CABINET

20 SEPTEMBER 2023

 

Reference from Overview and Scrutiny Committee – CIL Strategic Assessment & Spend Decision, following Call-In.

 

Timetable

Meeting

Date

Overview and Scrutiny Committee

15 August 2023

Cabinet

20 September 2023

 

 

Wards affected

All

 

Executive Summary

At its meeting on the 15 August 2023, the Overview and Scrutiny Committee (The Committee) considered the call-in request received in relation to the Cabinet’s decision on the CIL Strategic Assessment & Spend made on the 26 July 2023.

 

The Committee has referred the matter back to the Cabinet for re-consideration.

 

 

This report makes the following recommendation to the Cabinet: To

1.   Reconsider the issues around the Linton Crossroads Junction Improvement scheme, in particular concerning pedestrians and road safety, land delivery and the feasibility of delivering the project and consider whether there should be a claw-back mechanism; and

2.   Consider what action can be taken in conjunction with prospective future rounds of CIL bids, in bringing forward the Hart Street and Fountain Lane – Hermitage Lane Junctions.

 

 



Reference from Overview and Scrutiny Committee – CIL Strategic Assessment & Spend Decision, following Call-In.

 

1.   REASONS FOR RECOMMENDATION

 

1.1     At the Overview and Scrutiny (OSC) Meeting held on 15 August 2023, the call-in received for the Cabinet’s CIL Strategic Assessment & Spend decision was reviewed.

 

1.2     The (draft) Minute of the item’s consideration is shown below, which will be subject to approval at the 19 September 2023 OSC Meeting.

 

RECEIPT OF CALL-IN – RELEVANT PROCEDURE, CIL STRATEGIC ASSESSMENT & SPEND

 

The Principal Democratic Services Officer introduced the report and stated that the Committee was being asked to consider the call-in request received against the Cabinet decision made, which were shown respectively at Appendices 1 and 2 to the report. The options available to the Committee were outlined.

 

Councillors Naghi, Munford and English outlined their reasoning for calling-in the decision. The issues raised were that:

 

·         The Linton Crossroad Junction (LCR) was the second most dangerous in Kent and that the junction improvement should take place to improve safety and mitigate road congestion;

·         Safety was not discussed enough by the Cabinet in its deliberations, with the urgent update provided to the Cabinet at its July 2023 meeting referenced;

·         The Linton Crossroads Improvement scheme (the scheme) was part of the infrastructure delivery plan (IDP), within the adopted local plan (2017);

·         The funding had been collected for the scheme, which could be delivered by Kent County Council’s Highways department following engagement with and by that authority’s design and delivery teams; and

·         There was concern over the collection of monies that were not then used on road improvement schemes.

In referencing the Cabinet’s decision at appendix 2 to the report, it was stated that the scheme was ready for implementation whereas other schemes were not. The Planning, Infrastructure and Economic Development Policy Advisory Committee (PIED PAC) had supported allocating funding to the scheme and had recommended a time-delivery clause on the funding’s provision, to enable the funds to be returned should the scheme not be delivered by the infrastructure provider.

The Leader of the Council addressed the Committee to outline his reasoning for the decision and stated that:

 

·         The Cabinet had a lack of confidence in the scheme’s delivery, given the performance of KCC Highways and that the authority already held funds for other improvement schemes that had not been used;

·         The proposed LCR scheme was not currently ready for delivery;

·         KCC were consulting on a different Linton Crossroads improvement scheme at the time of the Cabinet’s decision, that was not the scheme bid for and would cost a different amount. It was unusual to make a decision on the matter when there was an ongoing public consultation;

·         The safety of the junction was important, but some of the incidents shown in the cluster map of the urgent update at appendix 3 to the report were outside of the proposed scheme area, and the improvements from the proposed scheme would be marginal; and

·         Other road improvement schemes could be progressed, with the Community Infrastructure Levy (CIL) process currently being reviewed.

The Cabinet Member for Communities, Leisure and Arts stated that it was the provision of funding, as opposed to the scheme itself that had been rejected. It was reiterated that other road improvements scheme were required, such as in Coxheath and the Fountain Lane improvement scheme that could be re-visited and developed by KCC.

 

In response to questions:

 

·         The Director of Regeneration and Place stated that the grant agreements between the Council and infrastructure providers would include delivery milestones. This would allow the funding to be returned and re-allocated if a scheme was not progressing. As the schemes submitted to the CIL bidding process were generally not well developed, only four had been recommended for funding approval; and

·         The Head of Development Management stated that they did not know if KCC highways and the landowners had had detailed discussions on the proposed scheme. KCC had only submitted the M20 Junction 7 Signalisation and Linton Crossroads schemes to the CIL bidding process and had stated that the latter was delivery ready. The considerations made in testing a scheme’s reasonableness were outlined, including delivery within five years.

KCC had indicated that the Fountain Lane junction improvement scheme did not achieve the cost benefit ratio required to progress the scheme, whereas the Linton Crossroads scheme does. KCC would be able to use compulsory purchase powers if required, as the highways authority. 

 

In response to comments, the Leader stated that:

 

·         The proposed scheme was not currently deliverable; the land purchases required could take a long time to finalise and the CIL funding could be directed to other schemes that were more deliverable;

·         Having met with KCC recently, a cost-benefit analysis had not taken place for the Linton Crossroads scheme as it was not a requirement given the schemes small size. Pre-application discussions were ongoing with the relevant landowners, but the lands availability was not confirmed;

·         The decision made gave the Council greater control of the CIL funds; as should the LCR scheme continue to be developed by KCC and become delivery ready, the funding could be provided. If an alternative scheme was delivery ready earlier, the funding could be directed to that scheme; and

·         The Cabinet would receive a report on the CIL process by November 2023, which the Committee able to conduct pre-decision scrutiny if it wished to.

During the discussion, several Committee Members stated that whilst the Fountain Lane junction required improvement, additional funding would be needed to progress the scheme, that it required property purchases, and had not been an option included within the Cabinet agenda papers. It was felt that the LCR scheme should take place to improve the safety of the junction, given the number of incidents at the location, its proximity to the local school and lack of pedestrian controls at the local bus stop. The PIED PAC’s support and recommendations on the matter were reiterated, alongside the consultant’s advice and that the junction improvement was within the Council’s IDP. The second scheme design being consulted on was stated to require the same funding allocation.

 

Some Members expressed concerns on the LCR scheme, as it differed to that being publicly consulted on and the land purchases required had not been agreed, which would take time. There were other schemes that could be progressed by KCC, with it stated that the Cabinet decision made allowing for greater control and flexibility in use of the CIL funding. There were questions raised on whether the design submitted would address the safety concerns at the site and the surrounding road network.

 

Overall, the Committee felt that the Cabinet should give further consideration to the LCR scheme, particularly on improving safety, the project’s feasibility including land delivery, and whether a time-restricted funding provision could be used.

 

RESOLVED: That the matter be referred back to the Cabinet to:

 

a.  Reconsider the issues around the Linton Crossroads Junction Improvement scheme, in particular concerning pedestrians and road safety, land delivery and the feasibility of delivering the project and consider whether there should be a claw-back mechanism; and

b.  Consider what action can be taken in conjunction with prospective future rounds of CIL bids, in bringing forward the Hart Street and Fountain Lane – Hermitage Lane Junctions.

 

 

2.   ALTERNATIVES CONSIDERED AND WHY NOT RECOMMENDED

 

Not applicable.

 

 

3.        REPORT APPENDICES

 

None.

 

 

4.        BACKGROUND PAPERS

 

(draft) Minutes of the Overview and Scrutiny Committee Meeting held on 15 August 2023: Your Councillors - Maidstone Borough Council