Maidstone Highway Works Programme Report

To:                  Maidstone Joint Transportation Board

 

By:                   KCC Highways and Transportation

 

Date:                21st January 2015

 

Subject:           Highway Works Programme 2014/15

 

Classification: Information Only

 

 

Summary: This report updates Members on the identified schemes approved for construction in 2015/16

 

 

1. Introduction

 

This report provides an update and summarises schemes that have been programmed for delivery in 2015/16

 

 

Footway and Carriageway Improvement Schemes – see Appendix A

 

Street Lighting – see Appendix B

 

Traffic Systems – see Appendix C

 

Bridge Works- see Appendix D

 

Drainage- see Appendix E

 

 

 

Conclusion

 

  1. This report is for Members information.

 

 

Contact Officers:

 

The following contact officers can be contacted on 03000 41 81 81

 

Carol Valentine                                   Highway Manager (West)

Richard Emmett                                 Maidstone District Manager

Sue Kinsella                                        Street Lighting Manager

Neil Tree                                             Footway and Minor resurfacing Treatment

Alan Casson                                        Resurfacing Manager

Mary Gillett                                         Major Projects Planning Manager

Wendy Boustead                                Carriageway Surface Treatment Team Leader

Byron Lovell                                        Machine Resurfacing Team Leader

Katie Lewis                                          Drainage Manager

Toby Butler                                         Intelligent Transport Systems Manager

Tony Ambrose                                                Structures Manager

 

 

Appendix A – Footway and Carriageway Improvement Schemes

 

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

 

 

Micro Asphalt Schemes – Contact Officer Mr Neil Tree

 

Road Name

Parish

Extent of Works

Current Status

 

Gravelly Bottom Road

 

Broomfield & Kingswood

 

From its junction with  Pitt Road to its junction with Chartway Street

 

Completed

 

Caring Lane

 

Thurnham

 

 

From its junction with Ashford Road to its junction with Forge Lane

 

Completed

 

Boxley Road

 

Boxley

From its junction with Grange Lane to its junction with The Street (village gateway)

 

Completed

 

 

Machine Resurfacing – Contact Officer Mr Russell Boorman

Road Name

Parish

Extent of Works

Current Status

 

Willington Street

 

 

Maidstone

 

From its junction with Sutton Road to its junction with Deringwood Drive

 

Completed

 

A274 Sutton Road

 

Langley

 

Plough Wents Road to Horseshoes Lane

 

Works programmed to start 06/10/14 - 08/10/14

 

A274 Sutton Road

 

Maidstone

 

Wheatsheaf PH to Longfield Place

 

Works are programmed to start Summer/Autumn 2014

 

A249 Sittingbourne Road

 

Boxley

 

Southbound approach to M20 J7 Roundabout

 

Works programmed to start Spring 2015

 

A249 Detling Hill

 

Detling

 

Between Pilgrims Way and Scragged Oak Road

 

Works programmed to start 28/08/14 - 01/09/14

 

Teston Lane

 

Teston

 

From its junction with Lower Road to end of bridge

 

Works programmed to start Summer/Autumn 2014

 

Claygate Road

 

Marden

 

From its junction with Jarmans Lane to the entrance of CMS co Ltd

 

Works programmed to start Summer/Autumn 2014

 

Footway Improvement - Contact Officer Mrs Wendy Boustead

Road Name

Parish

Extent and Description of Works

Current Status

Sutton Road

Maidstone

From its junction with Cranbourne Avenue to its junction with Mangravat Avenue.  Replacement of existing surface with asphalt 

Programmed to start January 2015 for six weeks

Mill Street

Maidstone

From its junction with Bank street to its junction with Bishops Way.  Replacement of existing surface with asphalt

 

Programmed to start 27/10/14 for four weeks

Eyhorne Street

Hollingbourne

From its junction with Hasteds to its junction with Musket Lane.  Renewal of blockwork and existing surface. 

 

Completed

Ashford Road

Thurnham/Hollingbourne

From its junction with Roundwell to its junction with Musket Lane.  Replacement of asphalt surface. 

 

Programmed to start Autumn 2014 for eight weeks

Lower Road

West Farleigh

 

From its junction with Kettle Corner to its junction with Teston Lane.  Slurry Surfacing

 

Completed

Ashford Road

Hollingbourne

 

From its junction with Eyhorne Street to outside of property Park Mill House.  Slurry Surfacing

 

Programmed to start 21/11/14 – 23/11/14

Ashford Road

Weavering

 

From its junction with Willington Street to its junction with New Cut Road.  Slurry Surfacing

 

Programmed to start Autumn 2014 (tbc)

 

 

 

 

 

 

 

 


Appendix B – Street Lighting

 

Following the results of the programme of structural testing, the following columns have been identified as requiring replacement. Work is due to commence in October and dates are currently being programmed.

 

100

 

Road Name

Ward

Column Ref

Location

Status

ACORN PLACE

PARK WOOD

KAAC004

R/O 6 WALLIS AVENUE

 

COMPLETED

ACORN PLACE

PARK WOOD

KAAC005

ADJ 23/24

COMPLETED

 

 

 

 

 

ALLINGTON WAY

ALLINGTON

KAAR004

O/S 6/8

NOVEMBER

ALLINGTON WAY

ALLINGTON

KAAR007

O/S 24/26

NOVEMBER

ALLINGTON WAY

ALLINGTON

KAAR008

OPP 32

NOVEMBER

BEDGEBURY CLOSE

EAST

KBBK007

O/S 31

NOVEMBER

BEDGEBURY CLOSE

EAST

KBBK012

OPP 58

NOVEMBER

BICKNOR ROAD

NORTH DOWNS

KBCG014

O/S 85

AWAITING PROGRAMME

BIRCHOLT ROAD

PARK WOOD

KBCP016

OPP J/W HERONDEN RD

NOVEMBER

CHAPMAN AVENUE

SHEPWAY NORTH

KCBG017

O/S 81

NOVEMBER

CHATTENDEN COURT

NORTH

KCBZ003

O/S 20

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC002

O/S 27

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC013

O/S 97

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC010

O/S 75A

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC007

O/S 76 SUTTON HOUSE

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC006

O/S 53

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC004

O/S 39

NOVEMBER

COLLEGE ROAD

HIGH STREET

KCFC001

J/W HAYLE ROAD

NOVEMBER

CROSS KEYS

BEARSTEAD

KCGT008

OPP 58

NOVEMBER

EVERSLEY CLOSE

ALLINGTON

KEBD001

O/S 2

NOVEMBER

FELDERLAND CLOSE

PARK WOOD

KFAU003

O/S 66/67

NOVEMBER

FELDERLAND DRIVE

PARK WOOD

KFAV001

R/O 49/50

NOVEMBER

FOREST HILL

SOUTH

KFBN002

OPP 8

NOVEMBER

GREENWAY

HEATH

KGBZ002

O/S 59

NOVEMBER

GREENWAY

HEATH

KGBZ004

O/S 49/51

NOVEMBER

HEATH GROVE

HEATH

KHCE003

O/S 21/21a

NOVEMBER

HEVER CLOSE

SHEPWAY SOUTH

KHDI003

O/S 21

NOVEMBER

HEVER CLOSE

SHEPWAY SOUTH

KHDI006

O/S 22

NOVEMBER

HILLDEN SHAW

SOUTH

KHEA001

S/O 64 BROADOAK AVENUE

NOVEMBER

HOWARD DRIVE

ALLINGTON

KHFD003

O/S 22

NOVEMBER

JOHN STREET

NORTH

KJAG005

OPP J/W HARDY STREET

NOVEMBER

 

 

 

 

NOVEMBER

LEICESTER ROAD

SHEPWAY SOUTH

KLAV005

OPP J/W LANCASHIRE ROAD

NOVEMBER

LINTON ROAD

LOOSE

KLBS011

ADJ 23

NOVEMBER

LINTON ROAD

LOOSE

KLBS007

ADJ BRIDGE

NOVEMBER

LINTON ROAD

LOOSE

KLBS002

ADJ 3 HONEYSUCKLE MEWS

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ090

O/S 488/490

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ092

O/S 496/498

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ067

OPP 372

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ063

O/S 347

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ205

ADJ FOOTBRIDGE S/O 48

NOVEMBER

LOOSE ROAD

LOOSE

KLCQ204

ON FOOTBRIDGE S/O 81

NOVEMBER

MADGINFORD ROAD

BEARSTEAD

KMAB001

O/S 3

NOVEMBER

MAXWELL DRIVE

ALLINGTON

KMBW007

O/S 32

NOVEMBER

MAXWELL DRIVE

ALLINGTON

KMBW010

O/S 73

NOVEMBER

MAXWELL DRIVE

ALLINGTON

KMBW005

O/S 16

NOVEMBER

MAXWELL DRIVE

ALLINGTON

KMBW003

OPP J/W Howard Road

NOVEMBER

MAXWELL DRIVE

ALLINGTON

KMBW001

OPP 2

NOVEMBER

ODIHAM DRIVE

ALLINGTON

KOBM007

ON FP S/O 14 LULLINGSTONE RD

NOVEMBER

PICKERING STREET

SOUTH

KPBK005

ON FP S/O 45A OR 47 NEW HOUSE

NOVEMBER

POSTLEY ROAD

HIGH STREET

KPDB015

OPP 132/134

NOVEMBER

POSTLEY ROAD

HIGH STREET

KPDB008

O/S 76

NOVEMBER

QUEENS ROAD

HEATH

KQAG005

OPP J/W Queens Ave

NOVEMBER

QUEENS ROAD

HEATH

KQAG008

OPP 314

NOVEMBER

QUEENS ROAD

HEATH

KQAG010

O/S Langlands/Cantermerle

NOVEMBER

QUEENS ROAD

HEATH

KQAG016

OPP J/W Warden Close

NOVEMBER

QUEENS ROAD

HEATH

KQAG020

OPP 275

NOVEMBER

QUEENS ROAD

HEATH

KQAG029

O/S 231/233

NOVEMBER

QUEENS ROAD

HEATH

KQAG031

O/S 211/213

NOVEMBER

QUEENS ROAD

HEATH

KQAG041

BTW 189/199 FLATS & 96/98

NOVEMBER

QUEENS ROAD

HEATH

KQAG042

BTW 189/199 FLATS & 96/98

NOVEMBER

QUEENS ROAD

HEATH

KQAG044

BTW 189/199 FLATS & 96/98

NOVEMBER

QUEENS ROAD

HEATH

KQAG049

O/S 70/72

NOVEMBER

QUEENS ROAD

HEATH

KQAG050

O/S 62

NOVEMBER

QUEENS ROAD

HEATH

KQAG006

O/S 333/335

NOVEMBER

RANDALL STREET

NORTH

KRAC002

O/S 18

NOVEMBER

RANDALL STREET

NORTH

KRAC003

O/S 39

NOVEMBER

RANDALL STREET

NORTH

KRAC004

O/S 51

NOVEMBER

RANDALL STREET

NORTH

KRAC005

J/W FISHER STREET

NOVEMBER

REDE WOOD ROAD

BARMING

KRAN010

O/S 56

NOVEMBER

ROMNEY CLOSE

BEARSTEAD

KRBI002

S/O 94 ASHFORD RD

NOVEMBER

RUSHMEAD DRIVE

SOUTH

KRCB001

J/W LOOSE ROAD

NOVEMBER

RUSHMEAD DRIVE

SOUTH

KRCB004

OPP ADJ 6

NOVEMBER

SHIRLEY WAY

BEARSTEAD

KSBP901

O/S 19

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG021

O/S 24

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG022

OPP J/W LONGFIELD PLACE

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG024

OPP 52/54

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG025

O/S 60

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG026

OPP 68

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG027

OPP 76/78

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG028

OPP 86

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG029

OPP 1-10 VALENCE HOUSE

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG030

OPP J/W MANGRAVET AVENUE

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG031

ADJ J/W MANGRAVET AVENUE

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG032

OPP OAK TREES SCHOOL

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG033

OPP J/W NORTHUMBERLAND ROAD

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG034

O/S 94/96

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG035

O/S 104

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG036

O/S 207/209

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG037

OPP J/W GROVE ROAD

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGG038

ADJ J/W GROVE ROAD

NOVEMBER

SUTTON ROAD

SHEPWAY SOUTH

KSGF003

ADJ POLICE HQ

NOVEMBER

TICHBORNE CLOSE

ALLINGTON

KTBK004

O/S 18

NOVEMBER

TICHBORNE CLOSE

ALLINGTON

KTBK005

O/S 25/26

NOVEMBER

TREVOR DRIVE

ALLINGTON

KTCI015

O/S 135

NOVEMBER

WALLIS AVENUE

PARK WOOD

KWAD010

J/W BRISHING CLOSE

NOVEMBER

 

Appendix C – Traffic Systems

 

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

 

Traffic Systems - Contact Officer: Toby Butler

 

Location

Description of Works

Current Status

A229 College Road / Knightrider Street

Refurbishment of traffic signal controlled junction

Programmed for January 2014

A249 Sittingbourne Road / Holland Road

Refurbishment of traffic signal controlled junction

Not yet programmed but expected during August 2015

 


 

Bridge Works – Contact Officer Tony Ambrose

 

Road Name

Parish

Description of Works

Current Status

A229 Fairmeadow

Maidstone

Painting Waterside Steps railings (on behalf of Maidstone Borough Council). Works carried out off-carriageway.

Completed

Appendix D- Bridge Works

 

 

 

 


Appendix E – Drainage Repairs & Improvements

 

Drainage Repairs & Improvements - Contact Officer Katie Lewis

 

Road Name

Parish

Description of Works

Current Status

Waterditch Lane

Lenham

Installation of new gullies and soakaway

Works Completed 05/06/13

The Square

Lenham

Replacement of 2 gullies and crushed pipework

Works Completed 22/05/13

Water Lane

Bearsted

Installation of new gullies, ditch clearance and addition of concrete aprons

Works Completed 07/08/13

Smiths Hill

West Farleigh

Installation of new gullies and kerbs

Works commenced 30/09/13

Tonbridge Road

Teston

Addition of deepbore to existing soakaway

Scheme identified and being designed

Cripple Street

Loose

Repair works to failed Soakaway

Works Completed 13/09/13

Bonnington Road

Vinters Park

Installation of new Soakaway and gullies

Works to commence End of October 2013

Vicarage Road

Yalding

Drainage repairs under Road Closure

Road Closure booked for 28/10/13

 

 

 

 

 

 

 

1.1               Legal Implications

1.1.1         Not applicable.

1.2               Financial and Value for Money Considerations

1.2.1         Not applicable.

1.3               Risk Assessment

1.3.1         Not applicable.

Contact: Carol Valentine/ Richard Emmett – 03000 41 81 81