To: Maidstone Joint Transportation Board
By: KCC Highways and Transportation
Date: 21st January 2015
Subject: Highway Works Programme 2014/15
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2015/16
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2015/16
Footway and Carriageway Improvement Schemes – see Appendix A
Street Lighting – see Appendix B
Traffic Systems – see Appendix C
Bridge Works- see Appendix D
Drainage- see Appendix E
Conclusion
- This report is for Members information.
Contact Officers:
The following contact officers can be contacted on 03000 41 81 81
Carol Valentine Highway Manager (West)
Richard Emmett Maidstone District Manager
Sue Kinsella Street Lighting Manager
Neil Tree Footway and Minor resurfacing Treatment
Alan Casson Resurfacing Manager
Mary Gillett Major Projects Planning Manager
Wendy Boustead Carriageway Surface Treatment Team Leader
Byron Lovell Machine Resurfacing Team Leader
Katie Lewis Drainage Manager
Toby Butler Intelligent Transport Systems Manager
Tony Ambrose Structures Manager
Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Micro Asphalt Schemes – Contact Officer Mr Neil Tree
|
|||
Road Name |
Parish |
Extent of Works |
Current Status |
Gravelly Bottom Road |
Broomfield & Kingswood |
From its junction with Pitt Road to its junction with Chartway Street |
Completed |
Caring Lane |
Thurnham
|
From its junction with Ashford Road to its junction with Forge Lane |
Completed |
Boxley Road |
Boxley |
From its junction with Grange Lane to its junction with The Street (village gateway) |
Completed
|
Machine Resurfacing – Contact Officer Mr Russell Boorman |
|||
Road Name |
Parish |
Extent of Works |
Current Status |
Willington Street
|
Maidstone |
From its junction with Sutton Road to its junction with Deringwood Drive |
Completed |
A274 Sutton Road |
Langley |
Plough Wents Road to Horseshoes Lane |
Works programmed to start 06/10/14 - 08/10/14 |
A274 Sutton Road |
Maidstone |
Wheatsheaf PH to Longfield Place |
Works are programmed to start Summer/Autumn 2014 |
A249 Sittingbourne Road |
Boxley |
Southbound approach to M20 J7 Roundabout |
Works programmed to start Spring 2015 |
A249 Detling Hill |
Detling |
Between Pilgrims Way and Scragged Oak Road |
Works programmed to start 28/08/14 - 01/09/14 |
Teston Lane |
Teston |
From its junction with Lower Road to end of bridge |
Works programmed to start Summer/Autumn 2014 |
Claygate Road |
Marden |
From its junction with Jarmans Lane to the entrance of CMS co Ltd |
Works programmed to start Summer/Autumn 2014 |
Footway Improvement - Contact Officer Mrs Wendy Boustead |
|||
Road Name |
Parish |
Extent and Description of Works |
Current Status |
Sutton Road |
Maidstone |
From its junction with Cranbourne Avenue to its junction with Mangravat Avenue. Replacement of existing surface with asphalt |
Programmed to start January 2015 for six weeks |
Mill Street |
Maidstone |
From its junction with Bank street to its junction with Bishops Way. Replacement of existing surface with asphalt |
Programmed to start 27/10/14 for four weeks |
Eyhorne Street |
Hollingbourne |
From its junction with Hasteds to its junction with Musket Lane. Renewal of blockwork and existing surface. |
Completed |
Ashford Road |
Thurnham/Hollingbourne |
From its junction with Roundwell to its junction with Musket Lane. Replacement of asphalt surface. |
Programmed to start Autumn 2014 for eight weeks |
Lower Road |
West Farleigh |
From its junction with Kettle Corner to its junction with Teston Lane. Slurry Surfacing |
Completed |
Ashford Road |
Hollingbourne |
From its junction with Eyhorne Street to outside of property Park Mill House. Slurry Surfacing |
Programmed to start 21/11/14 – 23/11/14 |
Ashford Road |
Weavering |
From its junction with Willington Street to its junction with New Cut Road. Slurry Surfacing |
Programmed to start Autumn 2014 (tbc) |
Appendix B – Street Lighting
Following the results of the programme of structural testing, the following columns have been identified as requiring replacement. Work is due to commence in October and dates are currently being programmed.
100
|
|||||||
Road Name |
Ward |
Column Ref |
Location |
Status |
|||
ACORN PLACE |
PARK WOOD |
KAAC004 |
R/O 6 WALLIS AVENUE |
COMPLETED |
|||
ACORN PLACE |
PARK WOOD |
KAAC005 |
ADJ 23/24 |
COMPLETED |
|||
|
|
|
|
|
|||
ALLINGTON WAY |
ALLINGTON |
KAAR004 |
O/S 6/8 |
NOVEMBER |
|||
ALLINGTON WAY |
ALLINGTON |
KAAR007 |
O/S 24/26 |
NOVEMBER |
|||
ALLINGTON WAY |
ALLINGTON |
KAAR008 |
OPP 32 |
NOVEMBER |
|||
BEDGEBURY CLOSE |
EAST |
KBBK007 |
O/S 31 |
NOVEMBER |
|||
BEDGEBURY CLOSE |
EAST |
KBBK012 |
OPP 58 |
NOVEMBER |
|||
BICKNOR ROAD |
NORTH DOWNS |
KBCG014 |
O/S 85 |
AWAITING PROGRAMME |
|||
BIRCHOLT ROAD |
PARK WOOD |
KBCP016 |
OPP J/W HERONDEN RD |
NOVEMBER |
|||
CHAPMAN AVENUE |
SHEPWAY NORTH |
KCBG017 |
O/S 81 |
NOVEMBER |
|||
CHATTENDEN COURT |
NORTH |
KCBZ003 |
O/S 20 |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC002 |
O/S 27 |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC013 |
O/S 97 |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC010 |
O/S 75A |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC007 |
O/S 76 SUTTON HOUSE |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC006 |
O/S 53 |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC004 |
O/S 39 |
NOVEMBER |
|||
COLLEGE ROAD |
HIGH STREET |
KCFC001 |
J/W HAYLE ROAD |
NOVEMBER |
|||
CROSS KEYS |
BEARSTEAD |
KCGT008 |
OPP 58 |
NOVEMBER |
|||
EVERSLEY CLOSE |
ALLINGTON |
KEBD001 |
O/S 2 |
NOVEMBER |
|||
FELDERLAND CLOSE |
PARK WOOD |
KFAU003 |
O/S 66/67 |
NOVEMBER |
|||
FELDERLAND DRIVE |
PARK WOOD |
KFAV001 |
R/O 49/50 |
NOVEMBER |
|||
FOREST HILL |
SOUTH |
KFBN002 |
OPP 8 |
NOVEMBER |
|||
GREENWAY |
HEATH |
KGBZ002 |
O/S 59 |
NOVEMBER |
|||
GREENWAY |
HEATH |
KGBZ004 |
O/S 49/51 |
NOVEMBER |
|||
HEATH GROVE |
HEATH |
KHCE003 |
O/S 21/21a |
NOVEMBER |
|||
HEVER CLOSE |
SHEPWAY SOUTH |
KHDI003 |
O/S 21 |
NOVEMBER |
|||
HEVER CLOSE |
SHEPWAY SOUTH |
KHDI006 |
O/S 22 |
NOVEMBER |
|||
HILLDEN SHAW |
SOUTH |
KHEA001 |
S/O 64 BROADOAK AVENUE |
NOVEMBER |
|||
HOWARD DRIVE |
ALLINGTON |
KHFD003 |
O/S 22 |
NOVEMBER |
|||
JOHN STREET |
NORTH |
KJAG005 |
OPP J/W HARDY STREET |
NOVEMBER |
|||
|
|
|
|
NOVEMBER |
|||
LEICESTER ROAD |
SHEPWAY SOUTH |
KLAV005 |
OPP J/W LANCASHIRE ROAD |
NOVEMBER |
|||
LINTON ROAD |
LOOSE |
KLBS011 |
ADJ 23 |
NOVEMBER |
|||
LINTON ROAD |
LOOSE |
KLBS007 |
ADJ BRIDGE |
NOVEMBER |
|||
LINTON ROAD |
LOOSE |
KLBS002 |
ADJ 3 HONEYSUCKLE MEWS |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ090 |
O/S 488/490 |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ092 |
O/S 496/498 |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ067 |
OPP 372 |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ063 |
O/S 347 |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ205 |
ADJ FOOTBRIDGE S/O 48 |
NOVEMBER |
|||
LOOSE ROAD |
LOOSE |
KLCQ204 |
ON FOOTBRIDGE S/O 81 |
NOVEMBER |
|||
MADGINFORD ROAD |
BEARSTEAD |
KMAB001 |
O/S 3 |
NOVEMBER |
|||
MAXWELL DRIVE |
ALLINGTON |
KMBW007 |
O/S 32 |
NOVEMBER |
|||
MAXWELL DRIVE |
ALLINGTON |
KMBW010 |
O/S 73 |
NOVEMBER |
|||
MAXWELL DRIVE |
ALLINGTON |
KMBW005 |
O/S 16 |
NOVEMBER |
|||
MAXWELL DRIVE |
ALLINGTON |
KMBW003 |
OPP J/W Howard Road |
NOVEMBER |
|||
MAXWELL DRIVE |
ALLINGTON |
KMBW001 |
OPP 2 |
NOVEMBER |
|||
ODIHAM DRIVE |
ALLINGTON |
KOBM007 |
ON FP S/O 14 LULLINGSTONE RD |
NOVEMBER |
|||
PICKERING STREET |
SOUTH |
KPBK005 |
ON FP S/O 45A OR 47 NEW HOUSE |
NOVEMBER |
|||
POSTLEY ROAD |
HIGH STREET |
KPDB015 |
OPP 132/134 |
NOVEMBER |
|||
POSTLEY ROAD |
HIGH STREET |
KPDB008 |
O/S 76 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG005 |
OPP J/W Queens Ave |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG008 |
OPP 314 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG010 |
O/S Langlands/Cantermerle |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG016 |
OPP J/W Warden Close |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG020 |
OPP 275 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG029 |
O/S 231/233 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG031 |
O/S 211/213 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG041 |
BTW 189/199 FLATS & 96/98 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG042 |
BTW 189/199 FLATS & 96/98 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG044 |
BTW 189/199 FLATS & 96/98 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG049 |
O/S 70/72 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG050 |
O/S 62 |
NOVEMBER |
|||
QUEENS ROAD |
HEATH |
KQAG006 |
O/S 333/335 |
NOVEMBER |
|||
RANDALL STREET |
NORTH |
KRAC002 |
O/S 18 |
NOVEMBER |
|||
RANDALL STREET |
NORTH |
KRAC003 |
O/S 39 |
NOVEMBER |
|||
RANDALL STREET |
NORTH |
KRAC004 |
O/S 51 |
NOVEMBER |
|||
RANDALL STREET |
NORTH |
KRAC005 |
J/W FISHER STREET |
NOVEMBER |
|||
REDE WOOD ROAD |
BARMING |
KRAN010 |
O/S 56 |
NOVEMBER |
|||
ROMNEY CLOSE |
BEARSTEAD |
KRBI002 |
S/O 94 ASHFORD RD |
NOVEMBER |
|||
RUSHMEAD DRIVE |
SOUTH |
KRCB001 |
J/W LOOSE ROAD |
NOVEMBER |
|||
RUSHMEAD DRIVE |
SOUTH |
KRCB004 |
OPP ADJ 6 |
NOVEMBER |
|||
SHIRLEY WAY |
BEARSTEAD |
KSBP901 |
O/S 19 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG021 |
O/S 24 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG022 |
OPP J/W LONGFIELD PLACE |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG024 |
OPP 52/54 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG025 |
O/S 60 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG026 |
OPP 68 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG027 |
OPP 76/78 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG028 |
OPP 86 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG029 |
OPP 1-10 VALENCE HOUSE |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG030 |
OPP J/W MANGRAVET AVENUE |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG031 |
ADJ J/W MANGRAVET AVENUE |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG032 |
OPP OAK TREES SCHOOL |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG033 |
OPP J/W NORTHUMBERLAND ROAD |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG034 |
O/S 94/96 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG035 |
O/S 104 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG036 |
O/S 207/209 |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG037 |
OPP J/W GROVE ROAD |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGG038 |
ADJ J/W GROVE ROAD |
NOVEMBER |
|||
SUTTON ROAD |
SHEPWAY SOUTH |
KSGF003 |
ADJ POLICE HQ |
NOVEMBER |
|||
TICHBORNE CLOSE |
ALLINGTON |
KTBK004 |
O/S 18 |
NOVEMBER |
|||
TICHBORNE CLOSE |
ALLINGTON |
KTBK005 |
O/S 25/26 |
NOVEMBER |
|||
TREVOR DRIVE |
ALLINGTON |
KTCI015 |
O/S 135 |
NOVEMBER |
|||
WALLIS AVENUE |
PARK WOOD |
KWAD010 |
J/W BRISHING CLOSE |
NOVEMBER |
|||
Appendix C – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler
|
||
Location |
Description of Works |
Current Status |
A229 College Road / Knightrider Street |
Refurbishment of traffic signal controlled junction |
Programmed for January 2014 |
A249 Sittingbourne Road / Holland Road |
Refurbishment of traffic signal controlled junction |
Not yet programmed but expected during August 2015 |
Bridge Works – Contact Officer Tony Ambrose
|
|||
Road Name |
Parish |
Description of Works |
Current Status |
A229 Fairmeadow |
Maidstone |
Painting Waterside Steps railings (on behalf of Maidstone Borough Council). Works carried out off-carriageway. |
Completed |
Appendix D- Bridge Works
Appendix E – Drainage Repairs & Improvements
Drainage Repairs & Improvements - Contact Officer Katie Lewis
|
|||
Road Name |
Parish |
Description of Works |
Current Status |
Waterditch Lane |
Lenham |
Installation of new gullies and soakaway |
Works Completed 05/06/13 |
The Square |
Lenham |
Replacement of 2 gullies and crushed pipework |
Works Completed 22/05/13 |
Water Lane |
Bearsted |
Installation of new gullies, ditch clearance and addition of concrete aprons |
Works Completed 07/08/13 |
Smiths Hill |
West Farleigh |
Installation of new gullies and kerbs |
Works commenced 30/09/13 |
Tonbridge Road |
Teston |
Addition of deepbore to existing soakaway |
Scheme identified and being designed |
Cripple Street |
Loose |
Repair works to failed Soakaway |
Works Completed 13/09/13 |
Bonnington Road |
Vinters Park |
Installation of new Soakaway and gullies |
Works to commence End of October 2013 |
Vicarage Road |
Yalding |
Drainage repairs under Road Closure |
Road Closure booked for 28/10/13 |
|
|
|
|
1.1 Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contact: Carol Valentine/ Richard Emmett – 03000 41 81 81