Joint Transportation Boards

To:                              Maidstone Joint Transportation Board

By:                              Tim Read, Head of Transportation

Date:                          21st January 2015

Subject:                    Highways Improvement Schemes Report

Classification:         For Information

 

Summary: The purpose of this report is to provide members with a progress report on traffic and safety schemes currently being progressed by KCC Highways and Transportation

 

 

 

 

 

Appendices

A.   Highway Improvement Schemes.

B.   Member Highway Funded Schemes.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix A- Highway Schemes

 

1.  A229 Running Horse Roundabout

 

We are continuing to monitor the scheme and propose minor amendments. All necessary technical approvals for the amendments have been obtained.  The work to alter the road markings is weather dependant but we hope to complete these works in the next few weeks.

 

2.   A229 Stile Bridge to Knoxbridge

 

We developed a scheme including improved direction signage, high friction surfacing and improved cats-eyes, as well as undertaking substantial vegetation removal. All of the works with exception to the large advanced direction signage is complete.  Special passively safe posts have delayed the larger signs and these are expected within the next four weeks.

 

 

3.    2014-15 Crash Remedial Measure Schemes

 

Work on the previously identified Crash Remedial sites is largely complete. Some signage works at B2163 Penfold Hill, Leeds and also on the A20 at Roundwell, Bearsted remains outstanding and this due within the next four to six weeks.

 

4.    2015- 16 Crash Remedial Measures Schemes

 

Work has commenced on identifying future sites requiring intervention. This has identified potential schemes at:

·         A20 Lenham j/w Faversham Road

·         Lidsing Road  j/w Pilgrims Way (Boxley Hill)

·         Sandling Lane j/w Old Chatham Road (Running Horse PH)

 

Contact Officer: Michael Heath

Tel: 03000 418181

 

 

 

 

 

 

 

 

 


  Appendix B- Member Highway Fund

 

Member Highway Fund programme update for the Maidstone District.

 

The following schemes are those which have been approved for funding by both the relevant Member and by John Burr, Director of Highways and is up to date as of 13 January 2015.

 

The details below are for Highway Schemes only and do not detail contributions Members have made to other groups such as Parish or District Councils.

 

More detail on their schemes can accessed by each Member via the online database or by contacting their Member Highway Fund Engineer.

 

 

Overview of 2014/15 Schemes

 

Brian Clark

 

Scheme

Status

To plant 1 one tree, Park Way

 

With Soft Landscape Team awaiting date for planting

Farleigh Hill, Tovil (dropped kerb)

Drainage concerns, recommendation not to continue.  Scheme on hold

Oxford Road (access ‘dog bone’ marking)

Complete

Cumberland Avenue, Shepway (upgrade 2 x street lighting columns  to LED lamps, remove bollards and install fencing, install parking bays)

Redesign in progress as of January 2015

Pheasant Lane (lockable bollards)

Handed over for delivery December 2014

Pheasant Lane (verge and post box protection)

Handed over for delivery December 2014

Lancet Lane Parking Restrictions TRO

Design underway, consultation scheduled to commence following advertisement of Notice (January 2015)

 

 

Eric Hotson

 

Scheme

Status

Brishing Lane, Maidstone (unsuitable for HGVs)

Handed over for delivery December 2014

 

 

Gary Cooke

 

Scheme

Status

Brishing Lane, Maidstone (unsuitable for HGVs)

Handed over for delivery December 2014

 

 

 

 

Jenny Whittle

 

Scheme

Status

Maidstone Road, Headcorn (highway mirror)

Design completed December 2014

 

 

Paul Carter

 

Scheme

Status

Sharsted Lane, Bearstead (dropped Kerb)

Handed over for delivery December 2014

 

 

Paulina Stockell

 

Scheme

Status

West Street, Hunton (verge marker posts)

Handed over for delivery December 2014

 

 

 

Overview of 2013/14 Schemes

 

Brian Clark

 

Scheme

Status

To plant 1 mature tree to replace one which was felled - Parkway

 

Complete

KB49 Pathway resurface Old Drive to Anglesea Avenue

Complete

Installation of 2 no. timber bollards – Cripple Street

Complete

To reconstruct ramps either side of table top plus a 3m length of carriageway in the landing area either side of ramp feature.

Complete

York Road – Replacement of post rail and fencing

Complete

Straw Mill Hill – 4 no. bollards

Complete

Bus Shelter replacement – Tovil Hill

Complete

Installation of ‘SLOW’ road markings – Burial Ground Lane

Complete

 

 

Dan Daley

 

Scheme

Status

To install pedestrians in road ahead lit warning signs on lamp columns either side of existing informal crossing point -Buckland Hill

 

Works Completed

Carry out improvements to signing – Marigold Way

Works Completed

Provide down-lighting at crossing point and warning sign for traffic coming round bend from Tonbridge Rd

Handed over for Delivery

 

Provide Warning Sign on Upper Fant Rd for traffic travelling westwards into Hackney Rd together with SLOW marking on roadway

 

Installation of SLOW marking – Complete

Installation of Warning Sign - ongoing

 

Buckland Road – Consultation with residents to improve access for emergency vehicles

Consultation On-going

Palace Wood School, Ash Grove – Traffic regulation order to amend the markings outside the school

TRO complete, awaiting installation of associated lining works

Bower Lane – Remove a section of parking restrictions and install further parking bays

TRO complete, awaiting installation of associated lining works

 

 

 

Eric Hotson

 

Scheme

Status

New 30mph interactive speed sign – A229 by Church Green

Complete

 

To install timber bollards to prevent parking on the footway – Gybbon Rise

Complete

 

Church Hill outside Boughton Monchelsea CPS – New footpath

Complete

 

A229 Sutton Valance – Commission to carry out a feasibility study for a pedestrian crossing and footway link to Haven Farm

Complete

 

 

 

Gary Cooke

 

Scheme

Status

Installation of timber bollards to prevent inconsiderate parking at school pick up and drop off times – Wexford Place

Completed

 

An additional parking bay in Buckingham Row

Completed

To install Unsuitable for HGVs signage in Downswood

Completed

To investigate and implement a reduced weight limit restriction of 7.5 tons on the B2163 Leeds

Abandoned

 

 

 

 

Ian Chittenden

 

Scheme

Status

Contribution for the replacement of 2 flower beds, including new trees and shrubs – Heathorn Street

Completed

 

To install a directional sign for Maidstone Football Club

Completed

To replace or remove trees within this division

Completed

St Paul’s School, Hatherall Road – Extension of school keep clear zig zag markings

Consultation Complete.  Awaiting Installation

 

 

 

Jenny Whittle

 

Scheme

Status

To install Unsuitable for HGVs signage – Rayners Hill

Complete

To install Unsuitable for HGVs signage – A20 before the Broomhill Road junction

Complete

Five Wents and Chegworth Road – Installation of signage

Handed over for Delivery

To install ‘Unsuitable for HGVs’ signs in Broomfield Road and the A20

Complete

 

Lenham Road, Kingswood – Installation of 2 no. bend warning signs

Complete

 

 

 

Paul Carter

 

Scheme

Status

Installation of ‘Cyclists Dismount’ signs – Ragstone Road

Completed

 

To make a contribution to PROW for resurfacing the top 20 metres of path - Pathway KM79 in Bearsted by the BP Garage.

 

Completed

 

Boxley Road – Lining refreshment

Handed over for Delivery

Dunn Street Road – Lining refreshment

Completed

Yeoman Lane – Concrete post and rail replacement

Completed

Bearsted, Boxley and Bredhurst – Various works by Community Operations

Handed Over for Delivery

 

 

 

Paulina Stockell

 

Scheme

Status

To install village gateway with welcome to Hunton sign, remove redundant posts, relocate existing footpath sign and install marker posts

Complete

Installation of School Warning signs – Lower Road, near St Helens school

Complete

Road marking improvements – various locations in East Farleigh

Awaiting completion of road markings at Forge Lane / Dean Street.

Contribution towards the remedial works carried out by the Traffic Schemes Team

Complete

Replacement of a multi-lingual sign in East Farleigh

Complete

Sheephurst Lane – To reduce the speed limit along the entire length to 40 mph.

Awaiting Completion

Dean Street – To extend the existing 30 mph.

Handed over for delivery

 

 

 

 

 

      Rob Bird

 

Scheme

Status

To install pedestrians in road ahead lit warning signs on lamp columns either side of existing informal crossing point -Buckland Hill

Works Completed

Carry out improvements to signing – Marigold Way

Works Completed

Provide down-lighting at crossing point and warning sign for traffic coming round bend from Tonbridge Rd

Handed over for Delivery

 

Provide Warning Sign on Upper Fant Rd for traffic travelling westwards into Hackney Rd together with SLOW marking on roadway

Installation of SLOW marking – Complete

Installation of Warning Sign – ongoing

Buckland Road – Consultation with residents to improve access for emergency vehicles

Consultation On-going

Palace Wood School, Ash Grove – Traffic regulation order to amend the markings outside the school

TRO complete, awaiting installation of associated lining works

Bower Lane – Remove a section of parking restrictions and install further parking bays

TRO complete, awaiting installation of associated lining works

 

 

 

Overview of 2012/13 Schemes

 

 

Gary Cooke – Maidstone South East

 

Scheme

Status

B2163 Leeds – Gateway Improvements

Complete

 

 

Dan Daley – Maidstone Central

 

Scheme

Status

Newbury Ave & Allington Way – Installation of warning signage and associated carriageway markings

Complete

 

 

Eric Hotson – Maidstone Rural South

 

Scheme

Status

Marden Road, Staplehurst – Extension of 30Mph Speed Limit

Programmed August 2014

 

 

 

 

 

 

 

Rob Bird – Maidstone Central

 

Scheme

Status

Newbury Ave & Allington Way – Installation of warning signage and associated carriageway markings

Complete

 

 

 

Paulina Stockell – Maidstone Rural West

 

Scheme

Status

St Margaret’s School, Collier Street – Installation of Interactive Sign and parking restrictions in the vicinity of St Margaret’s School

Consultation now complete.  Awaiting programming