Maidstone Leisure Centre solar microgeneration
1)
That the installation of a solar microgeneration system (solar
panels) at Maidstone Leisure Centre be approved;
2)
That a budget of up to £270,000 is made available for the
delivery of the project;
3)
That Officers be instructed to obtain the necessary permissions and
licences to implement the recommendations, including registration
for Feed in Tariff; sale or export of electricity; and appropriate
agreements with the District Network Operator; and to assign those
permissions and licences as appropriate; and
4)
That delegated authority be given to the Head of Commercial and
Economic Development, in consultation with the Head of Legal
Partnership, to enter into and conclude negotiations with Maidstone
Leisure Trust and Serco regarding their purpose of the electricity
generated.