MAIDSTONE BOROUGH COUNCIL
COBTREE MANOR ESTATE CHARITY COMMITTEE
8 JUNE 2011
REPORT OF THE REPORT OF THE COBTREE OFFICER
Report Prepared by: Brian Latimer – Cobtree Officer
1. GARDEN COTTAGE – FINAL ACCOUNT
1.1 Issue for Decision
1.1.1 To consider and, if appropriate, note the final costs arising from the underpinning works at Garden Cottage.
1.2
RECOMMENDED
1.2.1
It
is recommended that Members:
(i) Note the final
account for the underpinning works at Garden Cottage; and
(ii) Note the additional
costs which were required to be met from the contract contingency sum.
1.3
Reasons
for Recommendation
1.3.1
At
the meeting of the Committee on 9 March 2011 Members considered an exempt
report on matters relating to the underpinning works required to Garden Cottage.
It was resolved that the proposed action to be taken by officers in respect of
a claim for additional costs relating to a revised method of piling be
endorsed, and that a number of additional costs arising from the works be
noted.
1.3.2
At
that stage it was anticipated that the final cost of the project would be
contained within the original estimate of £81,200.
1.3.3
Members
will recall that the original budget was made up of the contract sum of
£73,180, which included a contingency element of £10,000. Further costs
included external consultancy fees (£6,805) and removal/storage costs (£1,167).
1.3.4
It
was reported that since the commencement of the works a number of items had
arisen which required Members attention and these have been dealt with in
accordance with Members instructions.
1.3.5
The
works have now been completed and a final account submitted. A comparison with
the original budgetary provision is set out below for Members information:
Item |
Original Estimate
|
Final Account |
+/- |
Contract Sum |
63,180 |
63,180 |
0 |
Contingency |
10,000 |
7,515 |
-2,485 |
Consultant Fee |
6,805 |
6,745 |
-60 |
Storage and Removal |
1,166 |
3,454 |
2,288 |
|
|
|
|
|
81,151 |
82,120 |
-257 |
1.3.6
The
additional works which required use of the contingency sum were as follows:
Removal of asbestos |
2328 |
Scaffolding to chimney |
525 |
Replacement Heating Pump |
294 |
Scaffolding for re-pointing |
746 |
Alterations to front step |
197 |
Internal investigation to damp wall |
373 |
Replace flue terminal |
192 |
Repair kitchen window |
120 |
Additional making good perimeter walls |
1176 |
Additional making good for decorating |
363 |
Replace ceilings |
625 |
Lining of walls for decorating |
385 |
Replace kitchen mixer tap |
115 |
Gulley Repairs |
75 |
|
7,515 |
1.3.7
The
major area of discrepancy between the original estimate and the final account relates
to removal and storage costs; this was due to confusion in interpreting the
original quotation and a longer period of storage than anticipated.
1.3.8
It
is recommended that Members note the content of the final account.
1.3.9
Members
should further note that the above figures do not include any reference to the
claimed increase in costs for the revised method of piling; a claim which the
Council continues to dismiss as invalid.
1.4 Alternative Actions and Why Not Recommended
1.4.1 The alternative course of action would be to dispute the additional costs met from the contingency sum, but this is not recommended as the required works were necessary and only identified as the contract progressed.
1.5 Impact on Charity Objectives
1.5.1 The above works have no direct impact on the objects of the charity; however, the Charity does have an obligation to maintain its assets in good tenantable order.
1.6 Risk Management
1.6.1 The only remaining risk relates to the disputed claim for additional costs associated with the revised method of piling. It is considered very unlikely that the contractor could substantiate the legitimacy of his claim.
1.7
Other
Implications
Financial |
X |
|
|
Staffing |
|
|
|
Legal |
X |
|
|
Social Inclusion |
|
|
|
Considerations for Disabled Persons |
|
|
|
Environmental/Sustainable Development |
|
|
|
Community Safety |
|
|
|
Human Rights Act |
|
|
|
Procurement |
|
1.7.1
The
additional costs have been contained within the contingency sum.
1.7.2
There
is no obligation on the Charity to meet the additional cost for the revised
piling system.
Background Documents
NO REPORT WILL BE ACCEPTED WITHOUT THIS BOX BEING COMPLETED
Is this a Key Decision? Yes No
If yes, when did it appear in the Forward Plan? _______________________
ü
Reason for Urgency
|