The
Committee considered the report of the Head of Planning and
Development.
Mr
Coveney, an objector, addressed the meeting remotely.
Prior
to the debate, Councillor Perry said that he was a Member of
Staplehurst Parish Council. However, he
had not participated in the Parish Council’s discussions on
the application and intended to speak and vote.
RESOLVED:
1. That permission
be granted subject to the conditions and informative set out in the
report, with:
The amendment of condition 3 (External Materials) to emphasise that
the materials must match the existing; and
An additional condition requiring the installation of
renewables.
2. That the Head
of Planning and Development be given delegated powers to finalise
the wording of the amended and additional conditions.
Voting: 12
– For 0 –
Against 0
– Abstentions