Jason Taylor, the Parks and Leisure Services
Manager, presented an update report to advise the Committee of the
progress of the play area improvement programme.
It was stated that:
·
In 2009 a point system was brought in to evaluate the standards of
play areas across the borough.
·
Research conducted in 2012 identified that best use of resources
would be to create a network of play areas, with residents able to
reach their nearest facility within a 12 minute walk.
·
The Play Area Strategy was produced, and funding for improvement
agreed in 2015. Improvements would be rolled out over a three year
period, with the first new equipment scheduled for installation in
2016.
In response to questions the following was
explained:
·
Play areas which were not improved would be offered to the
community or closed. Areas that were closed would have equipment
removed and remain as open or green space.
·
The Play Area Strategy had not been agreed and so the proposed
improvements for year one would be carried and a redrafted strategy
would come to Committee.
RESOLVED: That the update
provided on the Play Area Capital Improvement Programme be
noted.
For – 9 Against – 0
Abstain - 0