Risk Management Process Refresh

Meeting: 24/06/2015 - Policy and Resources Committee (Item 19)

19 Risk Management Process Refresh pdf icon PDF 352 KB

Decision:

DECISION MADE:

 

1)  That the Committee approved moving ahead with the process to build and maintain a comprehensive risk register as set in Section 4 and Appendix 1 to the report of the Director of Environment and Shared Services;

2)  That delegated authority is given to the Chief Executive (as the accountable officer) to take operational decisions necessary for the ongoing maintenance and review of the risk register; and

3)  That the Committee receive and consider bi-annual summary risk register reports for review, scheduled for January and July.


Minutes:

The Head of Audit Partnership presented his report on the Risk Management Process Refresh.

 

Members noted that the proposed changes to the risk management process were driven by a review that had been undertaken by Mid Kent Audit of risk management processes at another authority.

 

RESOLVED:

 

1)  That the Committee approved moving ahead with the process to build and maintain a comprehensive risk register as set in Section 4 and Appendix 1 to the report of the Director of Environment and Shared Services;

2)  That delegated authority is given to the Chief Executive (as the accountable officer) to take operational decisions necessary for the ongoing maintenance and review of the risk register; and

3)  That the Committee receive and consider bi-annual summary risk register reports for review, scheduled for January and July.

Voting  13 – For  0 – Against  0 - Abstain