MAIDSTONE BOROUGH COUNCIL
CABINET MEMBER FOR COMMUNITY AND LEISURE SERVICES
REPORT OF THE ASSISTANT DIRECTOR FOR ENVIRONMENT AND REGULATORY SERVICES
Report prepared by Jason Taylor
Date Issued: 28 July 2011
1. MOTE PARK REGENERATION PROJECT – APPOINTMENT OF CONTRACTOR AND FINAL APPROVAL OF SCHEME
1.1 Issue for Decision
1.2
To
consider the appointment of the preferred contractor for the Mote Park
Regeneration Project and the final approval of the scheme.
1.3
Recommendation
of the Assistant Director of Environment and Regulatory Services.
1.4
That
the Cabinet Member accepts the tender submission and proceeds with Contractor A
(as identified in the exempt Appendix) as the Councils preferred contractor, to
implement the Mote Park Regeneration Project capital works as approved by The
Heritage Lottery Fund.
1.5
That
the final scheme for the Mote Park Regeneration Project capital construction works
as shown in Appendix A, be approved by the Cabinet Member and permission given
to progress.
1.6
That
delegated authority is given to the Assistant Director of Environment and
Regulatory Services to agree any design changes required during the
construction period, in consultation with the Cabinet Member, in order to keep
the project within budget, if unforeseen circumstances arise.
2.1 Appointment of Contractor
2.2
Following
the Cabinet Member for Leisure and Culture’s decision in October 2010 to “progress
to the implementation stage of the Mote Park Regeneration Project and the
issuing of the tender documents in January 2011 for the works”, the Council has
undertaken a tender process as detailed below :
2.3
The
procurement of a contractor to carry out the Capital works for the Mote Park
Regeneration Project was not subject to a full OJEU (Official Journal of
the European Union)
procurement
process, but was over the council’s threshold for a tender process to be
required.
2.4
A
restricted tendering process was used requiring a Pre Qualification Questionnaire
(PQQ) to select a short list of contractors to take part in the actual
invitation to tender process (ITT).
2.5
The
opportunity was advertised via a BIPS (BIP Solutions) Competitive Contract
Notice and entries in the IESE (Improvement Efficiency South East) Portal and
the Councils own website.
2.6
Some
fifty-two contractors submitted an expression of interest, and twenty-three completed
submissions were received by the deadline of 31st August 2011.
2.7
Following
evaluation by Council Officers seven contractors were selected to take part in
the full tendering stage and all of these returned submissions by the deadline
of April 1st 2011.
2.8
These
submissions were evaluated by a team of officers and the landscape architect
for the project.
2.9
All
bills of quantities were checked by a quantity surveyor for obvious errors and
general compliance.
2.10 The
responses were extensively analyzed based on the pre published criteria and a
quality/cost weighting of 60%/40% respectively. This included the overall
approach to the project, their plans, methods and team structure to deliver the
brief.
2.11 As a
result the four leading suppliers at this stage were invited for clarification
interview during the week beginning 18th April 2011. These were held
over two days and attended by Council Officers, the Landscape Architect and the
Quantity Surveyor assigned to the project.
2.12 Following the interview suppliers were re-scored against the agreed criteria and the quantity surveyor undertook a detailed check of the bill of quantities and identified a number of mathematical errors, these were notified to the suppliers and their scores adjusted accordingly. However, all of the bids came in over the agreed budget and although it was clear that by a process of value engineering the highest scoring contractor could deliver the project within budget, the Council was not comfortable signing off the project until it had a full bona fide submission within the budget.
2.13 A revised set of requirements were then agreed internally and with the Lottery. To ensure fairness a supplement to the ITT was issued to all seven original tenderers requesting a revision to the contract.
2.14 The revised bids were received on the 6th July 2011 and checked for uniformity. The original pre-interview quality scores were added to the revised price scores based on the pre published criteria and a quality/cost weighting of 60%/40% respectively.
2.15 The four contractors that submitted bids within the budget were invited for clarification interviews on the 14th July 2011.
2.16 Following the interview contractors were re-scored against the agreed quality criteria.
2.17 The
following table shows the final evaluated scores following the interviews and
written confirmation from the bidders of their revised contract values.
Supplier |
Price Score 40% |
Quality Score 60% |
Total Score 100% |
Supplier A |
39.5 |
49.4 |
88.9 |
Supplier B |
38.7 |
47.6 |
86.3 |
Supplier E |
39.8 |
46.2 |
86.0 |
Supplier G |
40.0 |
45.6 |
85.6 |
2.18 Each company had its own special expertise, however Supplier A was judged to have the best overall proposal in terms of project control and cost scoring the highest combined Price/Quality score.
2.19 It is
recommended that the Cabinet Member for Community and Leisure Services gives
authority to the Assistant Director for Environment and Regulatory Services to
approve Supplier A as the preferred supplier and award the works (subject to
contract). The work programe is to be completed by June 2012.
3
Approval
of Final Scheme and Permission to Progress
3.1
Following
considerable consultation with local people, the Friends of Mote Park and other
stakeholders a set of proposals was produced and submitted to the Heritage
Lottery Fund for the Stage 2 application in June 2010. Following approval by
the HLF further development to the plans has taken place to ensure that the
proposals are achievable financially and practically. These changes have been
minimal and the overall scheme remains unchanged.
3.2
The
Master Plan for the Construction Phase of the project can be seen in Appendix
A. As the more detailed plans are very large and bulky they have not been
included in this report, but are available from the Parks and Leisure
Department. The following is a summary of the works proposed in Project Capital
Construction Works:
3.3
Improved
pedestrian access, with new DDA compliant footpaths comprising an inner (around
the lake) and outer circuit, enabling safe wheelchair and pushchair access
throughout.
3.4
Works
to manage the outflow of the lake to reduce lake edge flooding.
3.5
Repair
of the lake crossing causeway with a natural reed bed treatment to prevent
erosion.
3.6
New
bridge construction in order to provide an accessible pedestrian route across
the lake.
3.7
Refurbishment
of Mote Avenue and School Lane car parks.
3.8
New
parking facilities via Willington Street entrance.
3.9
Installation
of electronically controlled gates to prevent unauthorised vehicular access in
the park.
3.10 Reconstruction
of the historic waterfall.
3.11 Construction
of a boathouse promenade and the relocation of the model boat club platform.
3.12 Restoration
works to the historic pavilion.
3.13 Information
points at the entrances and historic park features enhancing user’s knowledge
and interest of the park.
3.14 New way
finding signage throughout.
3.15 New and
refurbished park furniture, including litter bins, seating and cycle stands.
3.16 Security
improvements including the provision of additional CCTV cameras at key
locations agreed with the Police.
3.17 Fishing
swims, including some for anglers with disabilities.
3.18 Two
additional local park centers with play equipment (including facilities for
children with disabilities) and potential for catering facilities.
3.19 Improved
seating throughout, providing rest points in the park.
3.20 Improvements
to park entrances enabling safe access.
3.21 Kiosk
improvements including external cladding and internal improvements.
3.22 It is
recommended that the Cabinet Member approves and gives permission to progress
with the Capital Construction Works as shown in Appendix A.
4
Delegated
Authority to Assistant Director of Environment and Regulatory Services
4.1
It
is likely that during the construction phase of the Mote Park Regeneration
Project that it will be necessary to make minor design adjustments to maximize
resources and to keep the project within budget. It is recommended that
delegated authority is given to the Assistant Director of Environment and
Regulatory Services to agree these minor changes, as to report back to the
Cabinet Member for Community and Leisure Services would result in lengthy
delays to the project programme.
5 Alternative Action and why not Recommended
5.1
Alternative
action that could be taken by the Cabinet Member could be to choose an
alternative supplier to Supplier A. This is not recommended as it would go
against the tendering process carried out by officers and the scoring which
found Supplier A to offer the best overall proposal.
5.2
The
Cabinet Member could choose not to approve the final scheme for the Mote Park
Regeneration Project capital construction works as shown in Appendix A, and not
give permission to progress with the work. This is not recommended as the whole
scheme has been consulted on and agreed over several years by a large number of
park users and stakeholders, to change the plans would be going against what
has been agreed with these stakeholders.
5.3 The Cabinet Member could not agree to give delegated authority to the Assistant Director of Environment and Regulatory Services to agree any design changes required during the construction period, but this would likely result in delays to the programme because of the time that it would take to bring reports to the Cabinet Member to agree minor changes.
6 Impact on Corporate Objectives
6.1
Key
objectives of the Strategic Plan 2011 – 15 which the regeneration of Mote Park
will have a positive impact on are:
6.2
For
Maidstone to be a decent place to live and continues to be clean and attractive
environment for people who live and visit the borough.
7 Risk Management
7.1
There
is a risk that the Heritage Lottery Fund will not approve the Council’s choice
of supplier – this is seen as very unlikely as the HLF have already approved
the procurement process used by the Council to select a supplier.
7.2
There
could be a risk of the selected contractor not delivering the project – this is
seen as minimal as references have been sought showing that the selected
supplier has delivered projects of this type in the past and financial checks
agree that the supplier is financially capable of delivering this project.
Robust contract management arrangements have been put in place which will be
overseen by the Assistant Director for Environment and Regulatory Services.
7.3 If approval of the final scheme, permission to progress and delegated authority for the Assistant Director of Environment and Regulatory Services to agree any design changes is not given it is likely that there will be a delay in the overall programme. This in turn is likely to result in the works not being completed by the June 2012 deadline.
8
Other
Implications
8.1
1. Financial
|
X |
2. Staffing
|
X
|
3. Legal
|
X |
4. Equality Impact Needs Assessment
|
|
5. Environmental/Sustainable Development
|
X |
6. Community Safety
|
X |
7. Human Rights Act
|
|
8. Procurement
|
X |
9. Asset Management
|
X |
8.2 Financial – The Council has already committed to proceed with this project and the capital contribution along with the funding from the Heritage Lottery Fund for the project is in the budget programme.
8.3 Staffing - Two posts (Mote Park Project Manager and Mote Park Audience Development Officer) are funded by the project. No additional staff will be required.
8.4 Legal – A legal agreement will need to be produced between Maidstone Borough Council and the chosen supplier.
8.5 Environmental/Sustainable Development – All suppliers scored highly on the environmental impact and all have experience working in environmentally sensitive areas.
8.6
Procurement
– The procurement section have been involved in this decision, once a supplier
is chosen minimal input will be required from them.
8.7 Asset Management – The works included in the Mote Park Regeneration Project will improve the Councils asset and increase the value of Mote Park to users.
9 Relevant Documents
9.1
Appendices
9.2
Exempt
Appendix
- Identification of Contractors, Tender Report and Client Acceptance memo from
MBC Procurement Section.
Appendix B – Mote Park Restoration Project Master Plan.
10
Background
Documents
10.1
Tender
documentation produced by suppliers.
10.2
Scoring
documents.
10.3 Mote Park Regeneration Project Stage 1 and 2 Heritage Lottery Applications.
10.4 Cabinet Record of Decision, 22nd December 2010. Mote Park Improvement Project.
10.5
Cabinet
Member for Leisure and Culture Record of Decision, 5th November
2010. Progressing Mote Park Improvements Project
All of these documents are held in Maidstone House.
|
How to Comment Should you have any comments on the issue that is
being considered please contact either the relevant Officer or the Member
of the Executive who will be taking the decision. Cllr John A. Wilson Cabinet Member
for Community and Leisure Services Telephone:
01622 720989 E-mail:
JohnAWilson@maidstone.gov.uk Jason Taylor Parks
and Leisure Manager Telephone:
01622 602753 E-mail:
JasonTaylor@maidstone.gov.uk