Enc. 4 for Quarter 3 Key Performance Indicator Report

 

 

PI AP CTC 001 Average wait time for calls into the contact centre


 

 

 

 

 

 

 

 

Code

Title

Due Date

Progress Bar

Assigned To

Latest Note

Note Date

PI AP CTC 01.01

Implement an Automated Switchboard

31-Jan-2013

Sandra Marchant

Q3 Update - Implementation of the system is still in progress however no live date is scheduled yet. IT resource is still required to assist with the implementation of this.

23-Jan-2013

PI AP CTC 01.02

Contact Centre resources

30-Jun-2013

Louise Wenzel

Q3 Update - Two Volunteers have been interviewed and one of them has been offered a 6-month placement in the Contact Centre on a voluntary basis. Initially this will just be for 2 days a week and the new Volunteer is due to start on Tuesday 29 January 2013.

23-Jan-2013

PI AP CTC 01.03

Cross training of Contact Centre CSAs

31-Dec-2013

Louise Wenzel

Q3 Update - A lot more cross training of Customer Service Advisors in the Contact Centre has been undertaken during the last quarter. More staff are now able to handle more services however the cross training still continues.

23-Jan-2013

PI AP CTC 01.04

Maintain a fully resourced Contact Centre

31-Dec-2013

Sandra Marchant

Q3 Update - The Contact Centre did not have any vacant posts at the end of year however one member of the team was on long term sick leave. This has resulted in a resignation with effect from January 2013 leaving a vacant post. In addition, 3 members of the team will commence maternity leave in March, July and August so this will have an impact on the team. An Assessment Centre is being arranged for 6 March 2013 and an advert for all vacancies will go out soon if permission is granted.

23-Jan-2013

PI AP CTC 01.05

Channel Shift

31-Dec-2013

Sandra Marchant

Q3 Update - A beta (test) version of the new website will be issued to all staff for their comments by the end of January followed by gaining feedback from customer focus groups. The new website will be live sometime in April. New self-serve forms will be developed after this. A self-serve process for booking a bulky collection will be available from sometime in January.

23-Jan-2013


 

 

PI AP CTC 002 Percentage of visitors to the Gateway responded to within 20 minutes


 

 

 

 

 

 

 

 

Code

Title

Due Date

Progress Bar

Assigned To

Latest Note

Note Date

PI AP CTC 02.01

Gateway resources

31-Jan-2013

Laura Mason

Q3 Update - The Gateway continues to use one of the Apprentices and will do so until March 2013.

23-Jan-2013

PI AP CTC 02.02

Maintain a fully resourced Gateway team

31-Dec-2013

Sandra Marchant

Q3 Update - The Gateway currently has 2 vacant full time posts and also needs to recruit for one additional CSA using funding from Arriva to help with the additional workload. An Assessment Centre is being arranged for 6 March and an advert will go out shortly provided permission is granted.

23-Jan-2013

PI AP CTC 02.03

Channel Shift

31-Dec-2013

Sandra Marchant

Q3 Update - A beta (test) version of the new website will be issued to all staff for their comments by the end of January followed by gaining feedback from customer focus groups. The new website will be live sometime in April. New self-serve forms will be developed after this. A self-serve process for booking a bulky collection will be available from sometime in January.

23-Jan-2013


 

 

 

 

 

 

 

PI AP HSG 005 Number of households prevented from becoming homeless through the intervention of housing advice


 

 

 

 

 

 

 

 

Code

Title

Due Date

Progress Bar

Assigned To

Latest Note

Note Date

PI AP HSG 5.1

Service improvements for customers at risk of mortgage repossession – A relationship is being built with financial providers to alert the council when possession procedures.

30-Nov-2012

Pauline Meaney

Action completed and advice pack implemented for new cases

21-Jan-2013

PI AP HSG 5.2

Review of Rent Deposit Bond Scheme – to increase the availability of accommodation in the private rented sector available to customers threatened with homelessness

31-Dec-2012

Neil Coles

Work progressing with review of scheme and relaunch - currently finalising details before seeking Cabinet Member decision. Completion date expected to slip to 31/03/13.

21-Jan-2013

PI AP HSG 5.3

Delivery of multi-agency support group for young people – to identify needs of vulnerable young people before they become homeless

31-Jan-2013

Pauline Meaney

Work ongoing to set up agreed approach across a wide multi-agency group of stakeholders. This action may slip as a result, but expected to be completed by 31/03/13.

21-Jan-2013


 

 

PI AP HSG PS 002 Number of homes occupied by vulnerable people made decent


 

 

 

 

 

 

 

 

Code

Title

Due Date

Progress Bar

Assigned To

Latest Note

Note Date

PI AP HSG PS 2.1

Implementation of ‘Coldbusters’ grant scheme to deliver replacement boilers and central heating systems for qualifying residents

30-Nov-2012

Nigel Bucklow

Scheme awaiting final sign-off by Legal Services before implementation.

21-Jan-2013

PI AP HSG PS 2.2

Review of reporting structure for IT system to ensure accurate reporting of outcomes

31-Dec-2012

 

Action completed.

21-Jan-2013

PI AP HSG PS 2.3

Completion of review of Housing Assistance Policy to meet current demand and economic climate

31-Mar-2013

Neil Coles

Work progressing with drafting policy before consultation and Cabinet Member decision.

21-Jan-2013