This
report seeks updated approval for a project to carry out the
decarbonisation and energy savings measures at Maidstone House and
the Link, including a replacement low carbon heating system,
replacement glazing, full external insulation of the building,
upgrading of the lights to LED, installation of solar PV on the
Link / Business Terrace roof and refurbishment of the 4th Floor.
The project is a key component of the Council’s Biodiversity
and Climate Change Programme.
Decision type: Key
Reason Key: Expenditure > £250,000;
Decision status: Recommendations Approved (subject to call-in)
Wards affected: High Street Ward;
Notice of proposed decision first published: 14/06/2024
Decision due: 24 Jul 2024 by Cabinet
Lead member: Cabinet Member for Climate Transition and Nature Recovery
Lead director: Director of Finance and Business Improvement
Department: Property and Procurement
Contact: Mark Green, Director of Finance, Resources & Business Improvement Email: markgreen@maidstone.gov.uk.