard Drive |
KHFD016 |
Allington |
Replacement of Street Light |
Completion by March 2020 |
Trevor Drive |
KTCI016 |
Allington |
Replacement of Street Light |
Completion by March 2020 |
ERNEST DRIVE |
KEBA004 |
ALLINGTON |
Replacement of Street Light |
Completion by March 2020 |
LEONARD CLOSE |
KLBG004 |
ALLINGTON |
Replacement of Street Light |
Completion by March 2020 |
BRACKEN HILL |
KBIC008 |
BOXLEY |
Replacement of Street Light |
Completion by March 2020 |
OLD CHATHAM ROAD |
KOAI001 |
BOXLEY |
Replacement of Street Light |
Completion by March 2020 |
BELLGROVE COURT |
KBIF001 |
BOXLEY |
Replacement of Street Light |
Completion by March 2020 |
BRACKEN HILL |
KBIC008 |
BOXLEY |
Replacement of Street Light |
Completion by March 2020 |
WILDFELL CLOSE |
KWFE016 |
BOXLEY |
Replacement of Street Light |
Completion by March 2020 |
VICTORIA STREET |
KVAJ003 |
BRIDGE |
Replacement of Street Light |
Completion by March 2020 |
CORNWALLIS ROAD |
KCFT005 |
BRIDGE |
Replacement of Street Light |
Completion by March 2020 |
TRAPHAM ROAD |
KTCF006 |
BRIDGE |
Replacement of Street Light |
Completion by March 2020 |
PALMAR ROAD |
KPAF007 |
BRIDGE |
Replacement of Street Light |
Completion by March 2020 |
PEMBROKE ROAD |
KPAW014 |
COXHEATH & HUNTON |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL005 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL006 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL007 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL009 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL021 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
DERINGWOOD DRIVE |
KDAL022 |
DOWNSWOOD & OTHAM |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU017 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU022 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU031 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU036 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU046 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU050 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU051 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TONBRIDGE ROAD |
KTBU055 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
MANSFIELD WALK |
KMFW202 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
WHITMORE STREET |
KWCR005 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
DOVER STREET |
KDBB004 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
GLEBE LANE |
KGAS006 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
TERMINUS ROAD |
KTAD009 |
FANT |
Replacement of Street Light |
Completion by March 2020 |
OAKWOOD COURT |
KOAD003 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
HEATH ROAD |
KHCH005 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
QUEENS ROAD |
KQAG004 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
QUEENS ROAD |
KQAG019 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
CHARLBURY CLOSE |
KCBH001 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
STANFORD DRIVE |
KSEI001 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
MILL WALK |
KMCT002 |
HEATH |
Replacement of Street Light |
Completion by March 2020 |
ST PETERS BRIDGE |
KSCE001 |
HIGH STREET |
Replacement of Street Light |
Completion by March 2020 |
COLLEGE ROAD |
KCFC005 |
HIGH STREET |
Replacement of Street Light |
Completion by March 2020 |
LOWER ROAD |
KLCU003 |
HIGH STREET |
Replacement of Street Light |
Completion by March 2020 |
UPPER ROAD |
KUBR010 |
HIGH STREET |
Replacement of Street Light |
Completion by March 2020 |
KING STREET |
KKAM021 |
HIGH STREET |
Replacement of Street Light |
Completion by March 2020 |
LINTON ROAD |
KLBS011 |
LOOSE |
Replacement of Street Light |
Completion by March 2020 |
LOOSE ROAD |
KLCQ094 |
MAIDSTONE |
Replacement of Street Light |
Completion by March 2020 |
EGERTON ROAD |
KEAQ001 |
NORTH |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG001 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG010 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG011 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG012 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG037 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG041 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
BICKNOR ROAD |
KBCG042 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
ASHFORD ROAD |
KABO063 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
ASHFORD ROAD |
KABO064 |
NORTH DOWNS |
Replacement of Street Light |
Completion by March 2020 |
WALLIS AVENUE |
KWAD016 |
PARK WOOD |
Replacement of Street Light |
Completion by March 2020 |
BELL ROAD |
KBBS005 |
PARK WOOD |
Replacement of Street Light |
Completion by March 2020 |
GREENFIELDS |
KGCA002 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
MARION CRESCENT |
KMBK002 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
MARION CRESCENT |
KMBK004 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
MARION CRESCENT |
KMBK009 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
CRANBORNE AVENUE |
KCGL014 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
LONGFIELD PLACE |
KLCN001 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
HOLTYE CRESCENT |
KHER002 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
HOLTYE CRESCENT |
KHER006 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
HOLTYE CRESCENT |
KHER007 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
RUTLAND WAY |
KRCC002 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
DENTON CLOSE |
KDAJ003 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
THE SPINNEY |
KTDS001 |
SHEPWAY NORTH |
Replacement of Street Light |
Completion by March 2020 |
SUTTON ROAD |
KSGF006 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
SUTTON ROAD |
KSGF007 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
SUTTON ROAD |
KSGF039 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
KENNINGTON CLOSE |
KKAD005 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
CAMBRIDGE CRESCENT |
KCAC016 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
GRAVENEY ROAD |
KGBL003 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
GRAVENEY ROAD |
KGBL009 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
CRANBROOK CLOSE |
KCGM001 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
ESSEX ROAD |
KEBB006 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
WESTMARSH CLOSE |
KWBT003 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
IFIELD CLOSE |
KIAB004 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
WINGHAM CLOSE |
KWDI005 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
FREEMAN WAY |
KFCN002 |
SHEPWAY SOUTH |
Replacement of Street Light |
Completion by March 2020 |
NORRINGTON ROAD |
KNAR007 |
SOUTH |
Replacement of Street Light |
Completion by March 2020 |
CRANBROOK ROAD |
KCGN068 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
CRANBROOK ROAD |
KCGN073 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
STATION ROAD |
KSFA018 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
STATION ROAD |
KSFA021 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
STATION ROAD |
KSFA024 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
HIGH STREET |
KHDO057 |
STAPLEHURST |
Replacement of Street Light |
Completion by March 2020 |
Appendix D – Transportation and Safety Schemes
The Schemes Planning & Delivery team is implementing schemes within the Maidstone district, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status correct as of 23/9/19.
Casualty Reduction Measures
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
Great Danes Roundabout |
Hollingbourne |
Signing and road marking improvements |
Jennie Watson |
Works complete |
Mill Street/Palace Avenue |
Maidstone |
Lining refreshing |
Jennie Watson |
Works partially completed in October 2018 – Yellow box markings completed – Contractor to return to refresh white lining
|
A20 Ashford Road, Lenham |
Lenham |
Scheme to make changes to junction |
Jennie Watson |
Works are substantially complete – Minor snagging items to be completed |
Springfield Roundabout - A229 Royal Engineers Road |
Maidstone |
Signing and road marking improvements |
Paul Leary
|
Following detailed analysis, tree clearance only to be carried out |
St Faiths Street/ Fairmeadow |
Maidstone |
Signing and road marking improvements |
Jennie Watson |
Works passed to contractor – Programmed for 8 October (weather dependent) |
A229 Lower Stone Street/ Knightrider Street |
Maidstone |
Introduction of red-light camera monitoring survey |
Jennie Watson |
ITS Team arranging red light camera monitoring survey over 7 days – Date to be confirmed |
Boxley Road/Sandling Lane, roundabout |
Maidstone |
Signing and road marking improvements |
Jennie Watson |
Works complete 6 September 2019 |
A20 Ashford Road/M20 Slip |
Hollingbourne |
Signing and road marking improvements |
Jennie Watson |
At design stage – Scheme to be progressed this financial year |
Integrated Transport Schemes – all other LTP funded non-casualty reduction schemes
Location |
Parish |
Description of Works |
Lead officer |
Current Status |
East Farleigh Bridge |
East Farleigh |
Upgrade of signing and lining for bridge width restriction |
Paul Leary |
Works completed May 2019. Minor snagging items to be carried out |
Mote Park Cycleway (Phase 1) |
Maidstone |
Upgrade of cycle route |
Paul Leary |
Works completed May 2019. Minor snagging items to be carried out. |
Mote Park Cycleway (Phase 2) |
Maidstone |
Signing and road marking improvements between Chancery Lane and Maidstone House |
Paul Leary |
Works handed over to contractor – Anticipated completion late December 2019 |
Local Growth Fund
Local Growth Fund programme update for the Maidstone Borough.
The Department for Transport (DfT) added Ł100m to the Local Growth Fund (LGF) pot in order to fund Local Sustainable Transport Fund Style schemes. KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion. The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.
The schemes aim to:
· improve access to employment and services
· reduce the need to travel by the private car
· enhance pedestrian, cycle and public transport facilities
· improve sustainable transport connections
The following schemes have been submitted as part of the successful Kent Thameside LSTF this financial year.
Scheme |
Status |
MAIDSTONE EAST STATION IMPROVEMENTS |
The newly appointed Asbestos and demolition specialist Rhodar are now on site and have begun demolition of the public house. This is currently running to programme, under asbestos controlled conditions, with most of the roof now removed. The whole ground floor has been cleared of all soft items, such as the bar, doors, partitions, etc, and the basement has been cleared in preparation for backfilling the area to provide protection to the tunnel during the demolition works. The expected completion of the overall programme will be clearer once the demolition of the pub is further completed but is currently expected to be in May/June 2020. Any public enquiries are being dealt with by Network Rail. Additional KSIP funding has now been confirmed to progress further highway improvements and walking and cycling connections to the station. |
Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers for sites Jamie Hare, Aaron Divall, Steven Noad, Sarah Parris, Andy Padgham, Steve A Stickels |
Scheme Name |
File Ref. |
Officer |
Parish |
Description of Works |
Current Status |
BP Tudor Service Station, London Road |
MA003072 |
CV |
Allington |
Alterations to existing access |
Pedestrian crossing point and additional signage still to do. |
Bell Farm, North Street |
MA003098 |
SN |
Barming |
New accesses to split sites, shared surface and new crossing point |
Agreement signed; highway works largely completed. |
Cross Keys |
MA003100 |
JH |
Bearsted |
New access, crossing point and parking area |
Agreement signed |
Barty Farm, Roundwell |
MA003278 |
AD |
Bearsted |
New Bellmouth and Lining works |
Agreement Signed |
Bicknor Road |
MA003256 |
AP |
Bicknor |
Formation of hard surfaced passing places |
Awaiting technical approval |
Heath Road/Church Street |
MA003111 |
SP |
Boughton Monchelsea |
New access, footway works, yellow lines and crossing upgrade |
High Friction surfacing re-laid. Inspection due for start of maintenance. |
Hubbards Lane |
MA003084 |
CV |
Boughton Monchelsea |
Two accesses to minor developments |
Works completed on both accesses, pedestrian crossing point to add |
Lyewood Farm, Green Lane |
MA3247 MA3248 |
AP |
Boughton Monchelsea |
New housing development and access |
Awaiting technical approval |
Goya Development, St Michaels Close, Aylesford |
MA003123 |
SP |
Boxley |
New access and footway work to new commercial properties |
Works complete except for new gulley. |
Maidstone Studios, New Cut Road |
MA003110 |
SP |
Boxley |
Zebra crossing and pedestrian crossing points |
Defective High Friction surfacing requires further attention |
St Michaels Close, Aylesford |
MA003103 |
CV |
Boxley |
Waitrose car park, new access |
Final remedials due |
Forstal Lane |
MA003141 |
SP |
Coxheath |
Widening of road and new footpath with access to new development |
Agreement Signed Awaiting works start date |
Heath Road (North side) |
MA003063 |
CV |
Coxheath |
New access and Footway work |
Works completed and in maintenance |
Land north of Heath Road Phase 2 |
MA3257 |
SP |
Coxheath |
Access to new development |
Agreement signed Awaiting works start date |
Linden Farm, Stockett Lane |
MA003107 |
SP |
Coxheath |
Access to new development and footway link to community hall |
Access & footway completed further 2 accesses to restore to footway near completion of development. |
Gatland House, Gatland Lane |
MA003081 |
CV |
Fant ward |
Parking restrictions, signage, road markings and tactile crossings for new school |
Works completed, Remedials to do |
Bell Farm, Ashford Road |
MA003094 |
CV |
Harrietsham |
Realignment of Church Road to form new access onto A20. New footway along A20 |
Works completed and in maintenance. |
Mayfield Nursery, Ashford Road |
MA003135 |
SP |
Harrietsham |
New access and alterations to existing Highway to adjoin upcoming Scheme Works |
Works ongoing on site currently in conjunction with Harrietsham improvement scheme |
Forge Meadows |
MA3253 |
AP |
Headcorn |
Access to 2 new properties and vehicle crossovers to existing properties |
Awaiting technical approval |
Grigg Lane & Wheeler Street |
MA3250 |
SP |
Headcorn |
Access Gibbs Farm development; zebra crossing on Wheeler St |
Technical approval granted, agreement in progress |
Grigg Lane, Lenham Road,
|
MA003050 |
CV |
Headcorn |
Access onto Grigg Lane and Lenham Road. Footway on Grigg Lane |
New accesses Grigg Lane and Lenham Road in place, New footway Grigg Lane completed |
Kings Road/Millbank |
MA3262 |
AP |
Headcorn |
Signalised crossroads (linked to Ulcombe Road MA3150) |
Technical approval granted, Agreement in progress |
Lenham Road (North side) |
MA003062 |
CV |
Headcorn |
New Footway to site and extends speed limit boundary |
Works completed and in Maintenance |
Lenham Road (South side) |
MA003057 |
CV |
Headcorn |
New footway |
Agreement prepared |
Oak Lane and Wheeler Street |
MA003048 |
CV |
Headcorn |
New footway plus junction improvements |
Works completed and in maintenance |
Ulcombe Road |
MA003150 |
SP |
Headcorn |
Access to new development |
Agreement signed |
Wheeler Street, Headcorn |
MA003137 |
SP |
Headcorn |
2 new accesses - off Wheeler Street and Kingsland Grove |
Awaiting works start date |
Eyhorne Street |
MA3198 |
AP |
Hollingbourne |
New access to development |
Awaiting technical approval |
Ledian Farm |
MA003086 |
JH |
Leeds |
New access to development at Ledian Farm |
Now Adopted |
8 Faversham Road |
MA003032 |
CV |
Lenham |
New access |
In maintenance; streetlight to replace |
Old Ashford Road |
MA003018 |
CV |
Lenham |
New footway plus access |
Approaching end of maintenance, bus stop location to amend. |
The Paddocks, Ashford Road (Grove House, Old Ashford Road) |
MA3114 |
CV |
Lenham |
New access, traffic island, speed reduction to 50mph & f/way link to Faversham Rd |
Footway built, remaining works to complete Oct 19 |
Westwood Park, Ham Lane |
MA003305 |
AP |
Lenham |
Main and emergency accesses to new housing development |
Awaiting technical approval |
Royal Engineers Rd/Mill Lane |
MA3312 |
JH |
Maidstone |
Access to New Development |
Under Technical Review |
531 Tonbridge Road |
MA003045 |
CV |
Maidstone |
Service layby for new retail unit |
In maintenance |
Bicknor Green, Gore Court Road |
MA003053 |
AD |
Maidstone |
Change of road priorities and widening / upgrading |
Works mostly complete |
Hartnup Street |
MA003138 |
SP |
Maidstone |
New Access |
Works complete now in maintenance. |
Heath Road, Coxheath |
MA003134 |
SP |
Maidstone |
New access and new footway |
Agreement signed awaiting start date |
Hermitage Lane, (opp. Maidstone Hospital) |
MA003060 |
JH |
Maidstone |
New Traffic signal junction |
Near to adoption |
Hermitage Lane/ Howard Drive |
MA003070 |
AD |
Maidstone |
New access for development (opposite the quarry entrance) |
Works complete |
Howard Drive |
MA003303 |
AD |
Maidstone |
Junction works to facilitate Bus Gateway entrance to Croudace site |
Agreement Signed |
Maidstone School of Science, New Cut Road |
MA003197 |
SP |
Maidstone |
New access to School and New roundabout and alterations to Highway |
Agreement signed Awaiting road space and start date |
McDonalds drive-through, Hart Street |
MA003013 |
CV |
Maidstone |
New access, improvements to Hart Street. |
Approaching the end of maintenance - remedial works due |
Oakapple Lane/ Hermitage Lane |
MA003046 |
AD |
Maidstone |
New bellmouth junction and associated ancillary works for new development including new bus stop |
Works Complete – in maintenance |
Royal Engineers Road |
MA003127 |
SP |
Maidstone |
New footpaths to development |
Awaiting funds and works start date |
The Poplars, Ashford Road |
MA3254 |
AP |
Maidstone |
Access to new development |
Approval granted; Agreement due for signing |
Wallis Avenue Phase 3, Parkwood |
MA003085 |
CV |
Maidstone |
Some stopping up of highway and redevelopment of old carpark and shops area opp. Longshaw Road |
Works complete |
Week St/Gabriel’s Hill |
MA003120 |
SP |
Maidstone |
Town Centre Public Realm improvements |
Completed and inspected for maintenance |
Heath Road |
MA3326 |
JH |
Linton |
New Access |
Under Technical review |
Albion Road, Marden |
MA003132 |
SP |
Marden |
New Access and development |
S278 works part completed. |
Goudhurst Road, Church Green (Plain Road development) |
MA3118 |
CV |
Marden |
Install Zebra crossing near rail station. |
Completed – in Maintenance |
Goudhurst Road/West End (Plain Road Development) |
MA3118 |
CV |
Marden |
Refurbish Zebra crossing outside school and Bus Borders to add by Library stops. |
Work completed and in maintenance |
Howland Road |
MA003088
|
SN |
Marden |
New development access |
Agreement signed; highway works largely complete |
MAP Depot, Goudhurst Road |
MA003012 |
CV |
Marden |
New bellmouth junction and footway |
Works in maintenance. Remedial works near completed and interactive speed sign awaiting installation |
Napoleon Drive and Plain Road |
MA003079 |
CV |
Marden |
New access on each road for new housing development |
Works Completed |
The Parsonage, Goudhurst Road |
MA003066 MA003067 |
CV |
Marden |
New access and associated upgrade works |
Access substantially completed, village gateway to be agreed |
Bell Lane |
MA003030 |
CV |
Staplehurst |
Upgrade of existing access for new development |
Due for adoption. |
Fishers Farm (East) Headcorn Road (Redrow) |
MA3106 |
SP |
Staplehurst |
Realignment and new access at Headcorn Road/Pile Lane junction |
Realignment complete and Pile Lane open |
Fishers Farm (West), Headcorn Road (Bovis) |
MA3037 |
SP |
Staplehurst |
New access onto Headcorn Road |
Works commenced on both S278 and S38 |
Hen and Duckhurst Farm, Marden Road |
MA003109 |
CV |
Staplehurst |
New Roundabout for development access |
Works on highway almost completed. HFS delayed by utility works. |
Oliver Road Staplehurst |
MA003019 |
CV |
Staplehurst |
Ped crossing to Marden Road, junction markings and bus boarders |
Works completed |
Woodford Park |
MA003099 |
SP |
Staplehurst |
New access for 9 dwellings |
Works completed and on to maintenance. |
Appleacres, Maidstone Road |
MA003152 |
SP |
Sutton Valence |
Access to new development and footway works |
Technical Approval given awaiting Legal Agreement |
The Oaks, Maidstone Road |
MA003078 |
CV |
Sutton Valence |
Upgrade existing Vehicle crossing access to Bellmouth with tactile crossing. |
Works complete |
Valdene Industrial Estate |
MA003054 |
CV |
Sutton Valence |
Upgrade of existing bellmouth and extension to f/w |
Footway works carried out; access works due Oct 2019. |
Cripple Street Maidstone |
MA003093 |
CV |
Tovil |
New access to development, widening and footway works |
Due for adoption – remedials due |
Site opposite cottages 129-147 Dean Street/Farleigh Hill |
MA003007 |
CV |
Tovil |
New access speed limit relocation, new footway and bus stop provision |
Works completed and in maintenance |
Tovil Green Lane |
MA003095 |
CV |
Tovil |
New Footway and crossing point to side of site |
Remedials completed – in maintenance |
Hampstead Lane |
MA3101 |
SP |
Yalding |
Relocate access to new development at old depot adj. station. Minor footway works |
Into maintenance period |
Vicarage Road |
MA003121 |
SP |
Yalding |
New access to development and speed restraints on existing Highway |
Technical Approval Granted |
Bentletts Yard, Claygate Road, Laddingford |
MA003357 |
SP |
Laddingford |
New footway and replaced surface to existing access |
Awaiting Technical approval although some works already carried out |
Old Ashford Road, Adj Groom Way |
MA003356 |
SP |
Lenham |
New access and footway |
Awaiting Technical Approval |
|
Developer Funded Works (Section 106 Works)
|
|||
File Ref. |
Road Name |
Parish |
Description of Works |
Current Status |
18/19-S106-MA-486 |
A20 Ashford Road |
Harrietsham |
Village improvement works: 2 phase approach. Phase 1 which consisted of narrowing the carriageway, widening footways to allow shared footway/cycleway, altering the controlled crossing, provision of central islands and changes to the speed limits and associated signing and lining. Phase 2 will include relocating street lighting columns to better suit the new road layout and to extend the lighting to include all the 30mph limit. Resurfacing of the carriageway to hide the old white lining and then new lining to the recently installed layout. . |
Phase 1 Works completed in June 2019. KCC investigating how phase 2 can be brought forward. Kent County Council are to collect the remaining S106 contribution from Bellway Homes now less the indexation.
Please see separate report. |
18/19-S106-MA-819 |
Linton Crossroads |
Linton/Loose |
Junction/signal upgrade |
Finalising designs however the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. It is hoped that a public consultation can be undertaken around October/November with implementation in 2020 pending all land, environmental and funding issues being resolved.
|
Appendix F – Bridge Works
Bridge Works – Contact Officer Earl Bourner |
|||
Road Name |
Parish |
Description of Works |
Current Status |
No planned works |
Appendix G – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler
|
||
Location |
Description of Works |
Current Status |
A26 Tonbridge Road near Milton Street, Maidstone |
Refurbishment of traffic signal-controlled crossing |
Programmed August 2019 |
B2162 Twyford Bridge, Yalding |
Refurbishment of traffic signals |
To be Programmed |
A229 Fairmeadow/ Medway Street |
Refurbishment of traffic signal-controlled junction |
Programmed September 2019 |
A20 London Road near Broadway |
Replacement of signal controller |
Programmed September 2019 |
A20 Tonbridge Road near Station Approach |
Replacement of signal controller |
Programmed September 2019 |
Appendix H - Combined Member Grant programme update
Member Highway Fund programme update for the Maidstone district
The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are
· in design
· at consultation stage
· about to be programmed
· Recently completed on site.
The list is up to date as of 23/9/19
The details given below are for highway projects only. This report does not detail
· Contributions Members have made to other groups such as parish councils
· highway studies
· traffic/ non-motorised user surveys funded by Members.
More information on the schemes listed below can be found by contacting the District Manager for the Maidstone district, Susan Laporte.
Dan Daley and Rob Bird
Details of Scheme |
Status |
18/19-CMG-MA-722 – Queens Avenue, Maidstone
Construction of build out for part one way |
Works Complete
|
Details of Scheme |
Status |
19/20-CMG-MA-923 – Church Hill, Boughton Monchelsea
Traffic Regulation Order application for speed limit reduction |
TRO sealed - Complete |
Paulina Stockell
Details of Scheme |
Status |
19/20-CMG-MA-947 – Darman Lane, Laddingford, Yalding
Traffic Regulation Order application for speed limit reduction |
TRO sealed - Complete |
1.1 Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contacts: Kirstie Williams/ Susan Laporte 03000 418181