Issue - meetings

MBC owned G&T sites reinvestment proposal

Meeting: 05/01/2021 - Communities, Housing and Environment Committee (Item 120)

120 Maidstone Borough Council Owned G&T Sites Investment Proposal pdf icon PDF 150 KB

Minutes:

The Housing Development Officer introduced the report, outlining the proposed investment and schedule of work for two Gypsy and Traveller Sites, located at Water Lane and Stilebridge. The identified areas for improvement were the amenity blocks, electricity and water supply to individual plots, road surfaces, communal lighting and signage. 

 

It was noted that the ongoing tender process was guided by the tender requirements and delivering value for money, rather than the £1 million budgeted. The final cost of the project would be provided later this year.

 

RESOLVED:That

 

1.  The planned works at Water Lane and Stilebridge mobile home sites be agreed; and

 

2.  The Director of Regeneration and Place be given delegated authority to enter into the necessary contracts and other agreements to enable works to take place.