Joint Transportation Boards

To:                              Maidstone Joint Transportation Board

By:                              Tim Read, Head of Transportation

Date:                          15th April 2015

Subject:                    Schemes Report

Classification:         For Information

 

Summary: The purpose of this report is to provide members with a progress report on traffic and safety schemes currently being progressed by KCC Highways and Transportation

 

 

1.  A229 Running Horse Roundabout

 

We are continuing to monitor the scheme and propose minor amendments to the signage and road markings on two approaches to the roundabout. We hope this may improve lane discipline on the approaches and roundabout. These alterations are now programmed for April 2015

 

2.   A229 Stile Bridge to Knoxbridge

 

We developed a scheme including improved direction signage, high friction surfacing and improved cats-eyes, as well as undertaking substantial vegetation removal. These works are now complete and we will continue to monitor the sites safety going forward.

 

 

3.    2014-15 Crash Remedial Measure Schemes

 

Work on the previously identified 2014/15 Crash Remedial sites is now complete. One site, the junction of the A20 at Roundwell, Bearsted remains outstanding.

 

4.    2015- 16 Crash Remedial Measures Schemes

 

Work has commenced on identifying future sites requiring intervention. This has identified potential schemes for the current 2015/16 financial year at:

·         A20 Lenham j/w Faversham Road

·         Lidsing Road  j/w Pilgrims Way (Boxley Hill)

·         Sandling Lane j/w Old Chatham Road (Running Horse PH)

 

Contact Officer: Michael Heath

Tel: 03000 418181

 

 

 

 

 

 

 

 

Appendix B:

 

Combined Member Fund (Highways) programme update for the Maidstone District.

 

The following schemes are those which have been approved for funding by both the relevant Member and by John Burr, Director of Highways and is up to date as of 18 March 2015.

 

The details provided below are for Highway Schemes only (i.e. schemes that are either in design, or awaiting/in the process of being constructed or recently completed on site).  The list does not refer to contribution only requests, including contributions to other groups such as Parish or District Councils.  Feasibility and investigation studies may be mentioned, but are also excluded from the update list*

 

*More information on highway schemes, and including highway contributions and highway studies, can be accessed by each Member via the online database or by contacting their Highway Project Engineer.

 

 

Combined Member Fund Highway Schemes

 

Paul Carter

 

Details of Scheme

Status

Roseacre Lane and Yeoman Lane – Proposed 20 mph Zone

Traffic survey and draft design complete.  Design check underway, and consultation with statutory stakeholders and other relevant parties will commence in April

Old Chatham Road/Sandling Lane – provision of dropped kerb crossing for pedestrians crossing from the car park to the Running Horse (Harvester) Public House and Restaurant

Design complete and a Road Safety Audit is in progress.  Consultation with the Harvester Group has commenced

Mr Carter has provided funding towards the Old Chatham Road HGV Management and Parking Scheme in addition to funding for Boxley shrub maintenance and PROW KH3 north link

 

 

 

Brian Clark

 

Details of Scheme

Status

Corrance Green - Replace recently felled Tree.  Grind Stump of felled tree in Corrance Green and replant.

With the County Member

Cumberland Avenue -  Provision of parking, installation of fencing and the removal of bollards, upgrade of lighting and extension of the existing verge area

Design underway.  Street lighting investigating the upgrade.

 

Brian Clark (continued)

 

Farleigh Hill – Provision of an informal drop kerb crossing on the footway outside the Tile Centre to allow disabled pedestrians to cross to Lidl if they come down from Tesco.  The works will require infringement of private land which has been agreed to by the land owner

Design complete.  Awaiting legal agreement between KCC and the land owner to be completed

Lancet Lane - implement double yellow line junction protection at the Waldron Drive/Lancet Lane junction to prevent hazardous parking

TRO with legal for sealing.  Works to be ordered upon completion of the sealing of the Order

Pheasant Lane (1) - Install new wooden bollards in the green area around post box at entrance of Pheasant Lane to prevent vehicles parking on the grass or mounting the kerb

Handed over for delivery.  Works are imminent

Pheasant Lane (2) – Provision of lockable bollards to prevent Pheasant Lane being used as a through road

Works completed 13 March 2015

West Park Road – Salt bin

Handed over to the KCC Operations Team for delivery



Caernarvon Drive – Salt bin has been provided but in the wrong place and is to be relocated to its correct position as per the original request

Handed over to the KCC Operations Team for delivery

Plains Road - Implementation of a yellow box marking at the Plains Avenue/Loose Road junction Maidstone. The works will be carried out on a weekday between up and 11pm to avoid to the Kent Lane Rental charges

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site.

Westward Road – Salt bin

Handed over to the KCC Operations Team for delivery

Mayfair Avenue - between footpath and allotment gate green area to left of the gate, install 2 bollards to prevent trucks parking on the green verge in front of the allotments

Handed over to Amey Consulting for design and delivery

Broadoak Avenue nr Cripple Street - Plant 2 trees, outside 5 and 7

Seeking site approval and quotation form the Soft Landscape Team

Parkway – Plant 2 trees

Seeking site approval and quotation form the Soft Landscape Team

 

Dan Daley

 

Details of Scheme

Status

Bower Lane, Fant – TRO (yellow lines)

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Cherry Orchard Way - TRO (yellow lines)

With Amey Consulting for implementation (TRO sealed).  Engineer has been advised a road space permit is being arranged and a gang sourced for out of hours working

Buckland Road -  TRO, removal of 1 residents parking bay outside no. 53 opposite no. 42 to improve access to driveways of properties and allow emergency vehicles to pass (C Reynolds of MBC)

With Amey Consulting for progression.  KCC Engineer has requested an update

Upper Fant Road – South west end of Upper Fant Road just before the bend leading into Hackney Road

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Fant Lane outside Bower Grove School - Provide down-lighting at crossing point and warning sign for traffic coming round the bend from Tonbridge Road and on the roadway in both directions

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Keswick Drive junction with Shearwater – Salt bin

Complete

Freshland Road – junction with Melford Drive – Salt bin

Complete

Stagshaw Close – TRO (single yellow lines and school Keep Clear)

With Amey Consulting for design and progression of the TRO in conjunction with Maidstone Borough Council Parking Team

 


 

Eric Hotson

 

Details of Scheme

Status

Brishing Lane, Boughton Monchelsea - Advanced warning of Unsuitable HGV sign on Brishing Lane. Lorries are either ignoring the existing sign or the existing sign is in the wrong place with HGVs not seeing the sign until it’s too late

Handed over to Amey Consulting for delivery

Marsham Crescent and Mercer Way - 2 x No Through Road Signs

Handed over for delivery

Linton Road, Loose - Salt bin outside Loose Valley Nursing Home

Handed over to the KCC Operations Team for delivery

Mr Hotson has also submitted a request for an investigation into improvements at Chart Sutton

 

 

Gary Cooke

 

Details of Scheme

Status

Brishing Lane, Boughton Monchelsea - Advanced warning of Unsuitable HGV sign on Brishing Lane. Lorries are either ignoring the existing sign or the existing sign is in the wrong place with HGVs not seeing the sign until it’s too late

Handed over to Amey Consulting for delivery

Mr Cooke has provided funding for Spring Clean Events to take place across his district in Leeds, Otham, Downswood, Boughton Monchelsea (north) and Parkwood/Shepway (south).  The project is a joint venture involving Highways, Consultation and Engagement, the Parish Councils and local volunteers.

 

 

Ian Chittenden

 

Details of Scheme

Status

St. Pauls School, Hatherall Road, Maidstone - 1. Extension of zig zag lines one side outside St Pauls school for about 30m to cover new pedestrian entrance where there has already been dangerous occurrences.

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Heathfield Road, Maidstone - Outside numbers 36, 38 and 40, Amendment to TRO to remove two short lengths of double yellow lines in front of driveways

Handed over to Amey Consulting for delivery.  Consultation resulted in design change.  Amended Notice to be advertised

 

 

 

Ian Chittenden (continued)

 

Maidstone - Please provide three new trees (1) In the verge opposite 1 Moncktons Avenue where a tree has been removed

(2) Tree pit in the verge outside 15 Curzon Road (3) In the grass verge opposite the Hilton Hotel in Bearsted Road to replace a large cherry tree that has been removed

Handed over to the KCC Soft Landscape Team for delivery

Windsor Close off Sittingbourne Road - drop kerbs pedestrian ramps with tactile paving at the junction of Windsor Close with Sittingbourne Road

Handed over for delivery

Mr Chittenden has provided funding for an investigation into options for reducing speed and improving road safety along Sittingbourne Road in Maidstone to the Chiltern Hundreds roundabout, including the potential to extend the 30 mph speed limit

 

 

Jenny Whittle

 

Details of Scheme

Status

Chegworth Lane/A20 – HGV sign improvements and provision of HGV gateways.  Scheme also includes upgrading the centre island direction signs (works are being undertaken and funded in conjunction with Richard Emmett)

In progress.  Design and costing are complete. 

East Sutton Parish Church – Salt bin

Handed over to the KCC Operations Team for delivery

Maidstone Road, Headcorn - The entrance to Headcorn Bowling Club is not clearly visible from Maidstone Road and there are issues with drivers accessing and exiting the Club.  The road is subject to a 50 mph speed limit.  Provision of direction signs and ‘Slow’ road markings to enhance the presence of the Club

Handed over for delivery

Mrs Whittle has provided funding to allow the continuation of a taxi Service that replaces the withdrawn Wormshill to Sittingbourne Post Bus.

 


 

 

Paulina Stockell

 

Details of Scheme

Status

Dean Street - Junction with Heath Road at one end past Forge Lane toward Tovil at the other, extend the existing 30mph speed limit

Handed over for delivery.  Road will be closed for two Sundays in addition to week day working.  Amey Consulting is arranging the road closures, with works expected to take place in May/June pending approval and media advertising of the closure

West Street, Hunton - Install 6 verge marker posts in the location as discussed with Donna Rixson and to act as an extension to the three previously installed.  To include isolated hedge cutting. 

Handed over for delivery. 

Sutton Valence Primary School - Ms Stockell has provided funding for an investigation into the provision of new gate and a proposed new access to the rear of the school, from the PROW.

 

 

Rob Bird

 

Details of Scheme

Status

Bower Lane, Fant – TRO (yellow lines)

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Cherry Orchard Way - TRO (yellow lines)

With Amey Consulting for implementation (TRO sealed).  Engineer has been advised a road space permit is being arranged and a gang sourced for out of hours working

Buckland Road -  TRO, removal of 1 residents parking bay outside no. 53 opposite no. 42 to improve access to driveways of properties and allow emergency vehicles to pass (C Reynolds of MBC)

With Amey Consulting for progression.  KCC Engineer has requested an update

Upper Fant Road – South west end of Upper Fant Road just before the bend leading into Hackney Road

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Rob Bird (continued)

 

Fant Lane outside Bower Grove School - Provide down-lighting at crossing point and warning sign for traffic coming round the bend from Tonbridge Road and on the roadway in both directions

Handed over for delivery.  No completion certificate has been issued.  Engineer to check site

Keswick Drive junction with Shearwater – Salt bin

Complete

Freshland Road – junction with Melford Drive – Salt bin

Complete

Stagshaw Close – TRO (single yellow lines and school Keep Clear)

With Amey Consulting for design and progression of the TRO in conjunction with Maidstone Borough Council Parking Team