The
Committee considered the report and the urgent update report of the
Head of Development Management.
In
introducing the application, the Principal Planning Officer advised
the Committee that following a conversation with the agent for the
applicant earlier that day, delegated powers were sought to check
and correct the plans list if Members were minded to grant permission.
Councillor Fort of Leeds Parish Council and Mr Blythin, agent
for the applicant, addressed the meeting.
RESOLVED: That consideration of this
application be deferred for one cycle to enable Members to compare
the revised submission with the originally submitted scheme for 354
PV panels including the kilowatt hours and SAP ratings.
Voting: 13
– For 0 –
Against 0
– Abstentions