Installation of photovoltaic technology

Meeting: 24/06/2015 - Policy and Resources Committee (Item 20)

20 Installing Renewable Energy Technology pdf icon PDF 104 KB

Additional documents:

Decision:

DECISION MADE:

1)  That the purchase, installation and operation of photovoltaic technology  be approved on the following buildings with the Council’s estate:-

  (a)  Lockmeadow Market Hall – 50kw Array
  (b)  Vinters Park Crematorium – 10kw and 4kw Array
  (c)  Magnolia House – 24kw Array

2)  That the purchase of renewably generated electricity from a third party at Maidstone House be approved;

3)  That a budget of £125,000 to implement the recommendations be 
 approved;

4)  That delegated authority be given to the Commercial Projects Manager to spend the budget and enter into the appropriate contracts to implement the recommendations;

5)  That delegated authority be given to the Commercial Projects Manager to obtain the necessary permissions and licences to implement the recommendations including the registration for Feed in Tariff; sale, export or purchase of electricity; and appropriate agreements with the District Network Operator; and to assign those permissions and licences as appropriate;

6)  That the progression of the work towards entering into an assignable power purchase agreement with a generator of renewable energy be approved and the trial for Maidstone House and the Gateway be agreed.


 

Minutes:

The Commercial Projects Manager presented his report on the installation of renewable energy technology.

Members were advised that solar panels had been installed at the Council’s depot as a trial in March this year and had exceeded all expectations in terms of projected energy savings.

Following this success, a feasibility study of some of the Council’s other sites was undertaken and five sites were identified.  This would enable a wider take up of renewable energy across the Council’s estate, and the wider Borough.

RESOLVED:

1)  That the purchase, installation and operation of photovoltaic technology be approved on the following buildings with the Council’s estate:-

  (a)  Lockmeadow Market Hall – 50kw Array
  (b)  Vinters Park Crematorium – 10kw and 4kw Array
  (c)  Magnolia House – 24kw Array

2)  That the purchase of renewably generated electricity from a third party at Maidstone House be approved;

3)  That a budget of £125,000 to implement the recommendations be 
 approved;

4)  That delegated authority be given to the Commercial Projects Manager to spend the budget and enter into the appropriate contracts to implement the recommendations;

5)  That delegated authority be given to the Commercial Projects Manager to obtain the necessary permissions and licences to implement the recommendations including the registration for Feed in Tariff; sale, export or purchase of electricity; and appropriate agreements with the District Network Operator; and to assign those permissions and licences as appropriate; and

6)  That the progression of the work towards entering into an assignable power purchase agreement with a generator of renewable energy be approved and the trial for Maidstone House and the Gateway be agreed.

Voting:    For – 14  Against – 0  Abstain - 0